Attachment 10 - MAHG201049 MSS.xls
XLS spreadsheet 77 KB Posted
- Attached to
- Larcher Chapel Five Phase Renovation Federal contract opportunity
- Solicitation number
- FA301021R0019
About this file
This document contains a material submittals schedule and related federal contract opportunity solicitation. The material submittals schedule outlines 100 line items for the renovation of Larcher Chapel at Keesler Air Force Base, including requirements for submittals on earthwork, concrete, masonry, structural steel, HVAC, plumbing, electrical and fire protection systems. Submittals are due within 10 days of notice to proceed and require various numbers of copies depending on whether electronic or physical submission is specified. The related federal contract opportunity solicitation is seeking bids for the five phase renovation of Larcher Chapel between $1,000,000 to $5,000,000, which is set aside as 100% for Service Disabled Veteran Owned Small Businesses. The base period of performance is 200 to 410 days dependent on options exercised. The pre-bid site visit will take place on July 30, 2021 and bids are due by the solicitation closing date. The work will be awarded on an all or partial basis depending on available funding.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| MAHG201049 | Project Title: | ||
| RENOVATE LARCHER CHAPEL | Solicitation / Contract Number: |
[ enter here ]
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | |||||||||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date | Date Received in Contracting | Date to Civil Engineering | Return Suspense Date | Submittal Numbers | Date Contractor | ||||
| Notified | Contractor Resubmittal | Final Approval | ||||||||||||||||||||
| Approved | Disapproved | |||||||||||||||||||||
| 1 | HazMat Questionnaire | 1 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | ||||||||||||||||||
| 2 | HazMat MSDS | 1 | 1 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | |||||||||||||||||
| 3 | Hazmat Reporting Entry Form | 1 | 1 | 1 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | ||||||||||||||||
| 4 | Recycling and Landfill Report | 1 | 1 | End of Contract | Provide the documents as required per the Environmental packet provided by Keesler AFB. | |||||||||||||||||
| 5 | Warranty (Manufacturer's) for all items as required in Project Manual | 1 | End of Contract | |||||||||||||||||||
| 6 | 1-Year Warranty (Contractor) | 1 | End of Contract | |||||||||||||||||||
| 7 | Section 023000 - Earthwork | 1 | 1 | 10 Days after NTP | ||||||||||||||||||
| 8 | Section 023620 – Termite Control | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||||
| 9 | Section 027640 – Pavement Joint Sealants | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||||
| 10 | Section 031000 – Concrete Forming and Accessories | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 11 | Section 032000 – Concrete Reinforcing | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 12 | Section 033001 – Cast in Place Concrete | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 13 | Section 036000 – Non-Shrink Grouting | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||||
| 14 | Section 048100- Unit Masonry Assembly | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 15 | Section 051200 – Structural Steel | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 16 | Section 053110 - Steel Roof Decking | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 17 | Section 054000 – Cold Formed Framing | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 18 | Section 055000 – Metal Fabrication | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 19 | Section 061000 – Rough Carpentry | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 20 | Section 062000 – Finish Carpentry | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 21 | Section 066500 – Solid Surfacing | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 22 | Section 071900 – Water Repellents | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||||
| 23 | Section 072100 – Building Insulation | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 24 | Section 072600 – Vapor Barriers | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 25 | Section 075200 – Modified Bituminous Roofing | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 26 | Section 076200 – Sheet Metal Flashing and Trim | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||
| 27 | Section 076213 – Sheet Metal Gutters and Downspouts | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||
| 28 | Section 077100 – Manufactured Roof Specialties | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||
| 29 | Section 078400 – Fire stopping | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 30 | Section 078410 – Through Penetration Fire Stop Systems | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 31 | Section 078420 – Fire Resistive Joint System | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 32 | Section 079200 – Joint Sealants | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 33 | Section 081000 – Steel Frames | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 34 | Section 081100 – Steel Doors | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 35 | Section 082110 – Wood Doors | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 36 | Section 084113 – Aluminum Frame Entrances and Storefronts | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 37 | Section 087100 – Finish Hardware | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 38 | Section 087453 - Access Control Hardware | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 39 | Section 088000 - Glazing | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 40 | Section 088190 - Hurricane Resistant Glazing | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 41 | Section 092216 - Non-Load Bearing Steel Framing | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 42 | Section 092500 - Gypsum Board | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 43 | Section 093000 – Porcelain Tile | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 44 | Section 093100 – Ceramic Tile | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 45 | Section 095110 – Acoustical Ceiling Panels | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 46 | Section 096519 – Resilient Tile Flooring | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 47 | Section 096780 – Resilient Wall Base | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 48 | Section 096813 – Tile Carpet | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 49 | Section 099100 – Painting | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 50 | Section 104310 – Signage | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 51 | Section 101550 – Toilet Compartments | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 52 | Section 105230 – Fire Extinguishers and harware | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 53 | Section 108000 – Toilet Accessories | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 54 | Section 144200 – Wheelchair Lift | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | Verification Samples. O&M manuals due at project closeout | |||||||||||
| 55 | Section 220529 – Hangers and Supports for Plumbing Piping and Equipment | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||||
| 56 | Section 220553 – Identification for Plumbing Piping and Equipment | 1 | 10 Days after NTP | |||||||||||||||||||
| 57 | Section 220800 – Commissioning of Plumbing | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 58 | Section 221116 – Domestic Water Piping | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 59 | Section 221313 – Sanitary Waste and Vent Piping (includes Storm Piping) | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||
| 60 | Section 230513 – Common Motor Requirements for HVAC Equipment (Motor Starters) | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 61 | Section 230516 – Expansion Fitting and Loops for HVAC Piping (piping and Fittings) | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 62 | Section 230519 – Meters and Gauges for HVAC Piping | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 63 | Section 230523 – General Duty Valves for HVAC Piping | 1 | 3 | 3 | 10 Days after NTP | |||||||||||||||||
| 64 | Section 230548 – Vibration and Seismic Controls for HVAC | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 65 | Section 230595 – HVAC Testing, Adjusting and Balancing Procedures | 1 | 3 | 7 days after TAB | ||||||||||||||||||
| 66 | Section 230700 – HVAC Insulation | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 67 | Section 230900 – Instrumentation and Controls for HVAC | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | Samples as indicated in section 23 09 00 | |||||||||||
| 68 | Section 230920 – Adjustable Frequency Drives | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 69 | Section 231123 – Facility Natural Gas Piping | 1 | 1 | 1 | 1 | 10 Days after NTP | O&M documentation due at project closeout (replacement part numbers) | |||||||||||||||
| 70 | Section 232116 – Hydronic Piping Specialties | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 71 | Section 232123 – Hydronic Pumps Centrifugal | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 72 | Section 232500 – HVAC Water Treatment | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||
| 73 | Section 233113 – Metal Duct | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 74 | Section 233200 – Sheet Metal Accessories | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 75 | Section 23 – Air Handling Units | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 76 | Section 233600 – Air Terminal Unit (Variable Volume Terminals) | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 77 | Section 235239 – Fire Tube Boilers | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||
| 78 | Section 236423 – Scroll Water Chillers | 1 | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||
| 79 | Section 237713 – Expansion Tanks | 1 | 1 | 1 | 1 | 10 Days after NTP | ||||||||||||||||
| 80 | Section 260501 – Minor Electrical Demolition | 1 | 10 Days after NTP | |||||||||||||||||||
| 81 | Section 260519 – Low-voltage Electrical Power Conductors and Cabled | 1 | 10 Days after NTP | |||||||||||||||||||
| 82 | Section 260526 – Grounding and Bonding for Electrical Systems | 1 | 10 Days after NTP | |||||||||||||||||||
| 83 | Section 260529 – Hangers and Supports for Electrical Systems | 1 | 10 Days after NTP | |||||||||||||||||||
| 84 | Section 260534 – Conduit | 1 | 10 Days after NTP | |||||||||||||||||||
| 85 | Section 260537 - Boxes | 1 | 10 Days after NTP | |||||||||||||||||||
| 86 | Section 260923 – Lighting Control Devices | 1 | 1 | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||
| 87 | Section 262416 - Panelboards | 1 | 10 Days after NTP | |||||||||||||||||||
| 88 | Section 262726 – Wiring Devices | 1 | 1 | 10 Days after NTP | ||||||||||||||||||
| 89 | Section 262800 – Low Voltage Circuit Protective Devices | 1 | 1 | 10 Days after NTP | ||||||||||||||||||
| 90 | Section 262818 – Enclosed Switches | 1 | 10 Days after NTP | |||||||||||||||||||
| 91 | Section 264300 – Surge Protection | 1 | 1 | 10 Days after NTP | ||||||||||||||||||
| 92 | Section 265100 – Interior Lighting | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||||
| 93 | Section 255600 – Exterior Lighting | 1 | 1 | 1 | 10 Days after NTP | |||||||||||||||||
| 94 | Section 271005 – Structured Cabling for Voice & Data | 1 | 1 | 10 Days after NTP | ||||||||||||||||||
| 95 | Section 273000 – Telephone-Data-CATV | 1 | 10 Days after NTP | |||||||||||||||||||
| 96 | Project Work Schedule (AF3064) | 1 | 10 Days after NTP | |||||||||||||||||||
| 97 | Certified Fire Protection Plans | 1 | 3 | 10 Days after NTP | ||||||||||||||||||
| 98 | Certified Fire Alarm Plans | 1 | 1 | 1 | 3 | 10 Days after NTP | ||||||||||||||||
| 99 | Certified Fire Protection Mass Notification Plans | 1 | 1 | 1 | 3 | 10 Days after NTP | ||||||||||||||||
| 100 | Project O&M Manuals | 1 | 1 | Project Closeout | 2 Hard Copies and 3 Compact Disks |
&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).
&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
Enter Resubmittal Number Enter the submittal final approval date
(MM/DD/YY)
File details come from the government source that posted it. Updated .