This document is a project manual for the construction of an Outpatient Mental Health Clinic at the Colmery-O'Neil VA Medical Center in Topeka, Kansas. The project has a VA project number of 589-501 and a solicitation number of 36C77624B0031.

The key details are:

  • The project involves the general construction, alterations, walks, grading, drainage, and other work as defined in the contract documents.
  • The normal working hours are 8:00 am to 4:30 pm Monday through Friday, with approval required for any work outside of those hours.
  • The contractor is responsible for providing a security plan and following all VA security requirements, including obtaining badges for employees, restricting photography, and maintaining document control.
  • The contractor will be required to coordinate with the Contracting Officer's Representative (COR) on scheduling, inspections, and other project activities.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

CONSTRUCT OUTPATIENT MENTAL HEALTH CLINIC

COLMERY-O’NEIL VA MEDICAL CENTER

TOPEKA, KANSAS

VA PROJECT NUMBER 589-501

MOD 3

100 Percent Contract Documents Submittal

Architect’s Project Number: 13043.20001 Date: March 29, 2024

Construct Outpatient Mental Health Clinic

VA P.N. 589-501

Topeka, Kansas

March 29, 2024

01-01-21

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

SECTION 00 01 10

TABLE OF CONTENTS

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS (NOT USED)

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 03-20

01 33 23 Shop Drawings, Product Data, and Samples 05-17

01 35 26 Safety Requirements 07-20

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 29 Testing Laboratory Services 11-18

01 45 35 Special Inspections 03-19

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 01-21

01 91 00 General Commissioning Requirements 08-19

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 82 11 Removal and Disposal of Asbestos-Containing Materials 01-21

02 83 33.13 Lead-Based Paint 01-21

Hazardous Materials Survey Report 01-21

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 01 00 Maintenance of Masonry 01-21

04 05 13 Masonry Mortaring 10-17

04 05 16 Masonry Grouting 01-21

04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

05 21 00 Steel Joist Framing 11-18

05 31 00 Steel Decking 01-21

05 36 00 Composite Metal Decking 01-21

05 40 00 Cold-Formed Metal Framing 01-21

Topeka, Kansas

00 01 10 - 2

SECTION NO. DIVISION AND SECTION TITLES DATE

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21

07 22 00 Roof and Deck Insulation 01-21

07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21

07 42 13.23 Metal Composite Material Wall Panels 12-20

07 42 93 Soffit Panels 12-18

07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21

07 60 00 Flashing and Sheet Metal 01-21

07 72 00 Roof Accessories 01-21

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 10-17

07 95 13 Expansion Joint Cover Assemblies 01-21

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 31 13 Access Doors and Frames 01-21

08 33 13 Coiling Counter Doors 01-21

08 41 13 Aluminum-Framed Windows, Entrances and Storefronts 01-21

08 44 13 Glazed Aluminum Curtain Walls 04-20

08 71 00 Door Hardware 01-21

08 71 13 Automatic Door Operators 01-21

08 80 00 Glazing 01-21

08 87 00 Architectural Window Films 05-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 26 00 Veneer Plastering 01-21

09 29 00 Gypsum Board 04-20

09 30 13 Ceramic/Porcelain Tiling 01-21

09 51 00 Acoustical Ceilings 12-18

09 51 26 True Wood Lay-In Grilles 04-21

09 65 13 Resilient Base and Accessories 01-21

09 65 19 Resilient Tile Flooring 05-18

09 66 13 Portland Cement Terrazzo Flooring 01-21

09 66 16 Terrazzo Floor Tile 01-21

09 68 00 Carpeting 01-21

Topeka, Kansas

00 01 10 - 3

09 72 16 Vinyl-Coated Fabric Wallcovering 01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 11 23 Tackboards 01-21

10 14 00 Interior Signage 01-21

10 22 26 Operable Partitions 01-21

10 26 00 Wall and Door Protection 01-21

10 28 00 Toilet Accessories 01-21

10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 08-17

12 32 00 Manufactured Wood Casework 01-21

12 36 00 Countertops 12-18

12 36 61.19 Quartz Agglomerate Countertops 06-21

DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14 – CONVEYING EQUIPEMENT (NOT USED)

