This is a Statement of Work (SOW) for the replacement of UV-blocking protective mesh screen curtains at the FAA Logistics Center's Distribution Center Cable Yard in Oklahoma City, Oklahoma.
The contractor must manufacture and/or procure, remove, dispose of, deliver, install, and configure 32 custom UV-blocking protective mesh curtains and associated hardware for two outdoor storage bay structures within the AJW-L600 Cable Yard. Specifically, the contractor shall install 16 curtains on the east storage bay and 16 on the west storage bay. The scope includes conducting a site visit to verify field measurements, removing and disposing of existing deteriorated curtains and hardware, providing all mounting brackets, fasteners, tensioning devices, and support hardware, securing curtains to existing structural steel members, performing final inspections and testing, and removing all debris. Pre-installation requirements include coordinating work schedules with the FAA Contracting Officer's Representative (COR), verifying dimensions and attachment locations, and submitting shop drawings and product specifications for FAA review. The replacement curtains must be designed for continuous outdoor exposure, provide UV protection while allowing airflow, resist tearing and mildew, and withstand Oklahoma weather conditions including wind gusts of 30-40 MPH average with maximum gusts of 60 MPH. The contractor must complete all work within 45 calendar days after receipt of Notice to Proceed, with an expected material lead time of 6-8 weeks and 2 business days for on-site demolition and installation. The contractor shall provide a minimum one-year warranty covering materials, workmanship, and installation defects. All contractor personnel must possess valid REAL ID-compliant identification and comply with FAA security procedures. The prime contractor and any sub-contractors must be United States-owned and operated businesses. Contractor personnel must comply with OSHA regulations, maintain an Accident Prevention Plan, and immediately report accidents or property damage to the COR.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 8.png | PNG image | |
| 6973GH-26-Q-00129 A00001.pdf | ||
| Attachment 4 Addendum One.pdf | ||
| Attachment 7 5811.jpg | JPG image | |
| Attachment 6 5810.jpg | JPG image | |
| Attachment 5 5809.jpg | JPG image | |
| Attachment 1R SOW FAALC 002-LSF WSE Curtains.pdf | ||
| 6973GH-26-Q-00129.pdf | ||
| Attachment 2 Pictures.pdf | ||
| Attachment 3 OK WD 2015-5315.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A t t a c h m e n t 1 P a g e | 1
STATEMENT OF WORK (SOW)
Replacement UV-Blocking Protective Mesh Screen Curtains for NAS Equipment
1. BACKGROUND
The Federal Aviation Administration (FAA) Logistics Center (FAALC), AJW-L230 Facility Management Team, requires the replacement of existing UV-blocking protective mesh screen curtains located at the AJW-L600 Distribution Center Cable Yard at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, Oklahoma.
The existing curtains have been in service for more than fifteen (15) years and have reached the end of their useful life. Many curtains are damaged, missing, or no longer provide adequate protection from ultraviolet (UV) radiation, wind, rain, and other environmental conditions. The curtains protect National Airspace System (NAS) equipment and other FAA assets stored in outdoor storage bays. Failure to replace the curtains will increase equipment deterioration, maintenance costs, and operational risks associated with the storage of mission-critical FAA assets.
2. PURPOSE
The purpose of this requirement is to manufacture and/or procure, remove, dispose of, deliver, install, and configure replacement industrial-grade UV-blocking mesh screen curtains and associated hardware for two outdoor storage bay structures located within the AJW-L600 Cable Yard.
The replacement curtains shall provide protection against UV exposure, weather-related degradation, and airborne debris while maintaining operational accessibility to stored equipment.
3. SCOPE OF WORK
The Contractor shall furnish all labor, supervision, materials, equipment, transportation, tools, permits, and incidental services necessary to complete the work described herein.
The Contractor shall:
a. Conduct a site visit and verify field measurements prior to fabrication.
b. Remove and dispose of approximately thirty-two (32) existing deteriorated curtains and associated hardware.
c. Manufacture/acquire and supply thirty-two (32) custom UV-blocking protective mesh curtains.
P a g e | 2
d. Provide all mounting brackets, fasteners, tensioning devices, and support hardware required for installation.
e. Install sixteen (16) curtains on the east storage bay and sixteen (16) curtains on the west storage bay.
f. Secure curtains to existing structural steel members in a manner that ensures safe operation and resistance to Oklahoma weather conditions.
g. Perform final inspections and testing to ensure proper operation and secure attachment.
h. Remove all debris generated during performance of the work and leave the work area in a clean condition.
4. INSTALLATION AND CONFIGURATION SERVICES
4.1 Pre-Installation
The Contractor shall:
• Coordinate all work schedules with the FAA Contracting Officer’s Representative (COR).
