Attachment 16 - Government Response to Questions - Virtual Site Visit.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Optimized Remediation Contract at McConnell Air Force Base, KS - Request for Proposals
Solicitation number
FA890323R0032
Issued by

View the file

Other files

File Type Posted
Solicitation Amendment FA890323R00320002 SF 30.pdf PDF
Attachment 1 - McConnell AFB ORC PWS Dated 13 July 2023.pdf PDF
Attachment 11 - McConnell AFB ORC Final SubCLIN Structure Rv3.xlsx XLSX spreadsheet
Attachment L-2_Past Performance Questionnaire.docx DOCX document
McConnell ORC RFP QA Answers.xlsx XLSX spreadsheet
Solicitation Amendment - FA890323R00320002.pdf PDF
Solicitation Section L - Instructions Conditions and Notices to Offerors.pdf PDF
Solicitation Amendment FA890323R00320001 SF 30.pdf PDF
Solicitation Amendment - FA890323R00320001.pdf PDF
Attachment L-1_Past Performance Information.docx DOCX document
Attachment M-1_ORC Relevancy Matrix.pdf PDF
Attachment 6 - Compliance With Contract Insurance.pdf PDF
Solicitation Section M - Evaluation Factors for Award.pdf PDF
Attachment 5 - Enclosure 3 - Community Involvement Plan Outline.pdf PDF
Attachment 2- Base Support Letter Dated 7 June 2023.pdf PDF
Attachment 4 - Enclosures 2A and 2B.pdf PDF
Q and A Template.xlsx XLSX spreadsheet
Attachment 15 - Interim Guidance on 1-4 Dioxane.pdf PDF
Solicitation Section L - Instructions Conditions and Notices to Offerors.pdf PDF
Attachment 11 - McConnell AFB ORC Final SubCLIN Structure.xlsx XLSX spreadsheet
Attachment 7 - Internal Confidentiality Agreement.pdf PDF
Attachment 1 - McConnell AFB ORC PWS Dated 11 May 2023.pdf PDF
Attachment 3 - Enclosure 1 - ORC Acronyms and Definitions.pdf PDF
Attachment 13 - CPSMR Template 25 AUG 2019.docx DOCX document
Solicitation Document - FA890323R0032.pdf PDF
Attachment L-4_Sample Client Authorization Letter.docx DOCX document
Attachment 8 - Delinquent Tax or Felony Conviction.pdf PDF
Attachment L-2_Past Performance Questionnaire.docx DOCX document
Attachment 14 - AFCEC Chemistry Data Quality Fact Sheet 01 APR 2020.pdf PDF
Attachment 12 - Wage Determination 2015-5341 27 DEC 2022.pdf PDF
Attachment 9 - Telecommunications Representation.pdf PDF
Attachment 10 - DFARS 252.204-7019 and DFARS 252.204-7020.pdf PDF
Attachment L-3_Consent Letter.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Attachment 16

SYNOPSIS QUESTIONS / RESPONSES

Optimized Remdiation Contract at McConnell Air Force Base, Kansas Project Numbers: PRQE20XX7917, and PRQZ20XX7811 Qstn # RFP REFERENCE CONTRACTOR QUESTIONS

ANSWERS BY GOV'T

1PWS Section 1.1 paragraph 3It is stated that RCRA permit dated 8 August 2007 is up for renewal. Is the renewal included in the scope for this ORC?NO
2Site FT006The performance objective is SC in PWS Table 1. Please provide requirements for SC. How many years and at what frequency of groundwater sampling (annual, seminannual or quarterly) results below clean up goals would be required to demonstrate SC?Reference Basewide GM Sampling Plan, Revision 2 or 3. Revision 3 is still pre-draft.
3Site SS014PWS Table 1 shows performance objective as RA-O through the duration of the POP. What is POP for this site? Virtual site visit slides show performance objective as RA-O for 5 years. It was indicated by Mr. Knight that the site contamination is expected to be cleaned up in 5 years, i.e. COC concentrations below remedial goals achieved. Would the AF extend POP for this site beyond 5 years if COC concentrations are still above remedial goals after 5 years?Reference PWS for this information

