Attachment_1_-_Statement_of_Work.pdf

PDF 925 KB Posted

Attached to
CERCLA TCRA at burn sites in Rocky Mtn NP, CO
Solicitation number
140P2123R0008
Issued by

About this file

This is a request for proposals for a CERCLA time-critical removal action at burned sites within Rocky Mountain National Park, Colorado. The National Park Service seeks a contractor to remove ash, debris, and contaminated soil from up to twenty-two burn sites located across four areas within the park. Work includes characterization, removal and disposal of hazardous materials; confirmation sampling and risk assessments. Optional line items include additional site cleanups, further sampling and analyses, and human health and ecological risk assessments. The estimated value is between $1 million to $5 million. Proposals are due approximately 30 days after posting. Award will be a firm-fixed-price construction contract to a small business following FAR Part 19.5 procedures. The prime contractor must comply with FAR 52.219-14 limitations on subcontracting. Davis-Bacon wage rates apply.

View the file

Other files

File Type Posted
Attachment_7a_Revised_Wage_Determination_CO20230002_Larimer_5-12-2023_0004.pdf PDF
Form_2_Price_Schedule_(corrected_5-18-23)_0004.xlsx XLSX spreadsheet
Attachment_9a_Clarifications_52_-_62_140P2123R0008_0004.pdf PDF
Sol_140P2123R0008_Amd_0004.pdf PDF
Sol_140P2123R0008_Amd_0003.pdf PDF
Sol_140P2123R0008_Amd_0002.pdf PDF
Form_2_Price_Schedule_(corrected_5-10-23)_0002.xlsx XLSX spreadsheet
Attachment_9_Clarifications_1-51_0002.pdf PDF
Attachment_4_-_East_Troublesome_Wildfire_SAP_Draft_Final_0001.pdf PDF
Sol_140P2123R0008_Amd_0001.pdf PDF
Attachment_2_-_Rocky_Mountain_National_Park_East_Troublesome_Fire_Draft_Site_Data_Tables.pdf PDF
Form_5_-_Relevant_Experience.docx DOCX document
Form_2_Price_Schedule_(after_SOL_review).xlsx XLSX spreadsheet
FAQs_for_RFP_140P2123R0008.pdf PDF
Sol_140P2123R0008.pdf PDF
Form_1_SF1442_-_RFP_140P2123R0008.pdf PDF
Attachment_7_-_Wage_Determination_CO20230002_Larimer_4-6-2023.pdf PDF
Form_4_-_Limitations_on_Subcontracting_compliance_worksheet.xlsx XLSX spreadsheet
Attachment_3_-_Colorado_Department_of_Public_Health_and_Environmental_East_Troublesome_Wildfire_Guidance_with_Disposal_Form.pdf PDF
Form_3_-_FAR_representations.docx DOCX document
Form_6_-_General_References.docx DOCX document
Attachment_5_-_Rocky_Mountain_National_Park_East_Troublesome_Fire_Final_Identification_and_quantification_of_debris_memo.pdf PDF
Attachment_8_-_Wage_Determination_CO20230003_Grand_2-24-2023.pdf PDF
Attachment_6_-_Archeological_Monitoring_Requirements.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1: Statement of Work, TCRA at burn sites Rocky Mountain NP

STATEMENT OF WORK

EAST TROUBLESOME FIRE TIME CRITICAL REMOVAL ACTION

ROCKY MOUNTAIN NATIONAL PARK

1. INTRODUCTION.

1.1. This Statement of Work (SOW) describes a Response Activity for burned buildings and outbuildings at Rocky Mountain National Park (ROMO), Colorado. The Contractor shall provide all management, supervision, labor, tools, and equipment necessary to load, haul, accept, process, record, reduce, and dispose of disaster-related debris and soil. The debris to be removed varies from site to site and may consist of vegetation, ash, wood, contaminated soil, remnant concrete/stone/masonry structures, concrete, metal articles, trees that prohibit work performance, stumps, presumed PCB containing light ballasts, chemical containers, aerosol cans, fire extinguishers, compressed gas cylinders, electronic waste, small motorized equipment (generators, chain saws, etc.), white goods (washers, dryers, refrigerators, etc.), etc.. Ash, debris, metal, and concrete at all locations is presumed to contain or be contaminated by friable asbestos, unless otherwise indicated in this SOW or attachments. The Contractor shall perform confirmation sampling and analysis in accordance with the Draft Final Sampling and Analysis Plan (SAP) provided and comparison with Removal Goals (RGs).

2. LOCATION and SITE DESCRIPTION

2.1. The twenty-two burn sites addressed by this activity are located within Rocky Mountain National Park (ROMO) in north-central Colorado, approximately 55 miles northwest of Denver. The park is situated between the gateway communities of Estes Park to the east and Grand Lake to the west.

Location maps for the Sites are provided in Attachment 5. Information regarding ROMO is available at Rocky Mountain National Park (U.S. National Park Service) (nps.gov).

2.1.1. Lodging and meal services are available at both gateway communities and other nearby communities including Granby and others within 50 miles of the Sites.

2.1.2. Establishment of a construction camp will not be permitted, although use of public campgrounds is allowed.

2.2. Nineteen (19) Sites are located on the west side of the park in the Colorado River District (CRD) between approximately three (3) and seven (7) road miles from Granby. Eighteen Sites in the CRD are located in the Green Mountain / Onahu Ranch geographic area and are directly accessible by paved or dirt roads.

2.2.1. The Betty Dick Garage Site (Site ID 831) is located at the Betty Dick Ranch geographic area.

Access to this Site crosses the Colorado River via a structurally deficient bridge approximately 65 feet long. No vehicular traffic is allowed over the bridge. Contractor personnel can access the Site via the bridge on foot from a parking area located approximately 0.3 miles from the Site. Aviation will be required to import and remove construction equipment and materials and to remove wastes to a staging area for loading and transport for disposal via sling load. See Aviation Requirements in Section 9.9.

