STATEMENT OF OBJECTIVES (SOO)

Install Fiber Optic Cables from ITB 6901 to B7701, B7704 & B7712

Project #: MAHG-2020-00007

Keesler AFB MS

19 April 2022

Prepared By

38 ES/ENII

4064 Hilltop Road

Tinker AFB OK 73145-2713

1.0 SCOPE

This Statement Of Objective (SOO) lists the objectives for the Contractor to engineer, furnish, install and test (EFI&T) a new 36-strand single mode (SM) fiber optic cable (FOC) from Information Transfer Building (ITB) 6901 to hand-hole (HH) 44, and a new 12-strand

SM FOC from HH-14 to each Building (B) B7701, B7704 & B7712. Objectives include

Fiber Optic Distribution Panels (FODP) to be provided and installed in each of the identified buildings to include splicing and termination. Finally, to support the installation of FOC, three (3) new hand holes (HH) and new two-way duct banks with inner-ducts will need to be provided and installed.

The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the objectives as stated in this SOO. All equipment, supplies, and materials provided shall be new and not refurbished.

The Contractor shall provide a Statement of Work (SOW) as part of their proposal incorporating all incorporating all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the objectives stated in this SOO.

The Contractor shall comply with the current TIA telecommunication installation and testing commercial standards as well as, Keesler Guidance for Outside Plant (OSP) Infrastructure;

April 2022 and Keesler Guidance for Premise Wiring; October 2021.

2.0 GENERAL INFORMATION

Additional general information, guidance, and procedures are provided within the attachments for this requirement.

2.1 Period of Performance (PoP)

The PoP for this project shall begin within 10 days after contract award and be completed within 150 calendar days. The award document will be considered the

Notice to Proceed (NTP). A pre-construction meeting will be scheduled after award and should take place within 10 days of contract award.

2.2 Place of Performance

The place of performance is Keesler AFB MS.

3.0 OUTSIDE PLANT REQUIREMENTS

3.1 Measurements

Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.

3.2 New NEMA 4X Enclosure

The Contractor shall install one NEMA 4X enclosure on the outside wall of B7701.

The Contractor shall determine the size of the enclosure needed to satisfy the particular requirement at that location based on the quantity of conduits coming into the enclosure. The contractor shall provide the same quantity of 4” ID sleeve(s) through the building wall. The entry enclosure and riser conduits shall be painted to match the color of the building exterior in the area where it is mounted. Coordinate with 81 CS/SCXP for final mounting location.

3.3 New Fiber Optic Distribution Panel (FODP)

The Contractor shall install FODP’s at the locations below. Coordinate with 81

CS/SCXP for final mounting location.

In ITB 6901: 36-port FODP (Existing Rack)

In B7701: 12-port FODP (Existing Rack)

In B7704: 12-port FODP (Wall Mount)

In B7712: 12-port FODP (Existing Rack)

4.0 OUTSIDE PLANT INSTALLATION

This section describes the underground maintenance hole/conduit system, flexible geotextile multiple cell fabric inner-duct and copper and fiber optic cable installation requirements. The Contractor shall design and install Customer-Owned Outside Plant

Telecommunications Infrastructure in according with TIA-758-B. Each cable installation shall be coordinated with the 81 CS/SCXP so that the impact on the building users is minimized. The sequence of installation is at the Contractor’s discretion.

4.1 Infrastructure Installation

The contractor shall install the following new infrastructure. All new locations and distances identified below are approximate.

4.2 New Hand holes

The Contractor shall install three 4’W x 4’L x 4’H (interior dimensions) hand holes

(to be designated as HH-124D, HH-124E & HH-124F). Coordinate with Base 81 CS for final hand holes placement and numbering scheme prior to installation.

4.3 Duct bank Infrastructure

Install the following 4” HDPE Duct banks

From To

Qty Size

(Inch)

Approx.

