Attachment 1R SOW FAALC 002-LSF WSE Curtains.pdf

PDF 110 KB Posted

Attached to
SITE VISIT Replacement UV-Blocking Protective Mesh Screen Curtains
Solicitation number
6973GH-26-Q-00129
Issued by

About this file

This is a Statement of Work (SOW) for the replacement of UV-blocking protective mesh screen curtains at the FAA Logistics Center's Distribution Center Cable Yard located at the Mike Monroney Aeronautical Center in Oklahoma City, Oklahoma.

The contractor is required to manufacture, procure, remove, dispose of, deliver, install, and configure thirty-two (32) custom UV-blocking protective mesh curtains and associated hardware for two outdoor storage bay structures. The work includes conducting a site visit to verify field measurements, removing and disposing of approximately thirty-two existing deteriorated curtains and hardware, supplying new curtains with all mounting brackets and fasteners, installing sixteen curtains on the east storage bay and sixteen on the west storage bay, and performing final inspections and testing. The replacement curtain system must be industrial-grade, designed for continuous outdoor exposure, provide UV radiation protection while allowing airflow, resist tearing and environmental degradation, and be suitable for high-wind conditions (average gusts of 30-40 MPH with highest gusts of 60 MPH). The contractor must match or exceed the performance of the existing system upon requester approval. All work must be completed within sixty (60) calendar days after receipt of Notice to Proceed, with material lead time of approximately six to eight weeks and on-site demolition and installation requiring approximately two business days. The contractor must provide a minimum one-year warranty covering materials, workmanship, and installation defects, comply with OSHA safety regulations, maintain an Accident Prevention Plan, and ensure all personnel possess valid REAL ID-compliant identification. The prime contractor and any sub-contractors must be United States-owned and operated businesses. The Government will provide access to designated dumpsters for disposal of removed materials. The project is considered complete upon successful installation of all curtains and hardware, completion of final inspection, correction of all deficiencies, delivery of warranty documentation, and written acceptance by the FAA Contracting Officer's Representative and Contracting Officer.

View the file

Other files

File Type Posted
Attachment 4 Addendum One.pdf PDF
6973GH-26-Q-00129 A00001.pdf PDF
Attachment 8.png PNG image
Attachment 5 5809.jpg JPG image
Attachment 6 5810.jpg JPG image
Attachment 7 5811.jpg JPG image
6973GH-26-Q-00129.pdf PDF
Attachment 3 OK WD 2015-5315.pdf PDF
Attachment 2 Pictures.pdf PDF
Attachment 1 SOW FAALC 002-LSF WSE Curtains.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A t t a c h m e n t 1 P a g e | 1

STATEMENT OF WORK (SOW)

Replacement UV-Blocking Protective Mesh Screen Curtains for NAS Equipment

1. BACKGROUND

The Federal Aviation Administration (FAA) Logistics Center (FAALC), AJW-L230 Facility Management Team, requires the replacement of existing UV-blocking protective mesh screen curtains located at the AJW-L600 Distribution Center Cable Yard at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, Oklahoma.

The existing curtains have been in service for more than fifteen (15) years and have reached the end of their useful life. Many curtains are damaged, missing, or no longer provide adequate protection from ultraviolet (UV) radiation, wind, rain, and other environmental conditions. The curtains protect National Airspace System (NAS) equipment and other FAA assets stored in outdoor storage bays. Failure to replace the curtains will increase equipment deterioration, maintenance costs, and operational risks associated with the storage of mission-critical FAA assets.

2. PURPOSE

The purpose of this requirement is to manufacture and/or procure, remove, dispose of, deliver, install, and configure replacement industrial-grade UV-blocking mesh screen curtains and associated hardware for two outdoor storage bay structures located within the AJW-L600 Cable Yard.

The replacement curtains shall provide protection against UV exposure, weather-related degradation, and airborne debris while maintaining operational accessibility to stored equipment.

3. SCOPE OF WORK

The Contractor shall furnish all labor, supervision, materials, equipment, transportation, tools, permits, and incidental services necessary to complete the work described herein.

The Contractor shall:

a. Conduct a site visit and verify field measurements prior to fabrication.

b. Remove and dispose of approximately thirty-two (32) existing deteriorated curtains and associated hardware.

c. Manufacture/acquire and supply thirty-two (32) custom UV-blocking protective mesh curtains.

P a g e | 2

d. Provide all mounting brackets, fasteners, tensioning devices, and support hardware required for installation.

e. Install sixteen (16) curtains on the east storage bay and sixteen (16) curtains on the west storage bay.

f. Secure curtains to existing structural steel members in a manner that ensures safe operation and resistance to Oklahoma weather conditions.

g. Perform final inspections and testing to ensure proper operation and secure attachment.

h. Remove all debris generated during performance of the work and leave the work area in a clean condition.

