Attachment 1 - Statement of Work.pdf
PDF 727 KB Posted
- Attached to
- Request for Qualifications USDA ARS PWA Architect-Engineer IDIQ Federal contract opportunity
- Solicitation number
- 12905B23R0005
About this file
This document is a Statement of Work outlining Architectural-Engineering services required for individual construction projects awarded by the Agricultural Research Service. Key details include:
The A-E will provide predesign, design, bid/proposal, construction, and post-construction services including environmental assessments, surveys, cost estimates, specifications development, permitting coordination, inspections, and as-built drawings. Specific requirements are outlined for boundary surveys, topographic surveys, geotechnical analysis, hazardous materials abatement, commissioning, energy analysis in compliance with EPACT 2005, and sustainable design principles. Design submissions are required at 15%, 35%, 50%, 95%, and 100% completion with a four week review period. Services will be obtained through fixed price task orders issued under an IDIQ contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Request for Qualifications Ammended.pdf | ||
| Attachment 2 - Past Perfomance Questionnaire.docx | DOCX document | |
| Questions and Answers ver 3.pdf | ||
| Questions and Answers ver 2.pdf | ||
| Questions and Answers.pdf | ||
| Attachment 4 - SF330.pdf | ||
| Attachment 7 - Terms and Conditions.pdf | ||
| Request for Qualifications Final.pdf | ||
| Attachment 5 - Questions and Answers.xlsx | XLSX spreadsheet | |
| Attachment 6 - PWA Map.jpg | JPG image | |
| Attachment 2 - Past Perfomance Questionnaire.docx | DOCX document | |
| Attachment 3 - Client Authorization Ltr.docx | DOCX document | |
| Attachment 8 - Lobbying Disclosure.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Architectural-Engineering Services
Table of Contents
Section/Title PAGE
1.0 INTRODUCTION
2.0 TERMINOLOGY AND ABBREVIATIONS
3.0 SCOPE OF WORK
3.1 General…
3.2 Working with Other Government Contractors…
3.3 Working with a Construction Manager at Risk (CMAR)…
4.0 STANDARD A-E SERVICES REQUIREMENTS
4.1 Compliance with Codes and Standards…
4.2 Web Portal Project Management System
4.3 Project Site Visits…
4.4 Document Requirements…
4.5 Submittals, Reviews, And Approvals…
5.0 PREDESIGN PHASE A-E SERVICES
5.1 Environmental Assessment (EA)…
5.2 Investigative Report or Study…
5.3 Program of Requirements (POR) Development…
5.4 Boundary Survey Services…
5.5 Topographic Survey Services…
5.6 Geotechnical Engineering Services…
5.7 Environmental Site Assessment…
6.0 DESIGN PHASE A-E SERVICES
6.1 Special Consultants…
6.2 Rendered Perspective…
6.3 Energy Saving Requirements…
6.4 Commissioning Design Task…
6.5 Design Development…
i
7.0 BID/PROPOSAL PHASE A-E SERVICES
7.1 Solicitation Review…
7.2 Prebid Conference…
7.3 Solicitation Amendments…
7.4 Bid Evaluation…
7.5 Proposal Evaluation…
8.0 CONSTRUCTION PHASE A-E SERVICES
8.1 Construction Management Services…
8.2 Construction Quality Assurance…
9.0 DESIGN REVIEW AND VALUE ENGINEERING SERVICES
9.1 General…
9.2 Design Review Services…
9.3 Value Engineering Services…
10.0 HAZARDOUS MATERIALS AND HAZARDOUS SUBSTANCES
ABATEMENT SERVICES……………………………………………………….61
10.1 General…
10.2 Abatement Services – (Identification, Assessment, and Corrective
Design Phase) …
10.3 Abatement Services – (Bidding Phase) …
10.4 Abatement Services – (Construction Phase) …
ii
A-E SOW
19 November 2019
1.0 INTRODUCTION
The Agricultural Research Service (ARS) issues fixed price task orders to obtain professional Architectural-Engineering (A-E) services for individual projects.
ARS uses two documents; one is the Statement of Work for A-E Services and the other is the Project Requirement Document.
The Statement of Work for A-E Services, (SOW), which is typically included in the A-E’s basic contract at the time of award, provides detailed information on the A-E’s responsibilities and on the standard requirements for document submissions.
The Project Requirements Document, (PRD), is developed specifically for each project and is issued by the Contracting Officer (CO) with the request for a fee proposal for the ordered task. The PRD identifies the specific services requested, establishes a schedule for the deliverables, gives budget information, discusses unique project needs, and provides the distribution list for the
2.0 TERMINOLOGY AND ABBREVIATIONS
A-E Architect-Engineer or Architectural-Engineer AOE Area Office Engineer ARS Agricultural Research Service BICSI Building Industry Consultant Services International BMS Building Management System CC Construction Contractor CD-ROM Compact Disk-Read Only Memory CMAR Construction Manager at Risk CO Contracting Officer CSI Construction Specifications Institute CVS Certified Value Specialist DC Design Charrette DR Design Review A-E or Design Review DRB Design Review Board EA Environmental Assessment EEM Energy Efficiency Measure ECC Estimated Cost of Construction EIS Environment Impact Statement EPM Engineering Project Manager ESA Environmental Site Assessment FD Facilities Division FDS ARS Facilities Design Standards (Manual and P&P 242.1M-ARS) FONSI Finding of No Significant Impact HSD Homeland Security Division
A-E SOW
IT Information Technology LA Local Authority LAN Local Area (Data) Network LCC Life Cycle Cost LCCA Life Cycle Cost Analysis OCIO Office of Chief Information Officer PDF Portable Documents Format PGM Policy Guidance Memorandum P&P Policies and Procedures POR Program of Requirements PRD Project Requirements Document RCDD Registered Communications Distribution Designer PSO Physical Security Officer RCI Resident Construction Inspector RPR Research Program Representative RPMB Real Property Management Branch SAVE Society of American Value Engineers SHEMB Safety, Health, and Environmental Management Branch SIR Savings to Investment Ratio SOW Statement of Work SRA Security Risk Assessment TDDG Telecommunications Distribution Design Guide Telecom Telecommunication Services (i.e., Voice, Data, LAN/WAN, etc.)
