Attachment 1d - ICRA.pdf
PDF 448 KB Posted
- Attached to
- PIMC - Fire Alarm Replacement Services
- Solicitation number
- IHS1530891
About this file
This document is an Infection Control Risk Assessment and Permit form used to evaluate and control infection risks during construction or maintenance work in healthcare facilities.
The form establishes a four-tier classification system (Types A through D) based on project scope and dust generation, combined with four risk group categories (Low, Medium, Medium High, and Highest) based on work location. Type A projects involve inspection and non-invasive activities with minimal dust, while Type D encompasses major demolition and new construction requiring consecutive work shifts. Risk groups range from office and storage areas (Low Risk) to operating rooms, intensive care units, and sterile compounding areas (Highest Risk). The form requires users to determine the appropriate class level (I through IV) by cross-referencing project type with risk group location, which then dictates the specific infection control protocols required.
Each class level specifies detailed control measures: Class I requires minimizing dust and replacing displaced ceiling tiles; Class II mandates water misting, sealing doors and vents, HVAC isolation, and HEPA vacuuming; Class III adds negative air pressure maintenance and anteroom requirements; and Class IV represents the most stringent protocols, including mandatory shoe covers, protective coveralls, HEPA filtration, and Infection Control inspection before barrier removal. The form requires identification of adjacent high-risk areas and specifies whether the permit must be posted onsite, with signature lines for both the permit requester and Infection Control authorization.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Price Schedule_v2.xlsx | XLSX spreadsheet | |
| QnA_v2.docx | DOCX document | |
| QnA.docx | DOCX document | |
| Attachment 1c - Floorplans Labeled.pdf | ||
| Attachment 1e - Points List.pdf | ||
| Attachment 3 - Wage Determination.pdf | ||
| Attachment 2 - Price Schedule.xlsx | XLSX spreadsheet | |
| Attachment 1b - FACP Report.pdf | ||
| Synopsis.pdf | ||
| Attachment 1a - Campus Buildings.pdf | ||
| Attachment 4 - IHS Indian Economic Enterprise Representation form.pdf | ||
| Attachment 1 - Statement of Work.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
Infection Control Risk Assessment and Permit
Work Location/Description:
Start Date End Date
Project Manager Name / Phone Number :
TYPE A:
TYPE B:
TYPE C:
TYPE D:
Low Risk
Medium Risk
High Risk
Highest Risk
Identify Any Adjacent High Risk Areas:
Above Below Front Behind Lateral NA
CLASS 1 1 Minimize raising dust from construction operations 2 Immediately replace any ceiling tile displaced for visual inspection.
CLASS II 1 Minimize raising dust by water misting work surfaces to control dust while cutting.
2 Seal unused doors with duct tape.
3 Block off and seal air vents with plastic or impervious material.
4 Wipe surfaces with cleaner/disinfectant.
5 Isolate HVAC system in areas where work is being performed
6 Contain construction waste prior to transport in tightly covered containers.
7 Wet mop and/or vacuum with HEPA-filtered vacuum prior to leaving area.
8 Remove critical barrier(s) carefully to minimize spread of dirt/debris.
9 Use hospital-approved disinfectant 10 Place dust mat at entrance and exit of work area.
11 Restore HVAC when work completed.
CLASS III 1 Isolate HVAC system in area of work to prevent contamination of the duct system.
2 Complete all critical barriers or implement control cube or other method prior to work.
3 Maintain negative air pressure within work environment with HEPA-equipment.
4 Do not remove barriers from site until completed project is checked by infection Control.
5 Environmental Services thoroughly cleans.
6 Vacuum work with HEPA-filtered vacuum.
7 Wet mop with hospital approved cleaner/disinfectant.
8 Remove barrier materials carefully to minimize spread of dirt/debris.
9 Contain construction waste prior to transport in tightly covered containers.
10 Cover transport receptacles or carts.
11 Tape coverings.
12 When complete, restore HVAC system where work was performed.
CLASS IV 1 Isolate HVAC system in work area to prevent contamination of duct system.
2 Complete all critical barriers or use control cube method prior to start of construction.
3 Maintain negative air pressure within work site – utilizing HEPA-equipped air filtration units.
4 Seal holes, pipes, conduits, and punctures.
5 Construct anteroom and require all personnel to pass through this room so they can be vacuumed off using a HEPA vacuum cleaner before leaving work site, or wear protective paper coveralls (bunny suit) that is removed each time leaving the work site.
6 Require all personnel entering work site to wear shoe covers.
7 Do not remove barriers from work site until project is checked by Infection Control; and is thoroughly cleaned by environmental services.
