This document provides details for a federal solicitation seeking the development, testing, manufacturing, and deployment of forty-eight AN/MPN-14K Airport Surveillance Radar Indicator Control Box units. The solicitation requests forty production units, four First Article Test units, and four spare units, along with the complete technical data package. Site visits to view existing MPN-14K systems are available upon request by June 22, 2022. Offerors must cover travel costs for any visits. The solicitation includes attachments laying out requirements for pricing, contract data requirements, quality assurance provisions, packaging, first article testing, and the original technical manual to be used for reference in fulfilling the statement of work. Responses to the solicitation are due by the date and time specified in Section L.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| CDRL No. | Authority | CDRL Title - Subtitle | Government Rights | Distro Code | Submission Time |
| A001 | DI-MGMT-81928/T | Contractors Progress and Status Report - Program Management Status Report | Government Purpose | C | 10th of each month beginning month after CA |
| A002 | DI-ADMN-81249C | Meeting Agenda | Government Purpose | C | AS REQ - SUB 10 DAYS PRIOR TO EACH MEETING |
| A003 | DI-ADMN-81250C | Meeting Minutes | Government Purpose | C | AS REQ - SUB 10 DAYS AFTER EACH MEETING |
| A004 | DI-QCIC-80553A/T | Acceptance Test Plan | Government Purpose | C | ONE TIME |
| A005 | DI-MISC-81943 | Trip/Travel Report | Government Purpose | C | ONE TIME - SUB 10 DAYS AFTER COMPLETION OF TRAVEL FOR THE F.A.T |
| A006 | DI-MGMT-81861C/T | Integrated Program Management Data and Analysis Report (IPMDAR) - Integrated Master Schedule (IMS) | Government Purpose | C | Concurrent with CDRL A001 and as required |
| A007 | DI-SESS-81000F/T | Product Engineering Desigh Data and Associated Lists | Unlimited Rights | C | Each review or audit |
| A008 | DI-MGMT-81803A | Item Unique Identification (IUID) Marking Plan | Government Purpose | C | If applicable, 90 DAC |
| A009 | DI-MISC-81454D | Computer Program Identification Number (CPIN) Catalog Information | Government Purpose | C | If applicable, 90 DAC |
| A010 | TM-86-01R | Technical Order (TO) | Unlimited Rights | C | Field Level |
35% - 1st TDR 75% - 2nd TDR 90% - at FAT 100% - Before Production Depot Level 35% - 15 Days After FAT 75% - 60 Days After 1st Submission 100% - 60 After 2nd Submission A011 DI-PACK-80120C/T Preservation & Packing Data Government Purpose D If applicable, upon packing and delivery of unit