UFGS Unified Facilities Guide Specifications USDA United States Department of Agriculture VE Value Engineer or Value Engineering WAN Wide Area (Data) Network
3.0 SCOPE OF WORK
3.1 General
The A-E shall provide the indicated professional services associated with the planning, pre-design, design, bid, and construction management phases of the proposed project. The PRD will identify the specific services required by the project. These services will be obtained through the issuance of a fixed price task order. The types of services to be provided under this contract include, but are not limited to, the following:
• Bid Phase Services
• Construction Administration
• Construction Drawings
• Construction Site Observation (Quality Assurance)
• Construction Specifications
A-E SOW
• Cost Estimates
• Designs
• Design Analysis
• Design Criteria Development and Basis of Design
• Design Reviews
• Design Workshops
• Energy Modeling and Computer Simulation
• Environmental Assessments and/or Impact Statements
• Environmental Site Assessments
• Facility Commissioning
• Feasibility Studies
• Hazardous Materials and Substances; Identification and Abatement
Design Services
• Industrial Ventilation (Stack Emissions) Studies and Prototypes
• Investigative Reports
• Master Planning
• Project Assessment Report
• Record Documents
• Shop Drawing Reviews and Approvals
• Soil Borings/Geotechnical Investigations and Designs
• Storm Water Protection Plans
• Surveys
• Telecommunications Designs
• Value Engineering (VE) Workshops
3.2 Working with Other Government Contractors
When the Government employs, by a separate contract, other contractors, such as general contractors, construction managers, design reviewers, or other consultants, the A-E shall be required by its contract to cooperate fully with and to assist the other contractors and to coordinate its work with theirs. The A-E shall advise the CO when coordinating and cooperating with the other contractors result in design changes.
3.3 Working with A Construction Manager At Risk (CMAR)
The A-E may be required to work with a Construction Manager at Risk (CMAR) beginning at the pre-design phase and continuing through the construction of a project. The A-E will agree to accept the relationship of trust and confidence, and to commit to the Government to cooperate with the CMAR and to furnish the requisite skill and judgment to further the interests of the Government.
A-E SOW
The CMAR is the contractor selected to assist the Government in reviewing the constructability of the design and in managing the overall construction of the associated project. The CMAR’s primary responsibility will be meeting the Government’s goals relating to scope, budget, schedule and quality. The CMAR provides managerial, technical, administrative, and quality control services to assist the Government in achieving these goals, as well as building the project.
The CMAR assists the Government during the design phase by reviewing and evaluating the construction documentation. The CMAR is required to work with the A-E and the Government in a cooperative team effort to develop a quality design. The CMAR is to notify the Engineering Project Manager (EPM) and the CO of all issues brought to the attention of the A-E and of the A-E’s response to each. The CMAR notifies the EPM if design submissions appear inadequate.
Most importantly, the CMAR makes the EPM aware of any issue that has the potential to jeopardize the project’s goals relating to scope, budget, schedule, and quality. The CMAR’s principal tasks during the design phase include, but are not limited to, the following:
• Conducting or participating in VE exercises
• Controlling schedules
• Keeping records
• Performing administrative and other services as defined in the CMAR’s scope of work
• Preparing cost estimates
• Reconciling cost estimates
• Reporting on progress
• Resolving problems
• Reviewing plans and specifications
4.0 STANDARD A-E SERVICES REQUIREMENTS
4.1 Compliance with Codes And Standards
4.1.1 General
A. The project design under this contract shall comply with the requirements of the current ARS Facilities Design Standards (P&P 242.1M-ARS) (FDS), and with the applicable national, state, and local building codes, standards, and guide specifications. The A-E is responsible for obtaining copies of all applicable codes and standards from the issuing authorities.
B. In addition to using the applicable national model code as the basis for minimum standards, the A-E shall incorporate into the project
A-E SOW
design any special requirements which are related directly to local practices or circumstances, and which do not conflict with ARS policy.
C. In accordance with Public Law 100-678, the applicable code authorities must be offered the opportunity to review the designs for ARS projects. To comply with this law, the FD requires that the A-E document its code conformance by submitting to the appropriate code officials for review all design submittals called for in the PRD, in accordance with the following procedures.
The A-E shall request the Local Authority (LA) in writing to review the plans and specifications for compliance with local codes, etc.
Depending upon the response of the LA, the A-E shall take action as described below:
1. No action from the LA. The LA does not review plans and specifications for Federal projects. The A-E shall provide to the CO a memo to document the Government’s effort to coordinate with the LA, and the LA’s declining the offer.
