Attachment 15 - SABER SEED Bid Schedule.xlsx
XLSX spreadsheet 542 KB Posted
- Attached to
- SABER IDIQ - Dover AFB Federal contract opportunity
- Solicitation number
- FA449725R0010
About this file
This file is a detailed Construction Cost Estimate spreadsheet for the SABER SEED Project located at Dover Air Force Base, Delaware. The spreadsheet is a comprehensive bid schedule template organized by 50 Construction Specifications Institute (CSI) divisions, designed to help contractors systematically break down and estimate project costs across different construction categories such as general requirements, existing conditions, concrete work, masonry, metals, electrical, HVAC, plumbing, and other technical divisions.
The spreadsheet provides instructions for contractors to complete cost estimates, allowing them to input labor, material, and total costs for each division. It includes sections for overhead, profit percentages for both prime and subcontractors, and a summary page that automatically calculates totals. The document is specifically tied to Contract Line Item Number (CLIN) 0010, which covers design and construction work to renovate B600 restrooms, including HVAC, electrical, and interior work. While the current spreadsheet shows placeholder values of zero, it is structured to enable detailed cost estimation across all major construction categories.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions Use the information from the prefilled division sheets below to complete the 50 Divisions Cost Estimate CSI* Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab. Please note that on the summary page there is a place to fill in overhead and profit percentages for both the prime and the subcontractor that will self-populate the summary page and all the division tabs.
Exceptions:
(1) if each subcontractor has a different overhead and profit rates than the percentage placed on the summary page, an adjustment will have to be made to that specific division page. The spreadsheet will still calculate correctly.
(2) If the prime is self-performing the work for that division then the profit and overhead will need to be zeroed for that particular division, because the primes overhead and profit is already captured on the summary page.
The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs except for the few exceptions listed above.
Divisions 1, 2, and 3 show sample inputs to illustrate how the spreadsheet works.
* CSI = Construction Specifications Institute
&"Verdana,Bold"Construction Cost Estimate
&P of &N
Summary BID SCHEDULE Date:
COMPANY
| PROJECT | ||||
| SABER SEED Project | CLIN: 0010 - Includes all Design and Construction work required to renovate the B600 restrooms to include HVAC, Electrical, and Interiors as specified in the Statement of work. | |||
| LOCATION | PROJECT NO. | 1122143 | ||
| DOVER AIR FORCE BASE, DE | ||||
| DIVISION | DESCRIPTION | % by | ||
| Division | Division Total |
| DIVISION 01 | GENERAL REQUIREMENTS | ERROR:#DIV/0! | - 0 | |
| DIVISION 02 | EXISTING CONDITIONS | ERROR:#DIV/0! | - 0 | |
| DIVISION 03 | CONCRETE WORK | ERROR:#DIV/0! | - 0 | FILL IN AS REQUIRED (this will link to the entire document) |
davisjam: davisjam:
Percentages listed are place fillers. Please complete as required
| DIVISION 04 | MASONRY | ERROR:#DIV/0! | - 0 | ||
| DIVISION 05 | METALS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 06 | WOOD, PLASTICS AND COMPOSITES | ERROR:#DIV/0! | - 0 | GC Overhead | |
| DIVISION 07 | THERMAL AND MOISTURE PROTECTION | ERROR:#DIV/0! | - 0 | GC Profit | |
| DIVISION 08 | OPENINGS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 09 | FINISHES | ERROR:#DIV/0! | - 0 | ||
| DIVISION 10 | SPECIALTIES | ERROR:#DIV/0! | - 0 | ||
| DIVISION 11 | EQUIPMENT | ERROR:#DIV/0! | - 0 | Risk/Bonding | |
| DIVISION 12 | FURNISHINGS | ERROR:#DIV/0! | - 0 | Design | |
| DIVISION 13 | SPECIAL CONSTRUCTION | ERROR:#DIV/0! | - 0 | This spreadsheet contains many formulas... please save a copy prior to editing in case you make a mistake. All shaded areas are either linked or contain formulas | |
| DIVISION 14 | CONVEYING EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 15 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 16 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 20 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 21 | FIRE SUPRESSION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 22 | PLUMBING | ERROR:#DIV/0! | - 0 | 2 | |
| DIVISION 23 | HEATING, VENTILATING AND A/C | ERROR:#DIV/0! | - 0 | 2 | |
| DIVISION 24 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 25 | INTEGRATED AUTOMATION | ERROR:#DIV/0! | - 0 | 0 | |
| DIVISION 26 | ELECTRICAL | ERROR:#DIV/0! | - 0 | ||
| DIVISION 27 | COMMUNICATIONS | ERROR:#DIV/0! | - 0 | Select Area Cost Factor Type: | |
| DIVISION 28 | ELECTRONIC SAFETY AND SECURITY | ERROR:#DIV/0! | - 0 | ||
| DIVISION 29 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 30 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 31 | EARTHWORK | ERROR:#DIV/0! | - 0 | ||
| DIVISION 32 | EXTERIOR IMPROVEMENTS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 33 | UTILITIES | ERROR:#DIV/0! | - 0 | ||
| DIVISION 34 | TRANSPORTATION | ERROR:#DIV/0! | - 0 | ||
| ERROR:#DIV/0! | - 0 | ||||
| DIVISION 36 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 37 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 38 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 39 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| DIVISION 46 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 47 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| ERROR:#DIV/0! | - 0 | ||||
| DIVISION 49 | RESERVED | ERROR:#DIV/0! | - 0 |
HARD COST TOTAL ERROR:#DIV/0! - 0
| PRIME GENERAL CONTRACT OFFICE OVERHEAD (Fill in%) | 0% | - 0 |
| SUBTOTAL | - 0 | |
| PRIME GENERAL CONTRACTOR'S PROFIT(Fill in%) | 0% | - 0 |
| SUBTOTAL | - 0 | |
| Design | 0.00% | - 0 |
| SUBTOTAL | - 0 | |