2.3. Three (3) Sites are located on the east side of the park in two geographic areas.

2.3.1. Two Sites, Moraine Park Stables Mess Hall (Site ID 893) and Moraine Park Stables Residence (Site ID 1086), are located approximately seven (7) paved road miles from Estes Park.

2.3.2. The Fern Lake Ranger Station (Site ID 14) is located in designated Wilderness Area and can only be accessed by contractor personnel via approximately 4-mile hiking trail. The site is located at approximately 9500 feet above sea level. Aviation will be required to import and remove construction https://www.nps.gov/romo/index.htm equipment and materials and to remove wastes to a staging area for loading and transport for disposal via sling load. See Aviation Requirements in Section 9.9.

2.3.3. The Sites are located at elevations ranging between approximately 8,000 and 9,500 feet above sea level, with summertime temperatures ranging from the 40’s at night into the 70’s or 80’s during the day.

2.3.4. The Sites are normally accessible from approximately May through October, although the Fern Lake Ranger Station will likely have a more limited construction season due to elevation.

2.3.5. The east and west sides of the park are seasonally connected by Trail Ridge Road (generally closed from around October through May), but contractors are advised this road is not suitable for construction traffic and may not be reliable for daily worker commuting.

2.3.6. The Sites, except as noted above, are accessible by paved or dirt roads. All Sites or aviation staging areas connect to major highway systems via paved mountain roadways.

2.4. See Table 1 for estimated quantities of ash/soil, metals, hazardous materials, etc. for each Site included in this response action.

2.5. See the Rocky Mountain National Park East Troublesome Fire Identification and Quantification of Building Debris Memo for descriptive information regarding each burn site, location maps, and site photographs (Attachment 5). Note that Attachment 5 includes sites that are not part of this SOW.

Quantities of materials included in this removal action do not match those presented in this document.

Use Table 1 in this SOW for Site identification and estimated quantities.

2.6. Draft Site Characterization analytical data tables for the Sites are provided as Attachment 2, including Toxicity Characteristic Leaching Procedure (TCLP) results for select Resource Recovery and Conservation Act (RCRA) metals where total metal concentrations exceeded the “Rule of 20.” The final Site Investigation report, including data tables, shall be provided to the contractor upon contract award.

3. GENERAL REQUIREMENTS.

3.1. This is a removal action at ROMO’s ash, debris, and soil impacted areas resulting from wildfire-caused structural fires and restoration of the sites to a natural condition. The Contractor shall perform all the requirements of this SOW to successfully complete the project, unless specifically identified as the responsibility of NPS or NPS-designated representative.

3.2. Work shall be performed under project-specific plans developed by the Contractor. The plans and work shall conform to U. S. Environmental Protection Agency (USEPA) document “Guidance on Conducting Non-Time Critical Removal Actions Under CERCLA”.

3.3. The Contractor shall comply with 29 CFR 1910.120(b), and all relevant and applicable safety regulations as promulgated by OSHA. Additionally, the Contractor shall adhere to all generally accepted professionally practiced safety standards.

3.4. The Contractor shall comply with regulations of the NPS, or other authority having jurisdiction, governing the protection of land that includes or is adjacent to the project.

3.5. Coordination with NPS

3.5.1. The NPS Contracting Officer (CO) provides necessary written notification and/or direction to Contractor and is the sole person authorized to change the contract requirements, performance period, price, or exercise options. The CO will appoint a Contracting Officer Representative (COR) and on-site Inspector who will coordinate Contractor’s removal efforts with Park staff’s daily operations. The COR and Inspector do not have authority to accept or reject work, authorize changes to contract terms and conditions, or obligate NPS for time or money.

3.5.2. The Contractor shall maintain close coordination with the NPS to assure adequate and timely flow of information. During the kickoff call, NPS and contractor will provide contact information for their respective participants.

3.5.3. Do not conduct site visits until the Contracting Officer authorizes them and the date(s) are approved by the park. Do not sample or otherwise disturb the Site without the prior approval of the Contracting Officer.

3.5.4. Coordinate Site activities with Contracting Officer or designee to minimize impact to the work of NPS personnel and to the visiting public.

3.5.5. During removal activities, Contractor shall have continuous access to the sites.

3.6. Quality Control

3.6.1. Contractor is responsible for quality of work. Inspect and test work as needed to ensure quality of materials, workmanship, construction, and finish, and to ensure functional performance complies with applicable specifications.

3.6.2. Independent testing laboratory is responsible for testing.

3.6.3. Contractor accepts ultimate responsibility, liability, and duty to control quality of services provided to the Government. Contractor shall be responsible for professional quality, technical accuracy, and coordination of designs, drawings, specifications, plans, reports, and other services furnished by Contractor, their Employees, Agents, Assignees, and Subcontractors under the contract. Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, plans, reports, and other services.

3.6.4. Contractor shall submit a Quality Control Plan (QCP) to the Contracting Officer or designee for approval, within 30 days of Notice of Award. If plan requires revisions or corrections, Contractor shall resubmit QCP within 10 days of receipt of NPS comments. Government reserves right to require changes to the plan during contract period as necessary to obtain quality specified. No change in the approved plan may be made without written concurrence by Contracting Officer or designee. The QCP shall include:

• A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

• A copy of a letter of direction to CQC Supervisor outlining assigned duties.

• Names, qualifications, and descriptions of laboratories to perform sampling and testing.

• Methods of performing, documenting, and enforcing quality control of work.

• Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

3.6.5. Daily Reports: Submit and include inspections and tests on first workday following date covered by the report. Use Daily Test Report Information Report Sheet and CMR & CQC Daily Report forms, or alternative forms approved by the Contracting Officer or designee.