2. Action by the LA – No Fee. The LA will review the design documents and provide comments at no cost to the Government. In general, comments made by the LA that ask for changes in the design shall be considered recommendations, but if the changes are required by the local code, they should be incorporated into the design.
Those changes or revisions not required by the applicable national model code are subject to discussion within FD, especially those impacting cost and schedule. The A-E shall submit for ARS review all comments made by the LA as well as the A-E response.
3. Action by the LA – Fee Assessed. The LA will review the design and provide comments, but it will require a fee for the staff hours required to provide these services.
a) The LA declines to review the design without payment for the review services. The A-E documents its effort to obtain the LA’s review of its plans and specifications, noting that the services could not be obtained without payment for review services.
b) The LA declines to review the design without payment for the review services and states that a construction permit cannot be issued unless its review process is completed. The A-E shall inform the CO in writing
A-E SOW
19 November 2019 with a recommendation for payment.
4.1.2 Conflict Between Codes and ARS Requirements
A. All conflicts between the design requirements of ARS and the requirements of national, state, or local codes, shall be resolved by designing for the most stringent requirement.
B. Any request by the A-E to deviate from the code or to use equivalent equipment, materials, or means or methods must be submitted through the EPM to the Chief, Facilities Engineering Branch for approval no later than the 35 percent design submission.
C. The request for a waiver must cite the standard or code being impacted, clearly describe the proposed deviation or the equivalent concept, reasons for the request, any associated cost impact, any impact the deviation would have on the project, and supporting rationale.
D. The EPM or AOE will coordinate the request with the appropriate FD Branch and provide a response to the A-E.
4.2 Web Portal Project Management System
The A-E, the Government, the Design Review A-E (DR), and the Construction Contractor (CC) may be required by contract to use the ARS-adopted Web portal system, Microsoft SharePoint, for document management throughout the project. A PowerPoint presentation providing information about this Web portal system can be found at:
https://www.eauth.usda.gov
4.3 Project Site Visits
4.3.1 The A-E shall make site visits and investigations as needed to develop a thorough understanding of existing conditions, and to ensure the accurate representation of all existing conditions affecting the scope of the project.
4.3.2 Site inspections shall be performed by professional architectural and engineering disciplines with the education, training, and experience appropriate for the project.
4.3.3 Site inspections shall be coordinated with the Research Program Representative (RPR), or a person designated by the RPR, to ensure adequate and appropriate scheduling. The A-E shall https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fftp.arsnet.usda.gov%2Fhome.html&data=02%7C01%7C%7Ccb9c2bfbe43d4a97029a08d76d350340%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C0%7C0%7C637097946757812653&sdata=0uasHVcxmp6LSvP8X0z0NU8TCR1fIOYUUe5Y6tsiK2Y%3D&reserved=0
A-E SOW
19 November 2019 adhere to the location security requirements and restrictions. A-E personnel shall present Government issued photo identifications to gain access to facilities.
4.3.4 The Government will make available to the A-E its record drawings and other relevant documents. The A-E will evaluate these drawings and make copies of those applicable to the project. The A-E shall advise the EPM of critical areas where test pits or other testing methods are recommended.
4.4 Document Requirements
4.4.1 General
A. The construction drawings and specifications must reflect the project’s particular site conditions and available construction period and must depict and describe the work so that the project can be readily constructed. To ensure this, the A-E shall have experienced construction engineers review and provide technical input to the drawings and specifications as they are being developed. This input shall be summarized and provided to ARS in the design analysis.
B. Final documents submitted for archival purposes shall include a copy of the Record Drawings and Specifications in digital format on a CD or DVD disc and by email or Web portal. The specifications are to be submitted in MS Word (1 copy) and Portable Documents Format [PDF] (1 copy), and the drawings are to be submitted in DWG and PDF drawing format.
C. Construction documents (drawings, specifications, and attachments) shall be submitted to the CO in PDF format.
These documents will be uploaded to the Contract Opportunities (FBO) Web site (https://sam.gov/content/home) by the CO.
1. Drawings shall be full size. The PDF file shall include bookmarks with a drawing number and title provided for each drawing. Separate files shall be provided for each drawing discipline (e.g., architectural, mechanical, electrical, plumbing, telecommunication, etc.). File size shall be no greater than 10mb. Files greater than 10mb should be divided into multiple files.
A-E SOW
2. Specifications shall be bookmarked with section numbers and section titles. File size shall be no greater than 10mb. Files greater than 10mb should be divided into multiple files.
4.4.2 Drawings
A. Drawings shall be prepared in conformance with the
“National CAD Standard”. Refer to www.nationalcadstandard.org.
B. Standard drawing size shall be 24 x 36 inches or 30 x 42 inches unless otherwise directed. ARS will provide sample cover sheets and title block sheets in electronic format.
Requests to deviate from the standard size shall be submitted to the CO.
C. The cover sheet shall include a vicinity map showing the project’s general position in relation to an existing site, or in the case of a new site, to the surrounding highways. A location map shall be provided also, showing the placement of the project’s elements relative to the existing buildings or other features on the site. All maps shall show graphic scales, north arrows, and appropriate legends.
D. Drawings shall be accurately dimensioned, with all work completely noted, and with legends provided for all symbols, materials, and abbreviations used on the drawings. Details, sections, elevations, and plans shall be identified and thoroughly cross-referenced.
E. Schedules shall be provided on the drawings for doors, windows, and finishes, and for mechanical, electrical, and Telecom equipment.
