Attachment 10 Questions and Responses.pdf
PDF 41 KB Posted
- Solicitation number
- 36C26025R0078
About this file
This document is a Questions and Responses file for Solicitation 36C26025R0078, a project to replace the roof of Building 33. The document provides clarifications on four key aspects of the roofing project:
Past performance requirements specify that offerors must submit between three and five past performance references. For the roofing work, existing downspouts will be reused, while a new coping cap must be installed. The project also requires complete removal of parapet sheathing, with a mandatory inspection of the underlying framing and notification to the Contracting Officer's Representative (COR) if any damage is discovered during the process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26025R0078 0002.docx | DOCX document | |
| 36C26025R0078 0001.docx | DOCX document | |
| Attachment 9 Prebid Site visit.pdf | ||
| Attachment 1 SOW 668-25-107 V2.pdf | ||
| Attachment 8 - Divisional Price Breakout.xlsx | XLSX spreadsheet | |
| Attachment 6 Contractor Rules of Behavior.pdf | ||
| Attachment 4 B33 Roof As Built 668-25-107.pdf | ||
| Attachment 2 Specifications 668-25-107 V2.pdf | ||
| Attachment 5 PCRA 668-25-107.pdf | ||
| 36C26025R0078_1.docx | DOCX document | |
| Attachment 3 Roof ACM Survey 668-25-107.pdf | ||
| Attachment 7 Wage Determination 20250627.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26025R0078 668-25-107 Replace Building 33 Roof
Questions and Responses
1. Would you please confirm how many Past Performances are required?
Provide at least three but no more than five Past Performances.
2. Will the existing downspouts be reused or replaced?
Downspouts will be reused.
3. In Section 07 01 50.19 "Preparation for Re-Roofing", 3.11 Base Flashing Removal, A, 3 it states "remove coping cap for reuse". Will the existing coping cap be reused or will a new one need to be installed?
New one will need to be installed.
4. In Section 07 01 50.19 "Preparation for Re-Roofing", 3.11 Base Flashing Removal, A it states "remove parapet sheathing and inspect parapet framing". Will you please confirm if this is accurate?
Yes, all sheathing will need to be removed as it is all in scope to replace. While sheathing is off, inspect the framing as well and notify the COR if damage is found