3.6.6. Enforcement: Contractor shall satisfactorily correct any deficiency noted by quality control staff or Contracting Officer or designee.

https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=362827 https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=362820

3.7. On-site treatments of hazardous substances are prohibited on park lands.

3.8. The Contractor shall furnish all removal services, materials, supplies, labor, equipment, investigations, testing, studies, superintendence, and travel, as required, for completing the tasks.

3.9. The Contractor shall, without additional expense to the government, obtain any necessary licenses, permits, perform required notifications, and shall comply with all federal, state, and local laws, regulations, rules, guidance, and codes applicable to the performance of the tasks required for this SOW, to include applicable portions of Colorado Department of Public Health and Environment (CDPHE) Regulation No. 8, Part B and related October 2020 guidance regarding management of ash and debris resulting from the East Troublesome Wildfire (CDPHE ETW Guidance) provided in Attachment 3.

3.10. The Contractor Project Manager shall be responsible for technical oversight of the work, preparation of invoices, monitoring of budgets and schedules, and maintaining timely and appropriate communication with NPS Contracting Officer or their designate. The Contractor Project Manager shall be supported by professional and skilled technicians and laborers with experience in performing tasks/activities for the project as specified in this SOW.

3.11. All draft and final submittals shall be in the most current versions of both Microsoft Word and Adobe Acrobat. The Contractor shall provide all maps, plates, graphics, etc. in both Adobe Acrobat and the original source files (Geographic Information System (GIS) shape files, spreadsheets, etc.). Include all GPS or other location measurements collected by the Contractor to define removal areas or decision units in the project documentation.

3.12. The contractor shall submit final technical documents (Remedial Action Work Plan (RAWP), Remedial Action Completion Report (RACR), etc.) to the NPS that meet the accessibility standards per Section 508 of the Rehabilitation Act. The contractor shall utilize the 508-accessibility checker or other similar features, if available in that software, at document inception and use professional judgement throughout document production to best meet 508 accessibility standards.

3.13. The file names of the documents submitted to the NPS shall comply with the following naming convention: ROMO__ETWBurnSites_Document_Version_Date where:

• “Document” is the abbreviated title of the document. Examples include:

o Archeological Monitoring Report – “ArchMonRpt” o Asbestos Inspection Report – “ACMInsRpt” o Ecological Risk Assessment – “ERA” o Human Health Risk Assessment – “HHRA” o Meeting Minutes – “MeetMin” o Progress Report - "ProgRep" o Quality Assurance/Quality Control Plan – “QAQCPlan” o Response Action Completion Report - "RACR" o Sampling and Analysis Plan – “SAP” o Site Health and Safety Plan - "SHASP" o Stormwater Pollution Prevention Plan - “SWPPP” o Work Plan - "WorkPlan"

• “Version” is the version of the document (e.g., “Draft” or “Final”). Do not use version numbers.

The date will indicate the version number.

• “Date” is the date signed by the contractor in the format of YYYYMMDD.

3.13.1. All draft and final technical plan or report deliverables (RAWP, RACR, SAP, etc.) shall be signed/stamped by the Environmental Professional before submitting to NPS.

3.13.2. All files shall be transmitted to the NPS via email or an agreed-upon secure file transfer method to the Contracting Officer, the COR and the ROMO POC.

3.14. The Contractor is advised not to perform any services requested by any person verbally or in writing, which could be considered a change in the terms or scope of this SOW or necessitating an adjustment in contract price or any contract term or condition. If such additional revisions to the SOW are required, the NPS Contracting Officer and Contractor will negotiate the scope, terms, and price, and formalize them in a written modification to the contract.

3.15. Contractor shall not demobilize from a site until all tasks are completed or as otherwise directed by the Contracting Officer.

3.16. Working Hour Restrictions: Limit work and deliveries to weekday hours of 6:30 AM to 6:00 PM unless otherwise approved by Contracting Officer or designee. No work shall occur on National Park Service (NPS) holidays or weekends without prior approval by Contracting Officer or designee.

3.17. Optional Contract Line Items (CLINs), Unit-Priced Line Items, and Notification Requirements.

3.17.1. Award of optional CLINs identified in the price schedule are not guaranteed and may or may not be awarded at the time of award of the contract.

3.17.2. The Contracting Officer may exercise optional CLINs after award as defined in Section H.7 of the solicitation/contract using the timeframes in Section 12 of this SOW.

3.17.3. The Contractor must notify the Contracting Officer in writing when performance of any unit-priced CLIN reaches 80% of the estimated quantity listed in the price schedule. At no time is the contractor authorized to perform services that in aggregate cost more than the amount shown on the associated unit-priced CLIN, which represents a "not to exceed" (NTE) value on the contract or current modification. Refer to Section G.1 in the solicitation/contract.

3.17.4. The Government may, at its sole discretion, increase or decrease the quantities of unit-priced line items to accomplish the work. The Contracting Officer may unilaterally exercise option(s) for increased quantities by written notice to the Contractor any time prior to demobilization from the Site, and for decreased quantities any time prior to final payment. If additional quantities above the estimated quantity are necessary during on-site work, the Contracting Officer may direct the contractor to continue performance up to an established quantity or price ceiling using the associated unit price(s) . The newly-authorized work will be timely definitized in a contract modification. Refer to Section H.8 in the solicitation/contract.

3.18. PERIOD OF PERFORMANCE AND SCHEDULE.

3.18.1. The Contractor may begin plans and pre-mobilization documentation after award.

3.18.2. The Contracting Officer will authorize the site visit after receipt and acceptance of the performance and payment bonds, liability insurance certificate, and SSHASP.

3.18.3. The Contracting Officer will issue a Notice to Proceed (NTP) with on-site removal activities after all planning documents (including schedule, RAWP, SWMP/UPPP, QCP, and SAP update) are fully accepted or approved. These are due within 60 days after award.