F. The A-E shall affix its professional seal and signature to the final original drawings. This seal shall be that which would be required by the state or district having jurisdiction where the project work is to be performed.
4.4.3 Specifications
A. Specification organization shall follow the format of the
Construction Specifications Institute (CSI). Numbering of sections within the divisions and section format shall follow CSI recommendations.
http://www.nationalcadstandard.org/
A-E SOW
19 November 2019
B. The cover of each volume shall bear the name of the project, the contract number, the volume number, the name of the A-E firm, and the date of preparation.
C. At the 95 percent complete design stage, a register of all required contractor submittals, with reference paragraphs, dates and action fields shall be provided in a separate section at the beginning of the specifications. The A-E shall also provide the register in Excel file format.
D. The Unified Facilities Guide Specifications (UFGS) have been adopted as the standard specification for all ARS-FD administered projects. The A-E can obtain current UFGS masters at: http://www.wbdg.org. Should the UFGS have more than one version of a particular section, the one used by the Naval Facilities Engineering Command (NAVFAC) shall be used.
E. To help the USDA meet its project-specific environmental goals, the A-E shall review the Federal Green Construction Guide for Specifiers and require the CC to use bio-based and bio-preferred products to the maximum extent possible. This Guide can be found at:
https://www.wbdg.org/ffc/epa/federal-green-construction-guide-specifiers. The A-E shall also refer to https:// www.biopreferred.gov/BioPreferred/
F. The use of “SpecsIntact” is strongly recommended.
SpecsIntact (Specifications-Kept-Intact) is an automated system for preparing standardized specifications. SpecsIntact can be accessed online at:
https://www.wbdg.org/dod/specsintact When specification sections are required that do not exist in UFGS, or, when it is determined that the UFGS section does not adequately address the ARS requirement, the A-E shall prepare a new specification section conforming to the three-part CSI format.
The A-E shall notify the CO of any deviations or additions to the UFGS and shall request formal approval for the deviation.
G. Outline specifications listing all of the specification sections intended for use in the project may be prepared as part of the 35 percent design submittal. Outline specifications shall be organized by CSI divisions and sections, and shall convey the type and quantity of construction, construction http://www.wbdg.org/design/greenspec.php http://www.usda.gov/procurement/programs/biobased/biobaseditems.htm http://www.usda.gov/procurement/programs/biobased/biobaseditems.htm http://www.usda.gov/procurement/programs/biobased/biobaseditems.htm http://www.usda.gov/procurement/programs/biobased/biobaseditems.htm http://www.wbdg.org/references/pa_dod_si.php http://www.wbdg.org https://www.wbdg.org/ffc/epa/federal-green-construction-guide-specifiers https://www.biopreferred.gov/BioPreferred/ https://www.wbdg.org/dod/specsintact
A-E SOW
materials, and equipment proposed. The 50 percent submittal shall consist of marked-up UFGS, with typed supplemental specifications as required by the project work.
A poor mark-up technique, which results in illegible specifications, will require re-submission.
H. Specifications shall reflect sound logic and shall call for materials and construction methods that ensure full and open competitive bidding by interested contractors, manufacturers, suppliers, specialists, and detailers/erectors.
To ensure comprehensive specifications, the A-E shall specify the salient characteristics of materials, equipment, systems, methods, and processes, and must refer to the Material and Workmanship Clause (FAR 52.236-5) contained in the solicitation.
I. The A-E shall exercise continuous review procedures to ensure that the specifications are applicable to the required work, are free of ambiguous generalities, provide the information required by references on the drawings, and are clearly and concisely written to satisfy the requirements of the intended work.
4.4.4 Cost Estimates
A. Detailed cost estimates shall be included with each design submittal. Cost estimates shall follow the CSI specification divisions and shall be itemized by sections within the divisions. Cost estimates will be submitted in both printed and electronic form.
B. Cost estimates shall show the unit costs of material and for each item of work. Cost estimates at the 35 percent submittal may be based on the cost per square foot, broken down by major elements of work. Lump sum cost estimates will not be accepted.
C. The cost estimate shall include a narrative that clearly lists the assumptions used in its preparation (e.g., the assumed start and completion dates of construction, the escalation rate, included and excluded cost elements, the design contingency applied, etc.)
D. Overhead and profit shall be shown as added percentages to the subtotals of the direct cost. All applicable insurance fees, bond costs, sales taxes, etc. shall be included.
A-E SOW
E. With each cost estimate submission, the A-E shall develop and provide a Project Budget Report analyzing the submission’s total estimated construction cost (ECC). The Report shall determine if the project is currently on budget, or if a cost overrun is probable. If it appears that the project is not on budget, the report shall closely analyze the project ECC, precisely identify the reasons why the probable cost overrun has occurred and determine whether or not a complete and usable facility can be designed within the funding limitation. If the A-E believes that one can be, the report will include the A-E’s methodologies and its recommendations for scope reduction and/or changes in the project’s materials, equipment, systems and methods to bring the project’s ECC within the estimated construction contract price. If the A-E believes that a complete and usable facility cannot be designed within the original funding limitation, it shall develop a new project ECC for the complete and usable facility. The A-E shall not proceed to the next design phase until the Government evaluates its recommendations or new ECC and the CO issues a notice to proceed for the next design phase and directions to the A-E on how to bring the cost estimate back within the project budget or adjusts the original estimated construction contract price.
