Attachment 1 SOW 668-25-107 V2.pdf
PDF 120 KB Posted
- Solicitation number
- 36C26025R0078
About this file
This Statement of Work (SOW) details a construction services project to replace the roof on Building 33 at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The project involves replacing 4,020 square feet of roofing, including the vestibule, with TPO membrane, FR-50 slip sheet, 5/8" CDX Plywood sheathing, crickets, metal scuppers, and parapet metal cap. The total project period of performance is 90 calendar days, with specific requirements for document transmission, including the use of a secured File Transfer Protocol (FTP) site for electronic submittals.
Key contractual details include the contractor's responsibility to provide all necessary labor, materials, tools, equipment, and supervision, as well as delivering as-built drawings and an Operation and Maintenance (O&M) Manual within 30 days after substantial completion. The solicitation is associated with Project 668-25-107, issued by the Department of Veterans Affairs Veterans Health Administration, with the principal NAICS code 238160 for Roofing Contractors and a product/service code of Z1DA for Maintenance of Hospitals and Infirmaries.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 10 Questions and Responses.pdf | ||
| 36C26025R0078 0002.docx | DOCX document | |
| 36C26025R0078 0001.docx | DOCX document | |
| Attachment 9 Prebid Site visit.pdf | ||
| Attachment 8 - Divisional Price Breakout.xlsx | XLSX spreadsheet | |
| Attachment 6 Contractor Rules of Behavior.pdf | ||
| Attachment 4 B33 Roof As Built 668-25-107.pdf | ||
| Attachment 2 Specifications 668-25-107 V2.pdf | ||
| Attachment 5 PCRA 668-25-107.pdf | ||
| 36C26025R0078_1.docx | DOCX document | |
| Attachment 3 Roof ACM Survey 668-25-107.pdf | ||
| Attachment 7 Wage Determination 20250627.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
Replace Building 33 Roof Mann-Grandstaff VA Medical Center
Spokane, WA May 27, 2025
Attachments to this document include the following. Contact the CO if any items are missing.
• B33 Roof As-Built Drawing
• MGVAMC Building 33 Roof ACM Survey
• Project Specifications
1. General Provide construction services to include labor, materials, tools, equipment, transportation, supervision, and other services necessary for Project 668-25-107, Replace Building 33 Roof at the Mann-Grandstaff VA Medical Center, Spokane, Washington. Total project period of performance shall be 90 calendar days.
2. Statement of Work
2.1 This project will replace 4020 SF of roofing on Building 33 to include the vestibule in accordance with the provided project drawings and project specifications. Replacement to include TPO membrane, FR-50 slip sheet, 5/8” CDX Plywood sheathing, crickets, metal scuppers, and the parapet metal cap.
See Bldg 33 Roof drawing for roof construction.
2.2 Provide commissioning services for the roof replacement.
3. Performance of Work
3.1. Where conflicts exist between this SOW and the project specifications or project drawings, this SOW takes precedence.
3.2. Document transmission.
3.2.1. VA email servers limit file sizes to 5MB per message.
3.2.2. Construction Contractor shall provide a secured File Transfer Protocol (FTP) site to transfer all contract electronic submittals. The contractor shall send a corresponding email to the COR stating a file is ready for review for each electronic submittal FTP upload, an automatic email from the FTP site is sufficient. The FTP site shall be accessible by VA staff using Government Furnished Equipment (GFE).
3.3. As-Built Drawings and Operation and Maintenance (O&M) Manual.
3.3.1. The contractor shall deliver the as-built drawings and owner’s manual to the COR no later than thirty (30) days after substantial completion.
3.4. The government does not guarantee the accuracy or completeness of any of the information provided in the attachments to this SOW. The contractor shall make assessments to determine existing conditions prior to the inception of work.
3.5. The contractor will not have access to any Government-Furnished Equipment.
All equipment and supplies used under the terms of this contract shall be the responsibility of the contractor.