8 Vacuum work area with HEPA-filtered vacuums.
9 Wet mop with hospital–approved disinfectant.
10 Remove barrier(s) carefully to minimize spread of dirt/debris associated with construction.
11 Contain construction waste prior to transport in tightly covered containers.
12 Cover transport receptacles or cart.
13 Tape coverings.
14 At completion, restore HVAC system where work was performed.
Is permit required to be posted onsite? _________YES _________NO
Permit Requested By Signature / Date Infection Control Signature / Date
2 | P a g e
Class Determination
RISK GROUP TYPE A TYPE B TYPE C TYPE D
LOW Risk Class 1 Class II Class II Class III/IV
MEDIUM Risk Class 1 Class II Class III Class IV
HIGH Risk Class 1 Class II Class III/IV Class IV
HIGHEST Risk Class II Class III/IV Class III/IV Class IV
Risk Groups
Low Risk
Office areas, Maintenance, Housekeeping, Storage Areas, Stairwells, Storage buildings, Warehouse, Library, Meeting Rooms, Staff Lounges, Empty Patient Rooms
Medium Risk Clinical Areas (Not Otherwise Listed), Outpatient Services (Not Otherwise Listed), Physical Therapy, Radiology, Dental, Behavioral Health, Same Day Surgery, Cafeteria, Snack Bar
Medium High Risk
Emergency Room, Laboratories, Pharmacy, Occupied Patient Rooms, Inpatient Departments, Food Preparation Areas, Nursery, PACU, Above Ceiling Work in Open Interstitial Space within 100 Linear Feet of Group III/IV, Labor and Delivery, Medication Rooms.
Highest Risk Sterile Areas, Segregated Compound Area (IV Room), Containment Segregated Compounding Area (Chemo), Airborne Isolation, Sterile Supply, Operating Rooms, C- Section Operating Rooms, Endoscopy, Intensive Care, Oncology Infusion.
Project Type
TYPE A Inspection and non-invasive activities
Removal of ceiling tiles for visual inspection only ( limited to one tile per 50 square feet)
Painting, not sanding
Wallcovering, electrical trim work, minor plumbing, and activities that do not general dust or require cutting of walls or access to ceiling other than for visual inspection
TYPE B Small-scale, short duration activities that create minimal dust
Installation of telephone and computer cabling
Access to chase spaces
Cutting of walls or ceiling where dust migration can be controlled
TYPE C Work that generates moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies
Sanding of walls for painting or wall coverings
Removal of floor covering, ceiling tiles, and case work
New wall construction
Minor duct work or electrical work above ceiling
Major cabling activities
Activities that cannot be completed in a single work shift
TYPE D Major demolition and construction projects
Activities that require consecutive work shifts
Required heavy demolition or removal of a complete cabling system
New Construction
| Untitled |
| Untitled |
| Untitled |
| Work LocationDescription: |
| Start Date: |
| End Date: |
| Project Manager Name Phone Number Row1: |
| fill_11: |
| fill_12: |
| fill_6: |
| CLASS 1: |
| 1 Minimize raising dust from construction operations 2 Immediately replace any ceiling tile displaced for visual inspection: |
| CLASS II: |
| CLASS III: |
| CLASS IV: |
| YES: |
| NO: |
| undefined: |
| RISK GROUP: |
| TYPE A: |
| TYPE B: |
| TYPE C: |
| TYPE D: |
| LOW Risk: |
| Class 1: |
| Class II: |
| Class II_2: |
| Class IIIIV: |
| Class 1_2: |
| Class II_3: |
| Class III: |
| Class IV: |
| HIGH Risk: |
| Class 1_3: |
| Class II_4: |
| Class IV_2: |
| Class II_5: |
| Class IIIIV_3: |
| Class IIIIV_4: |
| Class IV_3: |
| Low Risk: |
| Medium Risk: |
| Medium High Risk: |
| Highest Risk: |
| TYPE A_2: |
| TYPE B_2: |
| TYPE C_2: |
| TYPE D_2: |
| 2 P a g e: |
| Text1: |
| Check Box9: Off |
| Check Box10: Off |
| Check Box11: Off |
| Check Box12: Off |
| Check Box13: Off |
| Check Box14: Off |
| Check Box15: Off |
| Check Box16: Off |
| Check Box17: Off |
| Check Box5: Off |
| Check Box18: Off |
| Check Box100: Off |
| Check Box98: Off |
| Check Box99: Off |
| Check Box97: Off |
| Check Box96: Off |
| Check Box95: Off |
| Check Box94: Off |
| Check Box93: Off |
| Check Box92: Off |
| Check Box91: Off |
| Check Box90: Off |
| Check Box89: Off |
| Check Box87: Off |
| Check Box86: Off |
| Check box85: Off |
| Check Box84: Off |
| Check Box83: Off |
| Check Box82: Off |
| Check Box81: Off |
| Check Box80: Off |
| Check Box79: Off |
| Check Box78: Off |
| Check Box77: Off |
| Check Box76: Off |
| Check Box75: Off |
| Check Box74: Off |
| Check Box73: Off |
| Check Box72: Off |
| 71: |
| Check Box70: Off |
| Check Box69: Off |
| Check Box68: Off |
| Check Box67: Off |
| Check Box66: Off |