F. At the 50 percent design submittal stage, the FD will convene an internal Design Review Board (DRB). The DRB is responsible for reviewing the ECC submitted by the A-E, and the ECC review comments developed by the Design Review A-E (DR). It the ECC exceeds the project budget, records of the over-budget resolution as described above shall be made available to the DRB.
G. The 50 percent submittal cost estimate shall include:
1. A proposed bid schedule with the base bid item plus additive bid items and/or optional line items.
2. The current version of the Construction Wage Rate Requirements (formerly Davis-Bacon Act) wage determination for the construction site.
3. Sufficient detail to facilitate a review and verification of all cost assumptions.
4. The Project Budget Report determining the project
A-E SOW
budget status, cost overrun, methodology on cost control, and recommendations.
4.4.5 Reports
“Reports” include all submittals other than drawings, specifications, cost estimates, boundary surveys, and topographic surveys.
Reports will be typed on letter-sized (8 1/2 by 11 inch) paper and bound. The report shall be printed on both sides of the sheet. The pages are to be numbered. Bindings are to be plastic, allowing full opening and layout. The report is to be properly organized, indexed, and tabbed. If supplementary drawings are required to produce a complete report, and their contents can be clearly shown on letter sized or 11 by 17-inch paper, they should be bound into the report. If larger drawings are required, they should be placed on 24 by 36-inch sheets, and these will be submitted separately.
Reports submitted for archival purposes will be submitted as described in Section 4.4.1 B above.
4.4.6 Analyses and Calculations
A. These shall be provided with each submittal of the plans and specifications. The degree of completion shall be comparable to that of the plans. Provide applicable descriptions of all assumptions used in the calculations.
B. All computations shall be indexed and arranged in an orderly manner, with appropriate sketches, so that any element of the design can be identified easily.
C. The final design submission shall include a complete set of checked computations marked clearly as final design calculations.
4.4.7 Bid Schedules
A. Bid schedules shall contain the following information:
1. The scope of work to be performed.
2. The identification of the major items of work.
3. A schedule and a construction performance time (in calendar days). The schedule must identify and reflect any involved phasing, the time of actual on-site performance, long lead times that could affect the
A-E SOW
schedule, and parts of any buildings that must be kept operable.
B. Bid schedules shall be provided with the 50 percent design submittal.
C. The scope of the base bid item shall be developed to provide a complete and usable facility. Additive bid items or option items may be identified by the CO or may be design additives recommended by the A-E. When additive bid or option items are used, the A-E shall ensure that such items are indicated clearly on the drawings and described completely in the specifications, and reflected accurately in the cost estimates, bid schedules, and construction performance times.
D. The value of the base bid item should be 90 percent of the
ECC, with at least one additive bid or option item valued at 5 percent of the ECC. It is highly desirable to have the sum of all additive bid or option items approach 10 percent of the ECC. The sum of the final cost estimates for the base bid item and all additive bid or option items must not exceed 100 percent of the ECC.
4.5 Submittals, Reviews, and Approvals
4.5.1 General
A. The A-E shall meet the schedule and requirements for the submittals as described below. If the A-E feels that the Government-proposed schedule is not feasible, it shall develop and propose a detailed schedule for review and approval by the CO as part of the fee negotiation.
B. The schedule must include the time needed for the A-E to conduct its quality control procedures and to develop the cost estimate for each submission.
C. The A-E shall allocate its technical personnel and other resources to meet milestone dates and shall monitor the work of its consultants to ensure concurrent progress.
D. The A-E shall request any input from ARS in sufficient time to allow it to develop and deliver the required information so that the A-E’s work will not be delayed.
A-E SOW
E. Insofar as possible, the A-E shall “work around” areas requiring clarification to minimize any delay to the project.
Should a delay occur, the A-E shall work closely with the CO to regain or minimize lost time.
F. The A-E shall coordinate all submission reviews with
Federal, state and local agencies and utilities, and shall certify its coordination on the submission’s cover letter.
G. The A-E and its consultants must recognize that ARS reviews are general in nature, and that the detailed checking of submittals for technical accuracy, sufficiency, coordination, and quality control is the sole responsibility of the A-E and its consultants. ARS acceptance of the design does not relieve the A-E from any liability for all damages resulting from any negligent performance.
4.5.2 Submission Review Process
A. Copies of the design documents are submitted by the A-E for ARS review at various stages of development as identified in the PRD. Generally, the A-E’s submission will consist of drawings, specifications, a bio-containment narrative when applicable, a cost estimate, Budget Report, analyses and calculations, and its design checklist. Refer to Section 6.5.2 below for a description of the requirements for each submission.
B. The review process takes about four weeks. (See the PRD for the detailed schedule.) The first two weeks are used by the reviewers to study the documents, to develop written comments, and to submit them electronically to the EPM and A-E. During the third week, the A-E reviews all comments and prepares a written response for each, either concurring with the comment, taking exception to the comment (and providing its reason for taking exception), or stating that the comment needs further discussion. The A-E shall distribute copies of all comments received, along with its responses, to all reviewers prior to the design progress meeting held during the fourth week.
4.5.3 Design Progress Meetings
A. The A-E shall conduct the design progress meetings. These meetings will be used to monitor progress, review and approve the design direction, respond to questions and concerns, and approve deviations from the technical
A-E SOW
requirements. The A-E shall provide presentations for alternatives and identify the required decisions.