3.18.4. The performance period to complete the removal action and confirmation sampling is 120 calendar days after the NTP is issued. If necessary, removal actions may be suspended during wintry conditions and the 120-day clock will stop. The contractor shall resume operations as soon as sites are accessible and conditions are appropriate; the clock will resume when operations resume. See FAR clause 52.211-10 and addendum.

3.18.5. The RACR and other project documentation shall be fully completed within 140 calendar days after completion of removal activities.

4. CONTRACT SUPPORT TASKS. The procedures/activities associated with the debris and soil removal include the following Contractor tasks.

4.1. Prepare Schedule, Schedule of Values, and participate in Kick-off Conference Call.

4.1.1. Prepare and submit a detailed schedule of project activities to the NPS COR within 15 days after award of the contract. “Days” in this SOW means calendar days.

4.1.2. Prepare and submit a Schedule of Values (SOV) that aligns with the contract line items (CLINs) and breaks each one into discrete, measurable tasks or deliverables within 15 days after award of the contract.

4.1.3. Participate in kick-off conference call to discuss schedule and contract administration procedures with the Contracting Officer, Contracting Officer Representative (COR), NPS Regional and ROMO staff, to be held within 20 days after award of the contract.

4.2. Meetings/Conference Calls.

4.2.1. In addition to the Site Visit and Kick-off Call, the contractor shall facilitate and attend weekly conference calls (virtual meetings via Microsoft Teams preferred) to coordinate/facilitate the work of this project. The Contractor shall provide the Contracting Officer or designee with draft meeting minutes within one day of each call, incorporate feedback, and provide final minutes just prior to the next meeting. NPS will provide minimum agenda topics after award. Meetings are anticipated to last 15-30 minutes.

4.3. Site Visit.

4.3.1. Within 15 days after the Kick-Off Call, a site visit will be conducted by NPS and Contractor representatives. Contractor representatives shall include at a minimum the Contractor Project Manager, Site Superintendent, Environmental Professional, and hygienist or other appropriate Contractor safety manager. The primary purpose of the site visit is for the Contractor to gather information necessary to document site conditions and other site-specific features to aid in developing required plans and for removal action planning. All burn sites will be visited as conditions allow.

4.4. Site-Specific Health and Safety Plan (SSHASP). Within 15 days of contract award, the Contractor shall prepare and submit a SSHASP to the Contracting Officer, COR and ROMO POC for review. NPS will review and provide any comments within 5 days of receipt. The Contractor shall issue a final SSHASP within 5 days of receiving NPS comments, if any. Final SSHASP shall be in place prior to the Site Visit. The SSHASP shall include all applicable Job Hazard Analyses (JHA), and measures to protect personnel from asbestos, heavy metals, dioxin/furans, silica, dust, and other potential chemical exposures, natural, biological, and physical hazards, such as PPE, personal air monitoring, hygiene, medical surveillance, etc. The Contractor’s plan and on-site work shall comply with 29 CFR 1910.120(b) and all relevant and applicable safety regulations as promulgated by the OSHA to include current HAZWOPER certification for all onsite workers.

4.4.1. Due to remote locations, it is recommended that most employees are trained in basic first aid, CPR, and AED use; that an AED is on site; and that at least one person trained in advanced first aid who is also qualified and certified to work in remediation, HAZWOPER, and all other types of work to be performed is onsite during project activities.

4.4.2. SSHASP shall incorporate additional required elements of an Accident Prevention Plan, not already addressed in the SSHASP.

4.4.2.1. Required elements include:

• Name of responsible supervisor to carry out the program.

• Monthly safety meetings.

• First aid procedures.

• Outline of each phase of work, hazards associated with each phase, and methods proposed to ensure property protection and safety of the public, NPS staff, and Contractor employees.

• Training

• Planning for possible emergency situations.

• Housekeeping and fire protection.

4.4.2.2. Accident Reporting: Report:

• Accidents defined as death.

• Occupational disease.

• Traumatic injury to Contractor’s personnel, NPS employees, or the public.

• Property damage of accidents in excess of $100

• Fires within seven days.

• Complete DSC Contractor Accident/Property Damage Report (CM-22) and forward to

Contracting Officer. Complete DSC Contractor Accident/Property Damage Report (CM-22) and forward to Contracting Officer or designee.

4.4.2.3. Accident Prevention Products: Provide:

• First aid facilities.

• Personnel protective equipment shall meet requirements of NIOSH and MSHA (National Institute for

Occupational Safety and Health and Mine Safety and Health Administration).

• Emergency instructions including telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and park police. Place in conspicuous locations at work site.

• Adequate egress at all times according to Standard for Safeguarding Construction, Alteration, and

Demolition Operations (NFPA 241).

• Hard hats for employees and for up to six visitors.

• Designate and post signs in hard hat areas.

4.4.2.4. Training: Provide training for first aid and hazardous material handling and storage.

4.4.2.5. Ensure employees are physically qualified to perform assigned duties safely. Do not allow employees to work if their abilities are impaired. Operators of equipment shall be able to understand signs, signals and operating instructions, and capable of operating such equipment.

4.4.2.6. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=231291 https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=231291 the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

4.5. Removal Action Work Plan (RAWP). Within 10 days of the Site Visit, the Contractor shall prepare and submit for review a Site-specific RAWP outlining proposed field actions to successfully complete the removal action, including Technical Approach and Methodology, Geographic Area Management, confirmation sampling, and Organizational Structure (management to field supervisory level and division of responsibilities). The RAWP shall include proposed measures to control visible dust emissions during removal activities and shall provide for daily perimeter dust monitoring (upwind and downwind) of each active removal site using real-time field monitoring equipment. The RAWP shall identify all proposed waste treatment, disposal, and recycling facilities.