DIVISION 21 - FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20

22 05 19 Meters and Gages for Plumbing Piping 09-20

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 07 11 Plumbing Insulation 09-19

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 11-19

22 13 00 Facility Sanitary and Vent Piping 09-20

22 14 00 Facility Storm Drainage 09-15

22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20

Topeka, Kansas

00 01 10 - 4

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment 02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 02-20

23 09 23 Direct-Digital Control System for HVAC 08-20

23 21 13 Hydronic Piping 02-20 23 21 23 Hydronic Pumps 02-20 23 22 13 Steam and Condensate Heating Piping 02-20 23 23 00 Refrigerant Piping 02-20

23 31 00 HVAC Ducts and Casings 02-20

23 34 00 HVAC Fans 02-20

23 36 00 Air Terminal Units 02-20

23 37 00 Air Outlets and Inlets 02-20

23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-20

23 81 23 Computer-Room Air-Conditioners 03-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 24 16 Panelboards 01-18

26 27 26 Wiring Devices 01-18

26 29 21 Enclosed Switches and Circuit Breakers 01-17

26 41 00 Facility Lightning Protection 01-17

26 51 00 Interior Lighting 01-18

26 56 00 Exterior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 11 00 Telecommunications Room Fittings 06-15

27 15 00 Communications Structured Cabling 01-16

27 51 16 Public Address and Mass Notification Systems 10-18

27 52 23 Nurse Call and Code Blue Systems 12-20

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

Topeka, Kansas

00 01 10 - 5

28 05 26 Grounding and Bonding for Electronic Safety and

Security 09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security 09-11

28 13 00 Physical Access Control System 10-11

28 23 00 Video Surveillance 09-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12

Geotechnical Report, dated April 29, 2021, by PEC 04-21

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

DIVISION 33 – UTILITIES

33 40 00 Storm Sewer Utilities 12-17

DIVISION 34 – TRANSPORTATION

34 71 13 Passive Vehicle Barriers 04-18

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to Section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contract Work Hours:

i. Normal working hours for this contract will be from 8:00 am to 4:30

pm. (local time) Monday through Friday except for weekends and established Federal Holidays.

ii. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR. Requests shall be submitted via email atleast 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

B. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the Outpatient Mental Health

Clinic at the Colmery-O’Neil VAMC as required by Drawings and

Specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting

Officer..

C. Offices of Atriax Group, as Architect-Engineers, will render certain technical Services during construction. Such Services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by the General Contractor, the Contractor shall notify the Contracting Officer’s Representative (COR) in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than 3 work days unless otherwise designated by the COR.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 2

E. All employees of General Contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by Project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. Work includes general construction, alterations, walks, grading, drainage, and certain other items, as defined and indicated in the

Contract Documents.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and Contract Documents may be obtained from the website where the Solicitation is posted. Additional copies shall be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the

Project.

2. The General Contractor is responsible for assuring that all subcontractors working on the Project (and their employees) also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the Project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the Project site.

2. Before starting work, the General Contractor shall give 1 weeks’ notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this

Section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the Project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 3

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of Project including toolboxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section

08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/subcontractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information.”

2. The General Contractor is responsible for the safekeeping of all

Drawings, Project Manual and other Project information. This information shall be shared only with those with a specific need to accomplish the Project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified.”

Secure such information in separate containers and limit the access to only those who will need it for the Project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the Project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CDs and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information.”

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

Security, access and maintenance of all Project Drawings, both scanned and electronic, shall be performed and tracked through the EDMS system.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 4

“Sensitive information” including Drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions:

1. Vehicle authorization requests shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number (2 to 5) of permits shall be issued for General

Contractor and its employees for parking in designated areas only.