B. The design progress meetings shall be held at the project site, unless otherwise indicated in the task order.
C. Meetings shall begin at the start of the design phase and shall end with the final design turnover. The schedule of meetings shall be developed by the A-E and the CO.
D. The A-E shall provide a written proposed agenda to the CO for each meeting at least seven calendar days prior to the scheduled date of the meeting.
E. Within seven calendar days after each meeting, the A-E shall provide written minutes of the meeting to the CO, the EPM, the RPR, and the Design Review A-E. The minutes shall be in the following format:
1. Project Title
2. Purpose of Meeting
3. Attendees
4. Description of Discussion
5. Actions Required and Responsible Persons
6. Date Actions Required
7. Distribution of Meeting Minutes
F. The A-E’s staff and consultants attending the meetings shall be qualified and authorized to make technical decisions.
5.0 PREDESIGN PHASE A-E SERVICES
Predesign Phase A-E Services are described below. The PRD will identify the specific services and schedules required by a project.
5.1 Environmental Assessment (EA)
5.1.1 The A-E shall provide all services necessary for the preparation of an EA in accordance with the National Environmental Policy Act (NEPA) of 1969 (P.L. 91-190), as amended; Council on Environmental Quality (CEQ), Guideline 40 CFR 1500-1508; and
A-E SOW
applicable Federal, state, and local regulations. ARS NEPA compliance regulations can be found at 7 CFR 520 and Section 1.3 of the FDS.
The EA shall be developed by a well-qualified and highly experienced individual.
5.1.2 The assessment shall include, but not be limited to: analyses and investigations; determinations substantiated by documents;
retrievable facts; documented records, coordination with Federal, state, and local authorities; and interviews.
5.1.3 The EA shall conclude that either a Finding of No Significant
Impact (FONSI) is justified, or that an Environmental Impact Statement (EIS) is required. If it is determined by ARS that an EIS is required, based on the findings of the EA, a separate competitive solicitation may be issued for the preparation of the EIS. The EA shall also consider conditions during project construction and after project construction completion.
5.1.4 The EA shall follow this outline:
A. The objective of the proposed action
B. Alternatives for accomplishing the objectives of the proposed action
C. The agency-favored alternative
D. The environmental impacts of the proposal and the alternatives.
E. An overview of the site and the surrounding area, and a description of the possible impacts (including public reaction and controversy) of the proposed actions on:
1. The physical characteristics of the site such as: soil erosion by wind or water; stability of the soil surface; the quality of water from a sole source aquifer; aquifer yield and water rights; stream or spring flow; chemical or physical quality of ground or surface water; access to minerals; or the release to the air of particulates or a toxic substance for which there is a National Ambient Air Quality Standard.
2. Social and economic resources and land use, such as:
public health and safety; aquatic life; game animals or
A-E SOW
fish or their taking; aesthetics; undisturbed natural areas or wild and scenic rivers; rare, threatened or endangered species (a consultation with the U. S. Fish and Wildlife Service under Section 7 of the Endangered Species Act is required); critical habitat; species balance, especially among predators; wetlands, flood plains and coastal zones; population; housing supply or demand;
employment; commercial activities; industrial activities;
cultural patterns; or meteorological conditions and air movement patterns.
3. Known or potential historic, cultural, archaeological, and recreational resources; a consultation with the State Historic Preservation Office is required.
4. Utilities and services, such as: power and heating; solid waste management; water supply; or sewer and storm drainage.
5. Transportation and parking.
F. Conclusions and Recommendations
G. Appendix
H. Agencies or personnel consulted
5.1.5 The Government will furnish the following information (if available):
A. Site Plan B. Location Map C. Sample EA
5.1.6 The A-E is responsible for obtaining all additional information necessary to complete the EA.
5.1.7 The A-E shall submit the EA report for ARS review and approval in accordance with the submittals schedule identified in the PRD. See Section 4.4.5 above for reporting requirements.
5.1.8 The A-E shall assist ARS in evaluating and responding to public inquiries on the completed EA.
5.1.9 The A-E shall submit all supporting documentation used in the preparation of the EA.
5.2 Investigative Report or Study
A-E SOW
5.2.1 The A-E shall provide all services necessary to prepare and submit comprehensive investigative reports and studies, e.g., facility condition studies, master plans, energy audits, geotechnical investigations, utility and Telecom studies.
5.2.2 After coordination with the RPR, the A-E shall consult with all appropriate location personnel, facility users and utility service providers to obtain data and information relevant to the project.
5.2.3 Site investigations shall be accomplished by the professional disciplines trained in the area of the related work.
5.2.4 The A-E shall maintain a continuing log of all site visits and investigative procedures used to investigate the work. A copy of this log shall be included with the first submittal of the report or study.
5.2.5 The A-E shall submit the report or study for ARS review and approval in accordance with the submittals schedule identified in the PRD.
5.2.6 The report or study shall fully and accurately describe:
A. The objective of the investigation
B. The sequence of the work performed to accomplish the objective of the investigation
C. The procedures and equipment used in the investigation
D. Analyses and test data, with complete descriptions of all tests performed and test results.
E. Existing conditions affecting the scope or procedures of the work performed.
F. A complete description of the pertinent existing conditions
G. Proposed solutions and recommendations with a complete description of the work to be performed and itemized cost estimates.
H. The data and discussions to support the recommended action proposed for Government approval.
I. Names and qualifications of the personnel who performed
A-E SOW
the investigation.
