This Statement of Work (SOW) details contractor support for Maintenance of Traffic (MOT) and Temporary Traffic Control (TTC) during crewed space launches at Kennedy Space Center (KSC). The contractor will provide setup and teardown of traffic control equipment at three specific long gate locations: 2L (SR3 Merritt Island), 3L (SR 405), and 4TT (SR 402). Each location requires cones, portable toilets, stop signs, and portable light plants for nighttime launches.
The contract anticipates 3-4 crewed launches annually over five years, with each launch considered a single order. The contractor must complete equipment setup five hours before the launch window, remain on standby during the launch, and promptly remove all equipment afterward. Performance will be evaluated on timeliness, accuracy of equipment placement, safety, and responsiveness to NASA's Point of Contact. The traffic management plans include specific cone configurations to manage authorized and unauthorized vehicle traffic, with 2-3 KSC Security Officers present at each gate to support traffic control.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 80NSSC26Q0002-RFQ Amendment A00002.pdf | ||
| 80NSSC26Q0002 Amendment A00002 SF30.pdf | ||
| Questions and Answers.xlsx | XLSX spreadsheet | |
| 80NSSC26Q0002 Amendment A00001 SF30.pdf | ||
| Attachment 5 - Past Performance Questionaire.docx | DOCX document | |
| Attachment 4 - Past Performance Data Sheet.pdf | ||
| Attachment 3 - RFQ Questions Template.xlsx | XLSX spreadsheet | |
| Attachment 2 - Pricing Template.xlsx | XLSX spreadsheet | |
| 80NSSC26Q0002-RFQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KSC Launch Support Services Statement of Work
1.0 Project Objectives
The objective of this project is to procure contractor support for the setup and teardown of Maintenance of Traffic (MOT) and Temporary Traffic Control (TTC) equipment at three designated Kennedy Space Center (KSC) long gate locations during crewed space launch events. The primary goals are to ensure the safe and efficient flow of traffic, support KSC Security Police, and provide a secure perimeter for these high-profile events.
2.0 Background
This Statement of Work (SOW) is for a Blanket Purchase Agreement (BPA) to support ongoing crewed space launch operations from KSC. During crewed launches, KSC activates "long gates," which are access control points pushed out to the jurisdictional boundaries of the space center.
This process requires the temporary establishment of traffic control measures to manage the significant volume of traffic from authorized vehicles, and to redirect unauthorized vehicles. The contractor's services are critical to the successful and safe execution of these traffic plans.
3.0 Scope of Work
The contractor shall provide all personnel, materials, and equipment necessary to perform MOT services at three (3) specific KSC long gate locations:
• 2L – SR3 Merritt Island
• 3L – SR 405
• 4TT – SR 402
The work at each location shall include the setup of the following:
• Cones for routing traffic patterns
• One (1) portable toilet
• Two (2) stop signs
• One (1) portable light plant during hours of darkness
3.1 Anticipated Launches and Service Consistency
Based on historical and projected mission schedules, it is anticipated that there will be approximately 3-4 crewed launches per year over the next five-year period, resulting in an estimated total of 15-20 launches. The scope of work is largely consistent across all three locations and for each launch, with the primary variable being the time of day. Nighttime launches will require the use of additional lighting equipment (e.g., light plants). Each launch will be considered a single order under the BPA, with the understanding that a scrubbed launch will require a second attempt at service delivery.
4.0 Deliverables
The contractor shall provide the following deliverables for each launch event:
• Initial MOT Setup: The complete and accurate setup of all required cones, portable toilets, stop signs, and light plants at the three designated locations.
• Post-Launch Teardown: The prompt and complete removal of all contractor-provided equipment from the roadways and surrounding areas.
• Second Attempt Readiness: For any scrubbed launch, the contractor must be prepared to perform a second setup and teardown on the coordinated alternate date and time, as a single event is defined as including up to two attempts.
5.0 Timeline
The contractor’s timeline for each launch event is as follows:
• Material Delivery and Setup: All materials must be on-site, and the MOT setup must be completed approximately five (5) hours prior to the opening of the launch window.
• Duration of Launch Event: The estimated duration of the event (from setup to teardown) is variable, but the contractor must remain on standby to support the launch window, which can be brief.
• Post-Launch Teardown: All equipment must be picked up and removed from the roadway as soon as possible following a successful launch or scrub.
6.0 Performance Criteria
The contractor’s performance will be evaluated based on the following criteria:
• Timeliness: The ability to complete the setup of all equipment within the specified five-hour pre-launch window.
• Accuracy: The MOT setup must be in strict accordance with the pictorial plans provided by NASA, ensuring proper cone configuration and equipment placement.
• Safety: The setup and teardown of equipment must be performed in a manner that ensures the safety of all personnel, KSC Security Police, and the public.
• Responsiveness: Effective communication and responsiveness to the NASA Point of Contact (POC) for launch updates, especially in the event of a scrub, ensuring a timely second attempt.
Specific cone placement and placement of traffic control devices will be based on any FDOT/DOT requirements to manage traffic.
Exiting Traffic
Stop Sign
3 KSC
Officers
Gate 2 Long
Traffic Management Plan for Launch
Outbound
Traffic
Merges to
One Lane
Cone configuration needs to create lane shift to the right allowing a wider turn radius for unauthorized vehicles
NOTE: THE LINES REPRESENT
CONES
Unauthorized
Traffic Turn
Cone configuration needs to create lane shift to normal pattern for authorized vehicles
Light All
Unit(s)
Port-o-let
Close West Gator Creek Barricade
2 KSC
Officers
With Patrol Vehicle
Unauthorized Traffic
Authorized Traffic
Entrance
Exiting Traffic
Stop Sign
Gate 4TT
Traffic Management
Plan for Launch Do Not Enter Sign
Light All
Unit(s)
Port-o-let