Contractor shall coordinate with VA Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the Work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the Work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 5

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools for Work that transmit vibrations and create noises >80Db require VA COR approval during business hours. Dates and durations shall be submitted

15 working days before work is to be completed. VA COR shall approve dates and durations submitted by GC before work is to begin. If approved, work during business hours shall be 30 minutes of work followed by 30 minutes of quiet time (defined as <80 db and vibration free).

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than 2 work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or utility company involved.

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction

Project for such items as water, sewer, electricity, gas or steam, Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 6 payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day, 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the Contractor’s responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building, or portion thereof. In addition, Contractor shall notify the COR 2 weeks in advance of the proposed date of starting work in each specific area of site, building, or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:

a) Scope of Work: Temporary Main Entrance, Building Addition, Lobby

Renovation, Egress Stairs and Basement Renovation as shown on the

Construction Drawings. Note that Temporary Main Entrance must be fully operational prior to construction in the Lobby.

J. Building 2 will be occupied during performance of the work, but immediate areas of alterations will be vacated.

1. Certain areas of Building 2 will be occupied by Medical Center personnel for various periods as listed below:

AREA PERIOD

2nd floor Duration of Project

3rd floor Duration of Project

Penthouse Duration of Project

First Floor North Wing and Core Remain occupied during construction.

First Floor South Wing Remain occupied during Construction.

Basement Remain occupied during construction.

2. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 7 areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes, whether access or egress, shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc., to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

3. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 shall be temporarily vacated while alterations are performed.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain-link construction fence, 7 feet (2.1m) minimum height, around the construction area indicated on the Drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 15 inches (375 mm). Bottom of fences shall extend to 1 inch

(25 mm) above grade. Remove the fence when directed by COR.

L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 40 degrees F

(4 degrees C) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal), whichever will be required to respond to an alarm from Contractor's employee or watchman.

M. Utility Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 8 pipes, or conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No u�lity service such as water, gas, steam, sewers or electricity, or fire protec�on systems and communica�ons systems may be interrupted without approved task work plan and prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the

Medical Center Director’s prior knowledge and wri)en approval. Refer to Specifica�on

Sec�ons 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11

REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK

RESULTS FOR ELECTRONIC SAFETY AND SECURITY for addi�onal requirements.

2. Contractor shall submit an individual task work plan to interrupt any such services to COR, in writing, 20 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, before the utility interruption notification shall be posted by

Contractor, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.

Interruption time approved by Medical Center may occur at other than

Contractor's normal working hours.

4. The Utility Interruption notification must be posted 11

Federal workdays prior to when the utility interruption work can begin.

5. In case of a Contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 9

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least

1 lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the Work for this Contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all 3, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of the building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by Drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between Drawings and existing conditions at site.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 10

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and COR.

B. Any items required by Drawings to be either reused or relocated, or both, found during this survey to be nonexistent, or in opinion of the

COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by

Government. Provided the Contract Work is changed by reason of this

Subparagraph B, the Contract will be modified accordingly, under provisions of clauses entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-

2) and "CHANGES" (FAR 52.243-4).

C. Re-Survey: 30 days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures, and will form a basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workers in executing Work of this Contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed, they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 11

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which shall remain property of the Government are identified by attached tags or noted on Drawings or in

Specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to reinstallation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work shall be done under this Contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by Drawings and Specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the Work required under this Contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during Contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this Contract

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 12 or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS for additional requirements on protecting vegetation, soils and the environment. Refer to Articles "Alterations," "Restoration," and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of Contract, deliver Work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on Drawings or locations of which are unknown will be covered by adjustment to

Contract time and price in accordance with clauses entitled "CHANGES"

(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SOIL CONDITIONS

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 13 any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the Drawings and in the

Specifications are the result of site investigations by Professional

Engineering Consultants (FAR 52.236-4).

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on

Drawings.

C. A copy of the soil report will be made available for inspection by bidders upon request to the COR at the VA Medical Center, and shall be considered part of the Contract Documents.

D. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other Specification Sections.