J. Names, affiliation, and contact information of the personnel who provided input to the investigation.
5.2.7 The report or study shall be prepared and submitted as described in Section 4.4.5 above.
5.2.8 The A-E shall be solely responsible for conducting a thorough investigation and for preparing a complete and accurate report or study.
5.3 Program Of Requirements (POR) Development
5.3.1 The A-E shall provide all services necessary to develop a comprehensive POR for the project.
5.3.2 The A-E shall conduct meetings and interviews with the RPR, research leaders, facility staff and other appropriate personnel Immediately after the award, as required by the PRD. The A-E shall develop draft meeting agendas and submit them for review and approval by the CO at least seven calendar days prior to the date of the meeting. The purpose of the meetings and interviews is to review the Functional Statement developed by the RPR and to develop a thorough understanding of the needs and related technical requirements of the research program. This understanding will help the A-E to develop a design for a facility that can properly support the research program.
5.3.3 The A-E shall coordinate and conduct all meetings and interviews needed for the development of the specified POR submittals.
5.3.4 The POR document shall be prepared and submitted as described in Section 4.4.5 above. The POR typically shall include the following:
A. An Executive Summary
B. The results of the investigation to include:
1. A refined and detailed description of the functional and technical requirements of the proposed project.
2. A detailed description of the existing conditions affecting the proposed project.
A-E SOW
3. A description of the research program, location staffing, and existing research equipment.
4. Draft and final data sheets completed by the A-E detailing the spatial, casework, equipment, and utility requirements of the functional areas.
5. A tabular summary of the spatial, equipment and utility requirements of the functional spaces. Discuss functional relationships, space tabulations, the net-to-gross analysis, bio-safety containment levels, the areas included in net space areas, and compliance with the ARS administrative space requirements.
6. A Design Intent document that describes the basis of design for all buildings and major systems (structural, mechanical, controls, electrical, security, telecom, fire alarm, etc.) and the lists of applicable design criteria.
The narrative will include, but not be limited to, the following:
A. Basic system types and major components, including system interrelationships and any special features or requirements.
B. Design criteria and assumptions, including equipment sizing and selection criteria.
C. The systems’ intended operation and sequences of control.
D. All redundant systems, equipment or features
E. Flow diagrams showing the equipment and piping, ducts, and automatic valve and damper positions for each mode of operation.
F. Noise criteria along with applicable references
(e.g. ASHRAE, etc.).
7. The identification and documentation of the utility services that must be brought or extended to the site (as a cost to the project) and that pose potential budget and/or schedule impacts.
8. If the project involves bio-containment levels, provide flow diagrams for people, supplies, equipment, A-E SOW animals, and waste through the bio-barriers.
9. Brief discussions of the project’s planned energy and water conservation measures, sustainable features, and use of bio-based and bio-preferred products and materials.
10. An Energy Write-Up to Include:
A. A description of the planned energy efficiency measures (EEMs) and the renewable energy measures to be used.
B. A description of the basic HVAC system configuration, with information about its main equipment components, e.g., chillers, boilers, AHUs, VAV boxes, etc.
C. A description of the basic control sequences of the project’s energy saving features.
D. The identity of and documentation for the computer model simulation program that confirms its compliance with the requirements of Appendix G of ASHRAE 90.1-2004.
E. The identity of the consultant and person(s) to perform the modeling.
F. A summary of the requirements of EPACT of 2005 stating that the new facility will have energy consumption levels that are at least 30 percent below the levels set by ASHRAE 90.1-2004, if LCC effective.
11. A code analysis identifying and documenting the governing codes and their application, and documentation of the consultation with local code officials to identify all permits and reviews required for the project.
12. A discussion of the physical security requirements and systems.
13. A discussion of the telecommunications and data system requirements.
A-E SOW
14. A square foot cost estimate, itemized by major project system (site work, foundations, substructure, superstructure, exterior closing, roofing, interior construction, conveying, mechanical, electrical, etc.)
Include all sales taxes, all contractor’s costs and contingencies. Indicate the projected start and completion dates of construction, and all assumed rates of construction cost increases. Identify a Base Bid Item estimated to cost 90 percent of the ECC and Options or Additive Bid Items estimated to cost 10 percent of the ECC. The CO shall provide direction on the allocation of the ECC amount between the Base Bid and Options or Additive Bid Items.
15. The final POR shall discuss and address the pending decisions that need to be considered in the design phase.
16. An estimate of the annual facility operation costs for utilities and maintenance.
17. Minutes of all meetings.
C. Supporting technical data
5.3.5 The A-E shall provide the POR submittals for ARS review and approval in accordance with the schedule identified in the PRD.
5.4 Boundary Survey Services
5.4.1 The A-E shall provide all services necessary to survey the boundaries and to provide the Government with a legal description and drawing for the identified site.
5.4.2 Definitions:
Boundary survey – A mathematically closed diagram of the complete peripheral boundary of a parcel of land. It is thoroughly searched, and field measured, and includes a plat map, a metes and bounds description, and a licensed land surveyor’s signed certification.
Easement – A limited right or interest in the land of another which entitles the holder of the right to some user privilege or benefit out of or over said land.
A-E SOW
Legal description – A description of real property that identifies the real estate according to a system established by approved law.
The legal description must be provided either by the metes and bounds method or by the lot number of a recorded plat that includes any easements or reservations of any portion and must be complete enough that a particular parcel of land can be located exactly.