Yes

4Site SS014Virtual site visit slides show performance objective as RA-O for 5 years. It was indicated by Mr. Knight that the site contamination is expected to be cleaned up in 5 years, i.e. COC concentrations below remedial goals achieved. Would the AF issue a modification to extend POP for this site beyond 5 years if COC concentrations are still above remedial goals after 5 years?Reference PWS for this information
5FT007PWS Table 1 shows performance objective as RIP and RA-O through the duration of the POP. The virtual site visit slides 60-61 have Site Closeout at the top of the slide. What is the purpose of labeling some of the slides as SC at the top. This is the case for several other sites. Please clarify if that is a typo or if AF is expecting SC for this site and other RA-O sites?Wrong version of slide deck was inadvertantly uploaded. Title changed but not the pertinent information.
6LTM Sites LF010, LF033, ZZ047, ZZ048, ZZ049PWS Table 1 shows performance objectives as LTM with Institutional Controls. Would the contractor be responsible for maintaining (e.g. mowing, repairs) the landfill covers?No, mowing is not needed.
7BasewideWhat standard has been used by KDHE and/or EPA for the number of consecutive sampling events or time duration below the cleanup level to achieve site closeout or response complete?One year (4 consecutive events)
8BasewideDo changes to the current groundwater monitoring program for each site require a permit modification? Or can the network locations or frequency by revised via the periodic monitoring reports?No permit changes are required. However, they can make recommendations within reports and to the regulators as part of the periodic update meetings. If the regulators agree, changes can be made to the GWMP. Meetings to regulators are typically via TEAMS.
9Section 6.2Are the AF document review durations shown in the table in Section 6.2 cumulative? Or is the 120 day review time shown for a document requiring coordination/signature from the installation inclusive of AF and Legal Review?Depends on the nature of document. These review times are sequential not concurrent. For a highly complex document leading to a Decision, up to one year of review could potentially be involved.
10Section 6.2Please clarify which documents or document types require coordination/signature from the installation and/or CZ.Any document making a Decision, needs to be reviewed by CZTE and JAOE. i.e., DD, RFA, CMS, FS, RFI and RI
11Draft PWS 1.3.2 (i)How many sites will the RPM provide analytical data, new GWMW details, and current plume maps for that are not included in the ORC?14 sites
12Draft PWS 1.3.2How many GWMW's exist at sites not included in this ORC?144 with a potentially additional 22
131.3.2 (m)Will a separate CLIN be provided for the base background metals study?See SubCLIN Structure - CLIN0010
141.3.2 (m)Will additional sampling be required to update the base background study?Not necessarily.
151.3.2 (m)Will a statistical analysis be required to update the base metals background study?Yes
16Draft PWSWill a synoptic gauging event be required for the base?There is an annual event for the Annual GW Flow Map
17Draft PWS 8.1Does a baseline CSM exist for the site?The Contractor will be required to develop their own baseline CSM based on available data and then update per PWS requirements.
18Draft PWS 1.2.7.1.2What computer model files exist for 3D CSMs at the various sites? Can the government provide those files to the contractor on award?None exist in 3D but the most recent CSM is available in the AR.
19Draft PWS 1.3.2 (g)How is IDW suspected to be contaminated with PFAS stored/staged and handled on the base? Will the contractor be required to cover costs for storing and handling PFAS contaminated waste at the base?At the present time, liquid IDW impacted by PFAS is stored in contractor provided drums, totes, or tanks. Most contractors have been using the contractor equipment laydown yard to store soil and GW IDW. Liquid IDW is treated on-site by the contractor using a contractor supplied treatment system (usually a combination GAC/resin system), afterwhich it is analyzed for PFAS, then if it meets City of Wichita discharge standards, contractor personnel disposed of the IDW in the sanitary sewer. Before disposal can occur, a discharge permit is required from the City of Wichita Water Department ($100/permit/discharge). Disposal of liquid IDW into the sanitary sewer must be cooordinated with the MAFB Stormwater Manager. Soils impacted by PFAS are stored in contractor provided drums and/or roll-offs, usually at the equipment laydown yard. Impacted soils are disposed of by the contractor at a landfill (currently Plumb Thicket) approved to take PFAS impacted soils. Note: waste disposal must be coordinated through the MAFB Hazardous Waste Office. Waste disposal documentation (manifest, disposal tickets, waste characterization analytical results, etc.) is submitted to the MAFB Hazardous Waste Office. McConnell AFB is the waste generator.
20Draft PWS 8.2 Table 2Can the government provide level of effort is anticipated for the contactor for transition or completion of the Groundwater Sampling, PFAS RI, RFI, and McConnel PBR listed in table 2?The ORC contractor will not be responsible for the PFAS RI. Refer to the Sampling Transition Table.
21Draft PWSIs the contractor required to place a mobile office trailer on site?No, Prerogative of the contactor.
22Draft PWSIf conditional SC for contaminants other than PFAS is not accepted by KDHE how will that impact the ORC?SC will not be achieved.
23Sec 1.3.1 Table 1Comparison of the 2022 PWS and the 16 March 2023 PWS showed many of the performance objectives deleted "in accordance with the approved ROD/DD. Did these site fail to develop ROD/DD?Please refer to most recent version of PWS. All RODs/DDs are on the AR for reference.
24Virtual Site VisitDuring the virtual site visit ZZ052 was described as being below EPA and KDHE screening levels and that the performance objective might change. Please confirm.PO is Decision Document.
25Virtual Site VisitSS003 was described as having a Final VI workplan. Does TU546 also have an approved VI workplan?No
26Sec 1.3.1 Table 1The performance standard for the Community Involvemnt Plan includes approval by the USACE. Is this correct?AF approval is all that is needed.