Attachment 1 - SOW-High Density Mobile Storage v3.docx

DOCX document 35 KB Posted

Attached to
High Density Mobile Storage System - Amendment 02 Federal contract opportunity
Solicitation number
W912LC-25-Q-0014
Issued by
Department of the Army Colorado Army National Guard

About this file

This Statement of Work outlines requirements for a High Density Mobile Storage System at the Colorado Army National Guard Field Maintenance Shop 7 in Watkins, CO. The system must facilitate storage of tools, reparable parts, office supplies, and secure filing, consisting of 12 double-sided mobile carriages and 2 double-sided static platforms that fit within a 50' x 10' space. The system requires specific configurations of shelving units (76" high x 48" wide x 15" deep) with various combinations of shelves and drawers, including four units with metal rolling security gates and locking mechanisms.

The installation must be completed within 10 business days by certified installers to maintain manufacturer's warranty, with minimal disruption to the operational facility. The project includes procurement, delivery, installation, and cleanup, with carriages capable of supporting 800 lbs per linear foot. Only new equipment is acceptable, with no used or remanufactured products permitted. Work will be performed at 5049 Front Range Parkway, Watkins, CO 80137 during facility hours of 0630-1700 Tuesday to Friday, with payment processed through Wide Area Workflow (WAWF).

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

High Density Mobile Storage System Colorado army national guard

WATKINS, CO | FISCAL YEAR 25

PURPOSE STATEMENT

Field Maintenance Shop 7 (FMS 7) located at 5049 Front Range Parkway, Watkins, CO 80137 requires storage units that facilitate seamless access, security, filing, and stowage. Areas that necessitate attention for more unified storage of materials include tools, reparable parts, office supplies, and secure filing. The high-density mobile storage compartments need to be installed with minimal interruption to workflow for the maintenance facility. The maintenance facility will be operational during the installation of the storage unit; however, will accommodate the Contractor during the different phases of the installation. A total shutdown of the maintenance shop should be avoided, if possible.

SCOPE OF WORK

The vendor will gather requirements via an in-person site visit, develop a quote specific to the available area location at Watkins, CO. As well build, ship, install all equipment, and cleanup of site after installation is completed. A breakdown of required equipment and associated site visits is listed under the “Requirements” and “Salient Characteristics” section. The vendor will warranty their work as required under the “Service and Warranty” section.

PLACE OF PERFORMANCE

FMS 7 is located in a secure, fenced-in facility at 5049 Front Range Parkway, Watkins, CO 80137. Site access will be coordinated prior to any site visits through on-site Government employee. The employee will be responsible for monitoring installation access and monitoring activities during the course of installation. Facility hours are from 0630 to 1700 Tuesday to Friday.

REQUIREMENTS

· Procurement and delivery of all materials required for the completion of this project.

· All labor required for delivery, material offloading, material installation, service work, and warranty work. Labor includes any work required to install storage system.

· All work shall be completed within 10 business days or less, once installation of the storage system begins.

· New Equipment ONLY. NO USED OR REMANUFACTURED PRODUCTS WILL BE ACCEPTED.

· Contractor shall cleanup site after installation is completed.

SALIENT CHARACTERISTICS

· The carriages of each unit will be operated with manual assist controls.

· Carriages shall be capable of withstanding loading of at least 800 lbs. per linear foot.

· Quantity 12 double sided mobile carriages

· Quantity 2 double sided static platforms

· Complete mobile storage system shall fit into an area of 50’ long by 10’ wide

· Ten each: 76 ¼ high x 48” wide x 15” deep, with:

· One shelf that is 11 ¼” high x 48” wide x 15” deep, with dividers

· One shelf that is 12 ¾” high x 48” wide x 15” deep, with dividers

· Four 12” drawers

· One lockable roll-up door 76” high x 96” wide

· Twenty-four each: 76 ¼” high x 48” wide x 15” deep, with:

· Six shelves that are 9 ¾” high x 48” wide x 15” deep

· One shelf that is 11 ¼” high x 48” wide x 15” deep

· Two lockable roll-up door 76” high x 96” wide

· Twenty each: 76 ¼” high x 48” wide x 15” deep, with:

· One each that is 12 ¾” high x 48” wide x 15” deep

· One each that is 14 ¼” x 48” wide x 15” deep

· Three drawers that are 15” x 48” wide x 15” deep

· One lockable roll-up door 76” high x 96” wide

· Two each: 76 ¼” high x 48” wide x 15” deep, with:

· One shelf that is 9 ¾” x 48” wide x 15” deep

· One shelf that is 11 ¼” x 48” wide x 15” deep

· Two shelves that are 12 ¾” x 48” wide x 15” deep

· One shelf that is 24 ¾” x 48” wide x 15” deep

· Four of these storage units need to be lockable. The four that are lockable must have metal rolling security gates (tambour doors/shutter doors) on one side of the storage system to limit access to the system. Each of these storage systems must be movable with rotating spin handles. Locking mechanism installed on these storage units via a pin to floor, to prevent the opening of the system while in its closed secure position.

· Service and Warranty

· Installation must be accomplished by a certified installer of the product offered to maintain manufacturer’s warranty.

· Vendor will warranty work due to improper installation for a minimum of 30 days after installation.

ACCEPTANCE

· All purchased equipment is to be shipped by the vendor.

· All equipment will be capable of the full range of manufacturer specified capabilities.

· Equipment will be damage free after installation.

PAYMENT

· Vendor/Contractor must Invoice through Wide Area Workflow (WAWF)

· Vendor must be registered in WAWF to submit an invoice

· https://wawf.eb.mil

File details come from the government source that posted it. Updated .