Metes and bounds description – A narrative way of describing land with its terminal points, stationary markers, and angles by listing the compass directions and distances of its boundaries sufficient to be retraced and drawn.
Parcel – A contiguous quantity of land subject to a single ownership and recorded in the land records as a single piece.
Plat or survey map – A scale drawing, graphically showing the horizontal location, boundaries, easements, and features of an individual parcel of land.
Site - An area of ground where a building, structure or other project is located or proposed to be located, together with surrounding improvements.
Setback or building line – The minimum distance allowed between a property line and a building as required by code or zoning requirements. Safety or security requirements may also determine setback distances.
Topographic survey – A drawing based on field measurements showing the natural and manmade features on, above, and below the surface, and the variations in relief by means of contour lines indicating height above, or below, a fixed datum.
5.4.3 Conduct of boundary survey: The A-E shall provide field surveying as necessary to ensure complete and accurate control points, perimeter and/or centerline descriptions. Research public records for information bearing on the title to the parcel. Search thoroughly for necessary controlling monuments and other physical evidence.
Investigate possible parole evidence supporting positions of obliterated control monuments and record the necessary statements. Take necessary measurements to correlate found evidence. The surveyor may use electronic distance measuring (EDM), Global Positioning System (GPS), steel tape, or a combination thereof to obtain the required distances. Continue this process until determinations for the locations of the lines and
A-E SOW
corners appear to be substantiated by major evidence. All exterior corners shall be monuments and shall be referenced by coordinates to the state’s plane coordinate system, and the entire survey shall be extended or tied into the existing monuments.
Survey work shall be of such precision that the error of closure shall not exceed 1:10,000 and all lines shall be balanced, bearings and distances between corners adjusted, and the overall area computed by the doubled meridian method or other appropriate means as agreed to by the CO. All field survey work shall be performed under the direct supervision of a qualified land surveyor, registered in the state where the parcel of land is located.
5.4.4 Access: The A-E shall be responsible for obtaining the permission of the adjacent property owners as necessary to enter and perform the required work. The current owners shall be contacted prior to the start of any work and shall be allowed to accompany any survey personnel, if they desire.
5.4.5 Plat Map: The A-E shall provide complete and accurate survey maps. The maps shall be based on and plotted by coordinates and accurate survey data. All control points, markers, and monuments shall be clearly referenced and described. Survey lines shall be indicated by bearings and distances. Maps shall be oriented so that true north is to the top or left of the sheet and one street is parallel to one side of the sheet. The map shall be prepared in CADD format on standard size 24 by 36-inch 18 lb. bond paper (minimum) sheets with ½ inch borders on the top, bottom, and right sides, and a 1 ½ inch border on the left side. Drawings shall have a 5 inch by 5-inch title block. The title block shall indicate US Department of Agriculture, Agricultural Research Service, and the name of the facility, city, and state. A 4-inch by 4-inch title block shall be provided on the lower left-hand side of the drawing for the surveyor’s title block. The surveyor’s title block shall contain the name, address, and contact information of the surveyor and the survey date. Provide an area on the drawing for the surveyor’s seal and certification. Should more than one sheet be required, the first sheet shall include an index drawing of the overall area marked to indicate that portion mapped on each individual sheet. A vicinity map shall be provided in the upper right corner to indicate the general location of the land being surveyed. The A-E shall provide a real estate summary map of the site. It is the responsibility of the A-E to contact the local authorities to learn of the documentation needed to record the project site. At least one copy of each survey map shall be suitable for recording the survey at the real property recordation office having jurisdiction over the location of the parcel of land. The drawing shall show the following:
A. The adjusted traverse information for all field traverses.
B. The bearings of boundary lines computed to the nearest second.
A-E SOW
C. The distances of boundary lines to the nearest hundredth of a foot.
D. The central angle, arc length, radius, bearing and distance of the long chord and the interior angles between the long chord and the adjacent boundary lines. In the legal description, also state the direction of radius center with respect to the long chord.
E. Notes to indicate whether the bearings are referred to true or magnetic north. Other references are subject to approval.
F. The area of all parcels in acres to nearest thousandth.
G. All set iron pins and monuments, and their labels.
H. All lot lines (drawn lightly), if the property has been subdivided and given lot and block numbers, and the reference plat and deed book and page of such plat from which the lot and block numbers were taken.
I. The names of the present owners of all parcels and alleys, and the names of parties holding easement rights, and indicate the deed book numbers and page.
J. The names of the owners of adjacent property on the drawing.
K. The established building lines or setbacks according to zoning ordinances and their relation to the property lines.
State the sources of any established building lines or setbacks.
L. All bench marks and their elevations.
M. All permanent features such as buildings and structures, the locations of all adjacent and abounding roads or streets and street curbs, including driveways and entrances, type of surfacing, and limits. For public streets, right-of-way widths and center lines shall also be shown.
5.4.6 Easements and Appurtenances: The map shall show all
easements and other rights affecting the property, including the name of the owner(s) and the recordation information of the instrument. All adjoining landowners must be identified and shown on the map with a last name and address.
A-E SOW
5.4.7 Lines and legends: Property lines for all parcels shall be indicated in heavy lines so as to be the outstanding feature of the map. All symbols used shall be shown in the legend and the graphic scales, and the north arrow shall be on each map. Lines, lettering, and symbols shall be clear and accurate, and the overall map shall be neat in appearance.
5.4.8 Seal and certification: All maps shall be verified correct and contain the signature and seal of a land surveyor registered in the…