4.5.1. The Contracting Officer or designee will review and provide comments within 10 days of receipt.

4.5.2. The Contractor shall provide a final RAWP incorporating NPS comments within 5 days of receipt.

4.6. Storm Water Pollution Prevention (SWPP).

4.6.1. If the total estimated area of disturbance for any individual Site or a contiguous area within “a common area of development or sale,” such as the Green Mountain / Onahu Ranch area, is determined by the Contractor to exceed 1-acre, obtain coverage under the CDPHE Water Quality Control Division General Permit Stormwater Discharges Associated with Construction Activity Authorization to Discharge Under the Colorado Discharge Permit System (CDPS) COR400000.

4.6.1.1. The Construction General Permit requires the development of a Storm Water Management Plan (SWMP). The SWMP shall include and adhere to all requirements established in the General Permit.

4.6.2. If the Contractor determines that the total contiguous area of disturbance will be less than 1-acre, the Contractor shall prepare and implement an NPS Under-an-Acre Pollution Prevention Plan (UPPP) (use latest template from DSC workflows at https://www.nps.gov/dscw/publicforms.htm#ct).

4.6.3. All sites must be included in the SWMP or UPPP, as applicable.

4.6.4. Within 10 days of the Site Visit, the Contractor shall submit to the Contracting Officer or designee a draft SWMP or UPPP for review.

4.6.5. The Contracting Officer or designee will review and provide comments within 10 days of receipt.

4.6.6. The Contractor shall provide a final Plan incorporating NPS comments within 5 days of receipt.

4.6.7. Employ appropriate storm water best management practices at each site (such as use of wattles (100% biodegradable and 100% aspen fiber), silt fencing, dust control, etc.) to prevent off-site migration of waste into nearby waters. (i.e., sedimentation/ash control at storm drain or culvert inlets) in accordance with the permit and/or approved plan.

4.6.8. Regularly inspect, maintain, and repair storm water best management practices.

4.6.9. In addition to what is required in the SWMP or UPPP, the following temporary and permanent site stabilization is required

4.6.10. Temporary Site Stabilization:

4.6.10.1. Temporary sediment control measures shall be established within five (5) days from time of exposure or disturbance.

4.6.10.2. All temporary sediment control measures shall be biodegradable and weed free, made of 100% Aspen Fibers. American Excelsior or approved equal.

4.6.11. Permanent Site Stabilization

https://www.nps.gov/dscw/publicforms.htm#ct

4.6.11.1. Permanent erosion protection measures shall be established within five (5) days after final grading of areas.

4.6.11.2. Permanent site stabilization shall include importing topsoil and bringing it to final grade and application of mulch via hand or hydromulch.

• If hand mulching, apply mulch to a thickness of 2” evenly.

• If hydromulching, apply mulch only at the rate of 2000 lbs. per acre/2241.702 kg per hectare.

Mulch will be accepted when it uniformly covers the area being applied and is no less than ¼” thick at the time of application. Mulch applied to non-designated areas, such as roadways is to be cleaned immediately following application and will not be counted towards the total being applied

• Mulch shall be submitted for final approval and consist of the following:

o 100% Aspenwood fibers o Moisture: 10.0% ± 3% PH 5.4 ± 0.1 o Organic matter (oven dried basis): 99.3% ± 0.2 o Inorganic Ash (oven dried basis): 0.7% ± 0.2 o Water Holding: 1,402% o A minimum of 50% of the fibers will be equal to or greater than 0.15 inch.

o 75% or more will be retained on a 28 mesh screen.

o American Excelsior (1-800-777-Soil) or approved equal.

4.6.12. Contractor shall provide product submittals (with CM-16) proposed materials for temporary and permanent site stabilization.

4.7. Sampling and Analysis Plan (SAP) Update

4.7.1. The contractor shall implement and adhere to the SAP provided by NPS (Draft Final SAP included as Attachment 4). Minor modifications to the SAP that do not change the overall technical approach, sample count and analytical methods (e.g. sample naming conventions) may be identified by NPS or the Contractor and incorporated.

4.7.1.1. The Contractor shall update the provided SAP to include information regarding the selected analytical laboratory, detection limits, field, laboratory Standard Operating Procedures, and other minor modifications deemed appropriate.

4.7.1.2. Updated SAP shall be provided to the Contracting Officer or designee within 30 days of contract award.

4.7.1.3. The Contracting Officer or designee will review and provide comments within 10 days of receipt.

4.7.1.4. The Contractor shall provide a final Plan incorporating NPS comments within 5 days of receipt.

4.7.1.5. Do not commence confirmation sampling and analysis prior to NPS approval of the SAP updates.

4.8. Confirmation Soil Sampling. Perform confirmation soil sampling in accordance with the SAP and Section 6.

4.9. Removal Action Completion Report (RACR). The Contractor shall prepare draft, draft final, and final RACR detailing activities performed, with figures showing site features and sampling locations, site photographs (photographs shall be taken of each Site and surrounding area prior to, during, and after the removal of burn site debris and soil), results, conclusions, recommendations and “lessons learned”.

4.9.1. Submit the draft RACR to the Contracting Officer or designee within 30 days following the completion of field activities or receipt of all final laboratory data, whichever is later.

4.9.2. NPS will provide comments within 30 days after receipt of draft RACR.

4.9.3. Submit the draft final RACR incorporating NPS comments to the Contracting Officer or designee within 10 days of receiving comments from the NPS.

4.9.4. NPS will provide comments within 60 days after receipt of draft final RACR.

4.9.5. Submit the final RACR incorporating NPS comments within 10 days of receiving comments from NPS.

4.10. Option A – Perform Human Health Risk Assessment (HHRA) to Evaluate Initial Site Characterization and/or Confirmation Sampling Results and Establish Risk-Based Remedial Goals

4.10.1. The HHRA shall be prepared in accordance with the EPA Risk Assessment Guidance for Superfund Volume I: Human Health Evaluation Manual, including the latest published guidelines and include the following:

• Development of site/area-specific conceptual site exposure models (CSEM) for human exposure including residential, park employee and park visitor exposure scenarios. The NPS will provide details regarding park employee and park visitor exposure scenarios.