The Contractor shall certify that the land surveyor or civil engineer is not 1 who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this Contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government-established baselines and benchmarks, indicated on the Drawings, and shall be responsible for all measurements in connection with the layout. The

Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 14

If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor. (FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, are in accordance with lines and elevations shown on Contract Drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs.

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. Whenever changes from Contract Drawings are made in line or grading requiring certificates, record such changes on a reproducible Drawing bearing the registered land surveyor or registered civil engineer seal, and forward these Drawings upon completion of work to COR.

E. The Contractor shall perform the surveying and layout work of this and other Articles and Specifications in accordance with the provisions of

Article "Professional Surveying Services."

1.14 AS-BUILT DRAWINGS

A. The Contractor shall maintain 2 full-size sets of As-Built Drawings which will be kept current during construction of the Project, to include all Contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the

Contract Drawings. To ensure compliance, As-Built Drawings shall be made available for the COR review, as often as requested.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 15

C. Contractor shall deliver 2 approved completed sets of As-Built Drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the Project by the COR.

D. Paragraphs A, B, and C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a Warranty Management Plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit

2 sets of the Warranty Management Plan. Include within the Warranty

Management Plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The Plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this Contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the Project acceptance and continue for the product warranty period. A joint 4-month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the Warranty Management Plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest Project location.

3. Listing and status of delivery of all certificates of warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 16

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and/or suppliers.

e. Names, addresses and phone numbers of sources of spare parts.

f. Warranties and terms of warranty. Include 1-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

g. Starting point and duration of warranty period.

h. Summary of maintenance procedures required to continue the warranty in force.

i. Cross-reference to specific pertinent Operation and Maintenance manuals.

j. Organizations, names and phone numbers of persons to call for warranty service.

k. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4- and 9-month post-construction warranty inspections conducted by the Government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions shall be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance and Payment Bonds: The Performance and Payment Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 17

Contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to Contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this Section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contact shall be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

Following oral or written notification by the Contracting Officer, the

Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the 3 categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.

Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 18

1. First Priority Code 1: Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours, and work continuously to completion or relief.

2. Second Priority Code 2: Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours, and work continuously to completion or relief.

3. Third Priority Code 3: All other work shall be initiated within

3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

Fire suppression systems.

Fire alarm system(s).

b) Code 1-Air Conditioning Systems

Air conditioning leak in part of the building, if causing damage.

Air conditioning system not cooling properly.

c) Code 1-Doors

Overhead doors not operational, causing a security, fire or safety problem.

2) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

Overhead doors not operational.

Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

Power failure (entire area or any building operational after

1600 hours).

Security lights.

Smoke detectors.

f) Code 2-Electrical

Power failure (no power to a room or part of building).

Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical

Exterior lights not operational.

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 19

h) Code 1-Gas

Leaks and pipeline breaks.

i) Code 1-Heat

Power failure affecting heat.

j) Code 1-Plumbing

Hot water heater failure.

1) Leaking water supply pipes.

k) Code 2-Plumbing

Flush valves not operating properly.

Fixture drain, supply line or any water pipe leaking.

Toilet leaking at base.

l) Code 3-Plumbing

Leaky faucets.

m) Code 3-Interior

Floors damaged.

Paint chipping or peeling.

Casework damaged.

n) Code 1-Roof Leaks

Damage to property is occurring.

o) Code 2-Water (Exterior)

No water to facility.

p) Code 2-Water (Hot)

No hot water in portion of building listed.

q) Code 3

All work not listed above.

E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil- and water-resistant tag approved by the

Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit 2 record copies of the warranty tags showing the layout and design. The date of acceptance and the quality control signature must remain blank until the Project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 20

Warranty Tags

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty contact

Address

Telephone number

Warranty response time priority code

1.16 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property.

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of newly installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the Drawings and Specifications to prevent damage to the equipment and the electrical systems, i.e., transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The

Topeka, Kansas 01-01-21

March 29, 2024

01 00 00 - 21 electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection, including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal use shall be replaced with identical…