• Verify dimensions and attachment locations before fabrication.
• Submit shop drawings, product specifications, and material data sheets for FAA review and approval.
4.2 Installation
The Contractor shall:
• Remove and dispose of existing curtains and hardware.
• Install new mounting hardware and support systems as required.
• Install all replacement curtains in accordance with manufacturer recommendations.
• Ensure curtains are properly tensioned and aligned.
• Verify curtain operation and secure fastening.
4.3 Post-Installation
The Contractor shall:
• Conduct a final walkthrough with the COR.
• Correct any deficiencies identified during inspection.
• Provide warranty documentation and maintenance recommendations.
• Provide as-built installation documentation if modifications to existing attachment methods are required.
P a g e | 3
5. MATERIAL REQUIREMENTS
The replacement curtain system shall:
• Be same or similar to existing curtains
• Designed for continuous outdoor exposure.
• Provide protection from ultraviolet radiation while allowing airflow.
• Resist tearing, mildew, moisture, and environmental degradation.
• Be suitable for high-wind conditions common to central Oklahoma. According to the
National Weather Service the average wind gusts are between 30-40 MPH with the highest gusts of 60 MPH in Oklahoma City.
• Match or exceed the performance of the existing curtain system, upon approval from requester.
6. PERIOD OF PERFORMANCE
The Contractor shall complete all work within forty-five (45) calendar days after receipt of Notice to Proceed.
Expected schedule:
• Material lead time: Approximately six (6) to eight (8) weeks.
• On-site demolition and installation: Approximately two (2) business days.
7. LOCATION OF INSTALLATION
FAA Logistics Center
Mike Monroney Aeronautical Center (MMAC)
6500 South MacArthur Boulevard, Bldg. 002-LSF, Distribution Center Cable Yard
Oklahoma City, Oklahoma 73169
All on-site work shall be performed at the designated outdoor storage bays, identified by the COR.
8. GOVERNMENT-FURNISHED PROPERTY / DUMPSTERS
The Government will provide access to designated dumpsters located on-site for disposal of removed curtains and associated non-hazardous materials.
P a g e | 4
The Contractor shall:
• Transport demolition debris to Government-designated dumpsters.
• Segregate recyclable materials when directed by the COR, i.e. metal hardware.
• Dispose of hazardous materials, if encountered, in accordance with applicable federal, state, and local regulations.
• Coordinate dumpster use with the COR prior to commencement of demolition activities.
9. SECURITY REQUIREMENTS
9.1 Contractor Personnel
All contractor personnel requiring access to FAA facilities shall:
• Possess a valid REAL ID-compliant driver's license or acceptable federally approved identification.
• Present identification upon request by Government security personnel.
• Comply with all FAA security procedures and escort requirements.
9.2 Company Ownership
For security and operational reasons, the prime contractor and any sub-contractors performing work on-site shall be United States-owned and operated businesses.
9.3 Facility Access
• Access shall be coordinated through the COR.
• Contractor personnel shall remain only within approved work areas.
• Government reserves the right to remove any contractor employee who fails to comply with security requirements.
10. SAFETY REQUIREMENTS
The Contractor shall:
• Comply with OSHA regulations and industry safety standards.
• Maintain an Accident Prevention Plan.
• Use appropriate fall protection when working at elevation.
• Maintain safe pedestrian and vehicle access throughout the work area.
• Immediately report accidents, injuries, or property damage to the COR.
P a g e | 5
11. WAIVERS AND DEVIATIONS
Any deviation from this Statement of Work, approved materials, installation methods, specifications, or schedule shall require prior written approval from the Contracting Officer and COR.
No substitutions of materials, hardware, or fabrication methods shall be made without written authorization.
Requests for waivers or deviations shall include:
• Description of the requested change.
• Technical justification.
• Impact assessment on cost, schedule, performance, and warranty.
• Proposed alternative solution.
12. QUALITY ASSURANCE
The Contractor shall maintain a quality control program to ensure all work conforms to contract requirements.
The Government reserves the right to inspect all work and reject any materials or workmanship that fail to meet specifications.
13. WARRANTY
The Contractor shall provide a minimum one (1) year warranty covering materials, workmanship, and installation defects beginning upon Government acceptance.
The warranty shall include repair or replacement of defective materials at no additional cost to the Government.
14. ACCEPTANCE CRITERIA
The project shall be considered complete upon:
• Successful installation of all curtains and hardware.
• Completion of final inspection.
• Correction of all deficiencies.
• Delivery of warranty documentation.
• Written acceptance by the FAA COR and Contracting Officer.