Attachment 1 - Work Summary n Progress Report - Copy.pdf
PDF 199 KB Posted
- Attached to
- Golden Gate Shrine 895-NS-FY26-001
- Solicitation number
- 36C78626B0024_1
About this file
This is a Work Summary & Progress Report form for the Golden Gate National Cemetery National Shrine Project – Phase 3 located at 1300 Sneath Lane, San Bruno, California 94066 (Project No. 895-NS-FY26-001). The form is designed to track contractor completion and government acceptance of work performed under the Base Bid and Options 1, 2, and 3 of a cemetery section renovation contract.
The form requires contractors to document and submit completion data for eight categories of work: (1) Compaction Testing, (2) Granite Marker Setting, Alignment & Backfill onto Headstone Support System, (3) Soil Compaction Testing, (4) Base Compaction Testing, (5) R&R Marker Headstones, (6) Clean Markers, (7) Agricultural Soil Testing and Recommendations, and (8) Turf Renovation. For each work item, contractors must report the total quantity completed (measured in each units or square feet) and identify the specific cemetery sections where work was performed. The form includes space for contractors to document any circumstances that adversely affected work progress, such as weather, turf conditions, strikes, or government delays. The form explicitly states it is not to be used as an invoice and requires dual signatures from both the contractor and the Government's Cemetery Director or Contracting Officer's Representative (COR), with corresponding dates, to confirm completion and government receipt of the progress report. Contractors may duplicate the form as necessary for multiple reporting periods.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Golden Gate National Cemetery National Shrine Project – FY26 San Bruno, CA 94066 Project No.: 895-NS-FY26-001
ATTACHMENT 1
WORK SUMMARY & PROGRESS REPORT
BASE BID and OPTIONS 1 :
FULL SECTION RENOVATION &
MARKER RAISE AND REALIGNMENT
WORK SUMMARY & PROGRESS REPORT Period Covered:
From:
To:
Cemetery Location: Contractor:
Golden Gate National Cemetery 1300 Sneath Lane San Bruno, CA 94066
Project Title:
GGNC National Shrine – Phase 3
Cemetery Section Renovation
Inspection / Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test some or all of the services that have been tendered for acceptance. The Government may require re-performance of nonconforming services at no increase in contract price. The Government shall exercise its post-acceptance rights—
1. Within a reasonable time after the defect was discovered or should have been discovered; and
2. Before any substantial change occurs in the condition of the item unless the change is due to the defect in the item.
Work Completed & Submitted for Acceptance (This form is not to be used as an Invoice)
BASE BID and OPTIONS 1, 2 and 3
1. Compaction Testing
Total number of compaction tests ► _________/ EA
Cemetery Section(s) ► __________
2.
Granite Marker Setting, Alignment & Backfill onto Headstone Support System
Total # Markers: ► _________/ EA
Cemetery Section(s) ► ____________
3. Soil Compaction Testing
Total Number of Compaction Tests ► _________/ EA
Cemetery Section(S) ► __________
4. Base Compaction Testing
Total Number of Compaction Tests ► _________/ EA
Cemetery Section(S) ► __________
5. R&R Marker Headstones
Total # Markers: ► _________/ EA
Cemetery Section(S) ► ____________
6. Clean Markers
Markers Cleaned ► ___________/ EA
Cemetery Section(S) ► ___________
7. Agricultural Soil Testing and Recommendations
Total Number of Soil Tests ► _________/ EA
Cemetery Section(S) ► __________
8. Turf Renovation
Total Square Feet of Turf Area. ► ___________ SF
Cemetery Section(s): ► ____________
Report below any circumstances which may have adversely affected work progress such as weather, turf conditions, strikes, delays by the Government, etc.
Signature of Contractor: Date Signed
Signature of Cemetery Director /
COR
Date Signed
Note: Contractor shall sign confirming that services indicated have been completed. Government shall also sign in acknowledgment of receipt of the Progress Report.
Duplicate Form as Necessary
File details come from the government source that posted it. Updated .