4. INSTALLATION AND CONFIGURATION SERVICES

4.1 Pre-Installation

The Contractor shall:

• Coordinate all work schedules with the FAA Contracting Officer’s Representative (COR).

• Verify dimensions and attachment locations before fabrication.

• Submit shop drawings, product specifications, and material data sheets for FAA review and approval.

4.2 Installation

The Contractor shall:

• Remove and dispose of existing curtains and hardware.

• Install new mounting hardware and support systems as required.

• Install all replacement curtains in accordance with manufacturer recommendations.

• Ensure curtains are properly tensioned and aligned.

• Verify curtain operation and secure fastening.

4.3 Post-Installation

The Contractor shall:

• Conduct a final walkthrough with the COR.

• Correct any deficiencies identified during inspection.

• Provide warranty documentation and maintenance recommendations.

• Provide as-built installation documentation if modifications to existing attachment methods are required.

P a g e | 3

5. MATERIAL REQUIREMENTS

The replacement curtain system shall:

• Be same or similar to existing curtains

• Designed for continuous outdoor exposure.

• Provide protection from ultraviolet radiation while allowing airflow.

• Resist tearing, mildew, moisture, and environmental degradation.

• Be suitable for high-wind conditions common to central Oklahoma. According to the

National Weather Service the average wind gusts are between 30-40 MPH with the highest gusts of 60 MPH in Oklahoma City.

• Match or exceed the performance of the existing curtain system, upon approval from requester.

6. PERIOD OF PERFORMANCE

The Contractor shall complete all work within sixty (60) calendar days after receipt of Notice to Proceed.

Expected schedule:

• Material lead time: Approximately six (6) to eight (8) weeks.

• On-site demolition and installation: Approximately two (2) business days.

7. LOCATION OF INSTALLATION

FAA Logistics Center

Mike Monroney Aeronautical Center (MMAC)

6500 South MacArthur Boulevard, Bldg. 002-LSF, Distribution Center Cable Yard

Oklahoma City, Oklahoma 73169

All on-site work shall be performed at the designated outdoor storage bays, identified by the COR.

8. GOVERNMENT-FURNISHED PROPERTY / DUMPSTERS

The Government will provide access to designated dumpsters located on-site for disposal of removed curtains and associated non-hazardous materials.

P a g e | 4

The Contractor shall:

• Transport demolition debris to Government-designated dumpsters.

• Segregate recyclable materials when directed by the COR, i.e. metal hardware.

• Dispose of hazardous materials, if encountered, in accordance with applicable federal, state, and local regulations.

• Coordinate dumpster use with the COR prior to commencement of demolition activities.

9. SECURITY REQUIREMENTS

9.1 Contractor Personnel

All contractor personnel requiring access to FAA facilities shall:

• Possess a valid REAL ID-compliant driver's license or acceptable federally approved identification.

• Present identification upon request by Government security personnel.

• Comply with all FAA security procedures and escort requirements.

9.2 Company Ownership

For security and operational reasons, the prime contractor and any sub-contractors performing work on-site shall be United States-owned and operated businesses.

9.3 Facility Access

• Access shall be coordinated through the COR.

• Contractor personnel shall remain only within approved work areas.

• Government reserves the right to remove any contractor employee who fails to comply with security requirements.

10. SAFETY REQUIREMENTS

The Contractor shall:

• Comply with OSHA regulations and industry safety standards.

• Maintain an Accident Prevention Plan.

• Use appropriate fall protection when working at elevation.

• Maintain safe pedestrian and vehicle access throughout the work area.

• Immediately report accidents, injuries, or property damage to the COR.

P a g e | 5

11. WAIVERS AND DEVIATIONS

Any deviation from this Statement of Work, approved materials, installation methods, specifications, or schedule shall require prior written approval from the Contracting Officer and COR.

No substitutions of materials, hardware, or fabrication methods shall be made without written authorization.

Requests for waivers or deviations shall include:

• Description of the requested change.

• Technical justification.

• Impact assessment on cost, schedule, performance, and warranty.

• Proposed alternative solution.

12. QUALITY ASSURANCE

The Contractor shall maintain a quality control program to ensure all work conforms to contract requirements.

The Government reserves the right to inspect all work and reject any materials or workmanship that fail to meet specifications.

13. WARRANTY

The Contractor shall provide a minimum one (1) year warranty covering materials, workmanship, and installation defects beginning upon Government acceptance.

The warranty shall include repair or replacement of defective materials at no additional cost to the Government.

14. ACCEPTANCE CRITERIA

The project shall be considered complete upon:

• Successful installation of all curtains and hardware.

• Completion of final inspection.

• Correction of all deficiencies.

• Delivery of warranty documentation.

• Written acceptance by the FAA COR and Contracting Officer.