• Selection of Contaminants of Potential Concern (COPCs) by comparing maximum Site concentrations (UCL95 concentrations for Decision Units with triplicate ISM samples) to the most recent version of EPA and Colorado Screening Levels for residential exposure to soil based on a target cancer risk of 1E-06 and target hazard quotient (HQ) of 0.1.

• Calculate non-cancer hazards and cancer risks for the COPCs for the receptors listed above. Site-specific exposure assumptions for park employees and visitors will be provided by NPS before the risk assessment. The 95UCL will be used for the exposure point concentrations.

• For lead, estimate blood lead levels using the EPA Integrated Exposure Uptake Biokinetic (IEUBK) model and/or the Adult Lead Methodology (ALM).

• If human health risks are determined to be unacceptable, develop risk-based PRGs for each COC for appropriate human health exposure scenarios based on a target cancer risk of 1E-06 and a target HQ of 1 and compare those PRGs to site-specific background concentrations for consideration in developing final RGs.

4.10.2. Four other burn Sites within the CRD but not included in this removal action shall be included in the risk assessment, as directed by NPS. These four sites include the Timber Creek Road Camp Barn (Structure ID 783), Timber Creek Road Camp Tack Shed (Structure ID 572), Grand Lake Entrance Station Remittance Office (Structure ID 1141), and the Harbison Picnic Area Vault Toilet (Structure ID 1183). Location maps and post-burn photographs of these four locations are provided in Attachment 1.

These four additional Sites have been or will be redeveloped for continued use as was before the wildfire.

4.10.3. The Contractor shall prepare draft, draft final, and final HHRA Reports.

4.10.3.1. Submit the draft HHRA Report to the Contracting Officer or designee within 45 days of the Contracting Officer exercising the Option A.

4.10.3.2. NPS will provide comments within 30 days after receipt of draft HHRA Report.

4.10.3.3. Submit the draft final HHRA Report incorporating NPS comments to the Contracting Officer or designee within 10 days of receiving comments from the NPS.

4.10.3.4. NPS will provide comments within 15 days after receipt of draft final HHRA Report.

4.10.3.5. Submit the final HHRA Report incorporating NPS comments within 10 days of receiving comments from NPS.

4.11. Option B – Perform Screening-Level Ecological Risk Assessment (SLERA) and Refined SLERA to Evaluate Initial Site Characterization and/or Confirmation Sampling Results

4.11.1. The ecological risk assessment shall be performed in accordance with the NPS Protocol for the Selection and Use of Ecological Screening Values for Non-Radiological Analyses (2018 or latest version).

4.11.2. The ecological risk assessment will begin with a Screening Level Ecological Risk Assessment (SLERA), which is Steps 1 and 2 of the ecological risk assessment process as described in EPA Ecological Risk Assessment Guidance for Superfund: Process for Designing and Conducting Ecological Risk Assessments (EPA 1997; EPA 540-R-97-006). The SLERA shall include the following:

• Site visit by the ecological risk assessor to assess site conditions, confirm present and future use, confirm habitat types in vicinity of Sites, and gather additional information as necessary to support ecological risk assessment.

• The development of a site/area-specific CSEMs for ecological exposure as part of the screening level problem formulation.

• The selection of contaminants of potential ecological concern (COPECs) by comparing maximum concentrations listed in the most recent version of NPS (NPS 2018) and State of Colorado ecological screening values (ESVs). Use the lowest ESV.

• For identified COPECs, the calculation of refined screening level risk estimates using the 95UCLs and receptor specific ESVs for use in Refined SLERAs (aka Simple BERA) shall be used as an intermediate step prior to a full BERA.

4.11.3. Four other burn sites within the CRD but not included in this removal action, as described in Section 4.10.2, shall be included in the risk assessment, as directed by NPS.

4.11.4. The Contractor shall prepare draft, draft final, and final SLERA Reports.

4.11.4.1. Submit the draft SLERA Report to the Contracting Officer within 45 days of the Contracting Officer exercising the Option B.

4.11.4.2. NPS will provide comments within 30 days after receipt of draft SLERA Report.

4.11.4.3. Submit the draft final SLERA Report incorporating NPS comments to the Contracting Officer or designee within 10 days of receiving comments from the NPS.

4.11.4.4. NPS will provide comments within 15 days after receipt of draft final SLERA Report.

4.11.4.5. Submit the final SLERA Report incorporating NPS comments within 10 days of receiving comments from NPS.

4.12. Option C – Perform Baseline Ecological Risk Assessment (BERA) to Evaluate Initial Site Characterization and/or Confirmation Sampling Results and Establish Remedial Goals

4.12.1. If refined screening level risks are determined to be unacceptable, the ecological risk assessment may continue and a Baseline Ecological Risk Assessment (BERA) may be performed, which includes a refinement of steps 1 and 2, and Steps 3 through 7 of the ecological risk assessment process as described by EPA (1997). The BERA shall include the following:

• The refinement of the site-specific CSEM for ecological exposure, if needed.

• The specification of management goals, assessment endpoints, and measures of effect as described in EPA Guidelines for Ecological Risk Assessment (EPA 1998; EPA/630/R-95/002F).

• The calculation of HQs for a range of appropriate ecological receptor populations using site-specific exposure assumptions, appropriate toxicity values, and 95UCL or the exposure point concentrations. For plants and invertebrates, this will include use of no-effect and low-effect toxicity values from, for example, the ECORISK database developed by the Los Alamos

National Laboratory (LANL) (https://www.lanl.gov/environment/protection/eco-risk-assessment.php). For wildlife, this will include the comparison of dose-based estimates of exposure using food chain modeling for a range of surrogate receptors to no-effect and low-effect toxicity values from the literature.

• As appropriate, additional lines of evidence, such as site-specific toxicity tests, population evaluations, relevant uncertainties in the ecological toxicity literature, and home ranges versus nesting areas, may be employed to support final risk conclusions and identification of contaminants of ecological concern (COECs) as part of a weight of evidence evaluation.

• If ecological risks are determined to be unacceptable, estimate risk based PRGs for each COEC and each terrestrial receptor type (avian, invertebrates, mammals, and plants) based on the available lines of evidence. When computing PRGs based on an HQ approach, estimate risk-based PRGs based on a target HQ of 1 and a threshold-based effect level (e.g., the geomean of a no effect and low effect value). Compare those PRGs to site-specific background concentrations for consideration in recommending final RGs.

4.12.2. Four other burn sites within the CRD but not included in this removal action, as described in Section 4.10.2, shall be included in the risk assessment, as directed by NPS.

4.12.3. The Contractor shall prepare draft, draft final, and final BERA Reports.

4.12.3.1. Submit the draft BERA Report to the Contracting Officer or designee within 60 days of the Contracting Officer exercising the Option C.

4.12.3.2. NPS will provide comments within 30 days after receipt of draft BERA Report.

4.12.3.3. Submit the draft final BERA Report incorporating NPS comments to the Contracting Officer or designee within 10 days of receiving comments from the NPS.

4.12.3.4. NPS will provide comments within 15 days after receipt of draft final BERA Report.

4.12.4. Submit the final BERA Report incorporating NPS comments within 10 days of receiving comments from NPS.

5. REMOVAL ACTIVITIES

5.1. Base and Optional CLINs for Site Clean-up

5.1.1. Removal activities for the two burn sites at the Moraine Park Stables area and the eighteen burn sites at the Green Mountain / Onahu Ranch area are base CLINs (Items 1 through 19).

5.1.2. Removal activities at the Betty Dick Garage and at the Fern Lake Ranger Station are optional CLINs (Options BDG-1 through BDG-7, SBDG-1 and SBDG-2; and FLR-1 through FLR-6, SFLR-1 and SFLR-2).

5.1.3. In this SOW, refer to Section 3.17 for option exercising process and Section 12 for Definition of Line Items and timeframes to exercise options.

5.1.4. In the solicitation/contract, refer to Sections G.1, H.7, and H.8.

5.2. Response Activities should be performed during the dry part of the year. Removal Activities of debris and contaminated soils shall not be conducted during severe weather conditions (i.e. heavy rain, heavy snow, and/or high winds).

5.3. Prior to Response Activities, the Contractor shall complete and perform all notifications, permits, and compliance requirements to ensure a safe removal project. The Response Activity areas shall be demarcated as a safe work zones, including delineation of wetlands and utility clearances. The Contractor is required to coordinate with NPS and state officials on all necessary activities.

http://www.lanl.gov/environment/protection/eco-risk-assessment.php) http://www.lanl.gov/environment/protection/eco-risk-assessment.php)

5.4. Existing chain link fencing surrounding burn sites shall be dismantled as necessary to complete the work. Restore fencing overnight or use alternative fencing, temporary barricades, or other means to prevent unauthorized entry into work areas. Remove and return chain-link fencing to NPS at locations designated by park staff after completion of the project or at a specific site.

5.5. The contractor shall implement appropriate and effective control measures to prevent visible ash and dust emissions during performance of removal activities. Visible ash and dust emissions extending beyond safe work zones surrounding each burn Site is prohibited.

5.5.1. Outside of safe work zones surrounding each burn Site, the Contractor shall limit areas of soil disturbance and implement mitigations (e.g. apply water) to control dust emissions from heavy equipment and vehicle traffic.

5.6. Non-hazardous ash, debris, metal, concrete and soil shall be managed in accordance with the CDPHE ETW Guidance and all other applicable federal, state, and local laws.

5.7. Except for RCRA Hazardous Waste, the Contractor shall dispose of burn-site related wastes only at one or more of the landfills specified in the CDPHE ETW Guidance. In addition to the forgoing requirement, the selected landfill(s) for disposal of waste generated during the removal action must meet the requirements of the Off-Site Rule as specified in 40 CFR 300.440 (Off-Site Rule | US EPA). This does not include metal or concrete that the Contractor proposes to manage by recycling at an off-site recycling facility. The Contractor shall provide the Contracting Officer or designee with confirmatory documentation that the selected landfill(s) meet this requirement. This confirmation may be included as part of the RAWP or independently provided.

5.8. RCRA Hazardous Wastes shall be transported to at a RCRA Subtitle C Treatment Storage or Disposal Facility (TSDF) for treatment and/or disposal.

5.9. No transportation or disposal of materials shall occur until the proposed treatment, disposal, and recycling facilities are approved by the Contracting Officer or designee.

5.10. Contractor shall conduct waste pre-disposal characterization in accordance with disposal facility requirements.

5.11. The Contractor shall handle, characterize, identify, label and package all waste (including but not limited to hazardous waste) generated as a result of the removal action in accordance with all applicable federal, state and local laws.

5.12. The Contractor shall also be responsible for packaging, labeling and preparing manifests and other shipping documents and will make all other necessary arrangements for any off-site transportation and disposal of such waste in accordance with such laws.

5.13. The Contractor shall utilize a licensed transport, storage, and disposal (TSD) company, in good standing with the State of Colorado. The prime contractor shall be responsible for verifying the TSD Company’s credentials. Send waste manifest/bill of lading to the Contracting Officer or designee within two weeks of disposal and include with invoices.

https://www.epa.gov/superfund/site-rule#:%7E:text=Section%20121(d)(3,or%20contaminant%20(CERCLA%20wastes).

