This document is an Infection Control Risk Assessment for a construction project at a Department of Veterans Affairs facility in Hines, Illinois. The project involves renovations to portions of the first and second floors for new EHRM Training and Administrative space under solicitation number 36C77622B0050. The assessment classifies the construction activities into different risk groups based on dust levels and scope of work, and outlines infection control actions required of contractors based on the determined project class. Class I projects require basic precautions while Class IV projects, involving major demolition and construction, mandate the most stringent controls such as negative pressure barriers, HEPA vacuuming of personnel, and multiple terminal cleanings. Signatures from the contractor, project planner, supervisor, and infection control team are needed approving the assessment before commencing any renovation work.

View the file

Other files

File Type Posted
36C77622B0050 0004.docx DOCX document
36C77622B0050 0003.docx DOCX document
36C77622B0050 0002.pdf PDF
36C77622B0050 0001.zip ZIP file
Attachment 10 - Interim Life Safety Measures (ILSM) 02.pdf PDF
Attachment 19 - Hines VA Campus Site Plan.pdf PDF
Attachment 15 - No Smoking Policy 10-1-19.pdf PDF
Attachment 1 - EHRM Upgrade - Phase 2 Construction Drawings - Part 1.pdf PDF
Attachment 8 - Above Ceiling Entry and Wall Construction Permits.pdf PDF
Attachment 3 - EHRM Training and Admin Space Support - Specifications- Rev1.pdf PDF
36C77622B0050_1.docx DOCX document
Attachment 12 - Contractor PIV Instructions and Form.pdf PDF
Attachment 14 - OIT Horizontal Cable Requirements.pdf PDF
Attachment 23 - VHA Supplemental Contract Requirements for Combatting COVID-1912-14-2021.docx DOCX document
Attachment 13 - Contractor Parking.pdf PDF
Attachment 20 - Limitations on Subcontracting.docx DOCX document
Attachment 16 - Infection Control Barrier Sample.pdf PDF
Attachment 00 - SOW 578-21-706 Construction.docx DOCX document
Attachment 17 - Hines COVID-19 Guidelines.pdf PDF
Attachment 9 - Pre-Construction Risk Assessment (PCRA).pdf PDF
Attachment 2 - EHRM Upgrade -Phase 2 Construction Drawings - Part 2.pdf PDF
Attachment 5 - Safety and Health During Construction Activities.pdf PDF
Attachment 4 - Pre-Construction Checklist.pdf PDF
Attachment 21 - Contractor Safety and Environmental Form.docx DOCX document
Attachment 6 - Cutting Welding and Other Hot Work.pdf PDF
Attachment 7 - Dig Permit SOP Form.pdf PDF
Attachment 22 - Hines Construction Wage Rates 6-24-2022 Cook.pdf PDF
Attachment 18 - Hines Underground Utility Plan.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Risk Assessment for Construction / Renovation Projects Project Name: EHRM Training & Admin Space Support Project or Work-Order Number: 578-21-706 Project Manager or COR: Brandon Sidler Extension: 28570 Building Number: 20 Floor(s)/Room(s): Part of Floor 1. All of Floor 2.

Start date: 9/10/2022 Projected completion date: 3/10/2023

Construction Activity Infection Control Risk Group ☐ TYPE A: DUST LEVEL Low

Non-invasive activity, low noise, no vibration.

☒ GROUP 1: LOW

Office areas, FMS areas, all non-patient care areas.

☒ TYPE B: DUST LEVEL: Moderate to High Small scale, short duration, low-moderate noise, low-moderate vibration.

☐ GROUP 2: MEDIUM

All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.

☐ TYPE C: DUST LEVEL Moderate to High Requires more than one work shift (independent of working days) to complete, low-moderate noise, moderate–high vibration

☐ GROUP 3: MEDIUM/HIGH

ED, Radiology/MRI, admissions, food service areas, laboratories.

☐ TYPE D: DUST LEVEL High Major demolition and construction activities. Requires consecutive work shifts, moderate-high noise, moderate-high vibration

☐ GROUP 4: HIGHEST

Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis

Project Class Determination Matrix Construction Activity Type Risk Group

Type “A”

Type “B”

Type “C”

Type “D”

Group 1 I II II III Group 2 I II III IV Group 3 I III III IV Group 4 III IV IV IV

Contractors Actions by Project Class All personnel will have Emergency Preparedness training/posting/ID card.

CLASS

I

1. Execute work to minimize air-borne dust dispersed into atmosphere from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Contain construction waste before transport in tightly covered containers.

4. Clean work area upon completion of task including wiping surfaces with disinfectant.

5. Contact EMS for appropriate preparation for return to operation(s).

CLASS

II

In addition to above:

6. Post the signed ICRA at the entrance.

7. Isolate work area from patients/staff. Use appropriate temporary barriers and more permanent containment methods (i.e., seal holes in walls, tape gaps in doors, etc.)

8. Water mist work surfaces to control dust while cutting.

9. Block off and seal supply air vents. Place filter over return/exhaust vents.

10. Place dust mat or wipe feet at entrance/exit of work area.

11. Wet mop and/or vacuum w/HEPA filtered vacuum before leaving work areas.

CLASS

III

In addition to above:

12. Install barriers to create a negative pressure ante room and/or workroom.

13. Maintain negative air pressure in work area at all times until completion utilizing HEPA-equipped air filtration units.

14. Vacuum personnel with HEPA vacuum before leaving. Or, Don-Doff coveralls each time leaving work site. All wear shoe covers changed each time exiting the area.

15. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.

16. Do not remove barriers until completed project is inspected by Safety, IC-Team, EMS, and Area Manager.

17. Carefully remove barriers to minimize spread of dirt and debris. Contact EMS for final clean.

CLASS

IV

In addition to above:

18. Provide a disinfectant wipe down of any tool carts or waste transports prior to leaving the containment area.

19. Do not remove barriers until terminal clean is performed inside work zone and barriers are included in the cleaning process.

20. Perform 2nd terminal cleaning after removal of barriers. Contact EMS for final clean.

Signatures Date Contractor’s Signature:

(Projects Only)

Project Planner or Maintenance Worker Signature:

March 10, 2022

Supervisor Signature:

March 9, 2022

Infection Control:

Infection Control Risk Assessment for Construction / Renovation Projects
Infection Control Risk Group
Project Class Determination Matrix
Construction Activity Type (
( Risk Group
Group 1
I
Group 4
Contractors Actions by Project Class
All personnel will have Emergency Preparedness training/posting/ID card.
CLASS
CLASS
CLASS
CLASS
Signatures
Contractor’s Signature:
(Projects Only)
Project Planner or
Maintenance Worker Signature:
Supervisor Signature:
Infection Control: