Attachment 1 - Statement of Work.pdf

PDF 139 KB Posted

Attached to
Fire Rappelling Anchor Inspection
Solicitation number
FA462025QA811
Issued by

About this file

This Statement of Work (SOW) details the requirements for non-destructive testing of rappelling eyelets at Facility 1550 on Fairchild Air Force Base in Washington state. The contractor must perform pull testing on four rappelling eyelets, applying a 2,250-pound (10kN) test force in the usage direction with less than 0.04-inch deflection, and visually inspect anchors and attachments for damage such as cracks or deformation. Deliverables include a comprehensive testing report with results, observed deficiencies, recommended corrective actions, and photographic documentation.

The project is time-limited to 60 days after contract award, with work to be performed during standard hours of 0700-1630 Monday through Friday, excluding federal holidays. The contractor must provide all necessary tools, equipment, labor, and testing equipment, and comply with NFPA 1402 and OSHA standards. Security requirements mandate adherence to Fairchild Air Force Base regulations, and photography is prohibited without prior authorization from the 92 ARW Public Affairs Office. The government will provide site access and electrical power, and the solicitation is a 100% Total Small Business Set Aside under contract number FA462025QA811.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

Inspection and Testing of Rappelling Eyelets on Facility 1550 Fairchild AFB, WA

March 2025

Statement of Work (SOW) For

Inspection and Testing for Rappelling Eyelets on Facility 1550 Fairchild AFB, WA

1. DESCRIPTION OF SERVICE: The contractor shall provide all necessary tools, equipment, labor and testing equipment required to perform and document non-destructive testing on all rappelling eyelets at the Fire Training Site, Facility 1550.

2. SCOPE OF WORK: The Contractor shall complete all work, which includes furnishing all supervision, labor, material, equipment and services, unless otherwise specified herein, required under this contract. All work shall be performed in accordance with NFPA 1402, OSHA standards as well as any other applicable federal, state and local regulations and this Statement of Work (SOW).

1. Non-Destructive Pull Testing

a. Perform OSHA and NFPA 1402 required Non-Destructive pull testing on 4ea rappelling eyelets on facility 1550

b. Test to include: 2,250LB (10Kn) test force in the direction of usage with a deflection of less than .04in (1cm)

c. Once applied, all anchors and associated attachments shall be visually inspected for damage such as cracks and deformation

3. Deliverables: The contractor shall provide the following deliverables

1. A comprehensive report summarizing the testing performed, including results, any observed deficiencies and recommended corrective actions

2. Photographic documentation of inspections and repairs where applicable

4. GOVERNMENT FURNISHED PROPERTY AND SERVICES: The government shall furnish site access and electrical power. In the event of an emergency, dial 911.

5. GENERAL INFORMATION

5.1. HOURS OF OPERATION: Hours of operation are 0700-1630 Monday through Friday, excluding Federal Holidays and any other designated down day. Work can be done at other than normal hours of operation with the approval of the Contracting Officer. The contractor shall coordinate in advance all hours of work and any service interruptions with Civil Engineering points of contact.

5.2. SECURITY REQUIREMENTS: All personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering the government installation, shall abide by all Fairchild Air Force Base security regulations.

5.3. STANDARD OPSEC CONCERNS: Any video and photography when on FAB properties is prohibited unless properly authorized by the 92 ARW Public Affairs Office and are deemed necessary to execute this contract.

6. PERFORMANCE PERIOD: Project shall not exceed 60 days after contract award.

File details come from the government source that posted it. Updated .