5.14. During hauling, the Contractor shall comply with legal and local load restrictions.

5.15. The Contractor is responsible for cleaning the entire visibly impacted area of structure-related ash and debris within and surrounding each burn site, inclusive of a minimum 5-foot buffer surrounding each building footprint/debris field. In order to control the area of contamination, the Contractor shall not, at any time, extend or stockpile the contaminated materials outside of the excavation footprint for each burn site without prior approval of the Contracting Officer or designee.

5.16. Segregable Hazardous Materials / Waste Management

5.16.1. Collect and remove segregable hazardous materials/wastes from each burn site. See Attachment 1 for previously identified known or suspected hazardous materials identified at each burn site.

5.16.2. Site inspections performed by NPS and NPS contractors has identified at least ten (10) presumed PCB light ballasts attached to fluorescent light fixtures at the Betty Dick Garage site. Place presumed PCB light ballasts in appropriate containers for transport and disposal. Transport and dispose of presumed PCB ballasts in accordance with Toxic Substances Control Act (TSCA), state, and any applicable, federal or state regulations. PCB wastes shall not be land disposed.

5.16.2.1. The removal and disposal of presumed PCB capacitors at the Betty Dick Garage shall be completed even if the option to remove ash, debris, and soil from this location is not exercised.

5.16.3. Site inspections performed by NPS and NPS contractors have identified fire extinguishers, aerosol cans, and chemical containers at multiple sites, but those observed appeared to be discharged or empty. It is presumed empty or discharged articles can be managed as fire-related debris in accordance with the CDPHE ETW Guidance. Inspection of the Onahu Ranch Lodge (Building ID 575) was limited due to the presence of extensive debris which may have covered or buried hazardous materials.

5.16.4. Option GM-1. Additional hazardous materials/wastes, such as but not limited to, batteries, electronic waste, non-empty chemical containers, non-discharged aerosols, compressed gases, and non-discharged fire extinguishers may be encountered during removal activities. If identified, such materials shall be collected, wiped clean of ash and dust, properly segregated, contained, characterized, transported and disposed in accordance with applicable federal, state, and local regulations. For proposal purposes, Contractor shall assume up to 100 pounds of various hazardous materials/waste will require management as described above.

5.17. Management of Metals:

5.17.1. Large metal items shall be managed in accordance with the CDPHE ETW Guidance and recycled.

5.17.2. Wash dust from metals before removing from burned site.

5.17.3. Appliances containing refrigerant such as refrigerators and freezers require special handling and removal of the refrigerant if any remains.

5.17.4. See Table 1 of this SOW for estimated metal quantities, including white goods, at each burn site location.

5.18. Management of Ash, Debris and Soil.

5.18.1. Collect, consolidate, and remove/excavate ash, small debris, and soil for disposal. Sweep and/or vacuum ash from all underlying masonry slabs and footings. Ensure all ash is removed from cracks and joints in masonry.

5.18.2. Contractor shall sequence removal and excavation to mitigate propagation of surface ash and debris to deeper and adjacent soils.

5.18.3. Excavate soils below the original structure / debris-field footprint and a surrounding 5-foot buffer to a depth of 6-inches, unless otherwise specified in this SOW.

5.18.3.1. The Betty Dick Garage and Fern Lake Ranger Station sites will be excavated to a depth of 3-inches.

5.18.4. Ash, debris, and soil shall be managed and disposed in accordance with the CDPHE ETW Guidance, unless otherwise specified in this SOW.

5.18.5. The ash debris and soil shall be placed in approved end-dump roll-off boxes, dump trucks, or other suitable transport containers lined with double 6-mil plastic sheeting completely closed over the material and sealed once the container is loaded. Cover partially loaded containers at the end of each workday to protect them from the elements. If necessary to facilitate the response action, wastes may be stockpiled on thick plastic sheeting within the excavation area for each burn site, and immediately covered to protect it from the elements (wind and/or rain) with similar plastic sheeting for temporary site storage prior to loading, transport and disposal at a licensed facility.

5.18.6. Large rocks, boulders or bedrock shall be wiped or swept to remove ash and dust and left in place or set aside if in the way of soil removal. No bedrock shall be removed and excavation shall be terminated at bedrock surface if encountered.

5.18.7. Smaller stones, small poured or block concrete piers and footings, and bricks shall be removed and managed as debris.

5.18.8. See Table 1 of this SOW for estimated quantities of ash, debris and soil.

5.19. Management of Poured Concrete Slabs and Foundations

5.19.1. Poured concrete slabs and foundations shall be demolished, managed, transported, and disposed or recycled in accordance with the CDPHE ETW Guidance, unless the SOW specifies them to remain in place.

5.19.2. Slabs and foundations shall be demolished prior to final soil excavation to ensure all concrete remnants and particles are removed from the site.

5.19.3. Three poured concrete slabs and two poured concrete foundations located in the Green Mountain / Onahu Ranch area shall be demolished and removed following removal of ash and debris.

5.19.4. The concrete slab located at the Betty Dick Garage shall remain in place.

5.19.5. See Table 1 for locations and estimated quantities of poured concrete slabs and foundations.

5.20. Management of Standing Structures

5.20.1. Seven rock/masonry chimneys and one rock pumphouse remain standing in the Green Mountain / Onahu Ranch Location. In accordance with the CDPHE ETW Guidance, CDPHE does not consider these structures to be completely destroyed by fire. CDPHE considers these structures to be safe for asbestos inspection. Photos of these structures are provided in Attachment 1.

5.20.2. Prior to demolition, the Contractor shall require that these eight standing structures be inspected by a Certified Colorado Asbestos Building Inspector (CABI) in conformance with Colorado Regulation No.