| BUILDER'S RISK / PERFORMANCE BONDS (Fill in%) | 0.0% | - 0 |
| CONTRACT TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Sustainment Repair/Const ACF Already Factored
Div1
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | EQUIPMENT | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| GENERAL REQUIREMENTS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | ||
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| - 0 | |||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div2
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXISTING CONDITIONS |
| - 0 | ||
| - 0 | - 0 | |
| - 0 | - 0 | - 0 |
| - 0 | |||
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| 0.00% | |||
| - 0 |
TOTAL $ - 0
&"Verdana,Bold"Construction Cost Estimate
Div3
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONCRETE WORK | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div4
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| MASONRY | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div5
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| METALS |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div6
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| WOOD, PLASTICS AND COMPOSITES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div7
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| THERMAL AND MOISTURE PROTECTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div8
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| OPENINGS |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | |||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div9
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FINISHES |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div10
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIALTIES |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div11
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div12
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FURNISHINGS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div13
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIAL CONSTRUCTION |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | |||
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div14
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONVEYING EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div15
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div16
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div20
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div21
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FIRE SUPRESSION |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | |||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div22
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PLUMBING |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div23
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| HEATING, VENTILATING AND A/C |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | |||
| 0.00% | - 0 | ||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div24
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| 0.00% | - 0 | ||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div25
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| INTEGRATED AUTOMATION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div26
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRICAL |
- 0 - 0 - 0
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| - 0 | |||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div27
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| COMMUNICATIONS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div28
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRONIC SAFETY AND SECURITY | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div29
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div30
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div31
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EARTHWORK |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| - 0 | |||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div32
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | FJXT 240013 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXTERIOR IMPROVEMENTS |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | ||
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 |
| SUBTOTAL | - 0 | ||
| - 0 | |||
| - 0 | |||
| - 0 | |||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div33
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| UTILITIES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div34
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| TRANSPORTATION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div35
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div36
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div37
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div38
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div39
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div40
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div41
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div42
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | - 0 | ||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div43
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div44
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div45
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div46
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div47
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div48
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div49
| BID SCHEDULE | DATE | |||
| 31-Dec-99 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| SABER SEED Project | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 1,122,143.00 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | |||||||
| TOTAL LABOR/MATERIALS | - 0 | ||||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
File details come from the government source that posted it. Updated .