Distance

(Feet)

Notes

MH-131 MH-16B 2 4 220 Directional Bore

HH-124C New HH-124D 2 4 590 Directional Bore

New HH-124D New HH-124E 2 4 500 Directional Bore

New HH-124E New HH-124F 2 4 485 Directional Bore

New HH-124F MH-11O 2 4 560 Directional Bore

HH-149C B7701 2 4 300 Directional Bore. Stub-up into new NEMA 4x Enclosure outside wall B7701

4.4 Geotextile Inner-duct (or Inner-duct)

Install three (3) each, 3 inch, 3-cell Geotextile Inner-ducts (9 individual cells per duct) as shown at the table below. Each three cell shall have a separate thread color and one of the three cell must be detectable.

Install the following 3” 3-cell Geotextile Inner-ducts

From To Quantity Approx.

Distance

(Feet)

Notes

MH-131 MH-16B 3 220 In one of new conduits

HH-124C New HH-124D 3 590 In one of new conduits

New HH-124D New HH-124E 3 500 In one of new conduits

New HH-124E New HH-124F 3 485 In one of new conduits

New HH-124F MH-11O 3 560 In one of new conduits

HH-149C B7701 3 300 In one of new conduits

4.5 Fiber Optic Cable Installation

The Contractor shall install single mode (SM), loose buffer tube, water blocked, outside plant (OSP) fiber optic cable (FOC) suitable for underground applications.

The intent is to install the cable in one continuous length, to the extent that it is practical. The cable shall meet RUS 7 CFR 1755.900 criteria; shall comply with industry standards with regard to manufacturers’ cable marking, jacket, rip cords, water blocking, fiber color coding, jacketing materials, etc. In addition, the FOC shall comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and

1550nm.

All fiber optic cables shall be installed in new or existing geotextile inner-duct / inner-duct.

4.6 From ITB 6901 to HH-44

The Contractor shall install approximately 11,500 feet (included Maintenance Loop) of 36-strand SM FOC from ITB 6901 to HH-44. Terminate 36-strand SM FOC in the new 36-port FODP in ITB6901.

ITB 6901 to HH-44

FROM TO

Approx.

Distance

(Feet)

Notes

ITB 6901 MH-131 100 In available inner-duct

MH-131 MH-16B 220 In new Maxcell

MH-16B MH-16A 500 In available inner-duct

MH-16A MH-16C 600 In available inner-duct

MM-16C MH-127 250 In available inner-duct

MH-127 MH-126 500 In available inner-duct

MH-126 MH-125 425 In available inner-duct

MH-125 MH-124 475 In available inner-duct

MH-124 HH-124A 650 In available inner-duct

HH-124A HH-124B 450 In available inner-duct

HH-124B HH-124C 125 In available inner-duct

HH-124C New HH-124D 590 In new Maxcell

New HH-124D New HH-124E 500 In new Maxcell

New HH-124E New HH-124F 485 In new Maxcell

New HH-124F MH-11O 560 In new Maxcell

MH-11O MH-154 665 In available inner-duct

MH-154 MH-153 400 In available inner-duct

MH-153 MH-152 300 In available inner-duct

MH-152 MH-151 500 In available inner-duct

MH-151 MH-150 560 In available inner-duct

MH-150 MH-149 375 In available inner-duct

MH-149 HH-149A 600 In available inner-duct

HH-149A HH-149B 425 In available inner-duct

HH-149B HH-44 250 In available inner-duct

4.7 From HH-44 to B7701

The Contractor shall install approximately 650 feet (Included Maintenance Loop) of

12-strand SM FOC from HH-44 to B7701. Terminate 12-strand SM FOC in the new

12-port FODP in B7701.

FROM TO

Approx.

Distance

(Feet)

Notes

HH-44 HH-149C 275 In available inner-duct

HH-149C B7701 300 In new Maxcell

4.8 From HH-44 to B7704

The Contractor shall install approximately 150 feet (Included Maintenance Loop) of

12-strand SM FOC from HH-44 to B7704. Terminate 12-strand SM FOC in the new

12-port FODP in B7704.

FROM TO

Approx.

Distance

(Feet)

Notes

HH-44 B7704 125 In available inner-duct

4.9 From HH-44 to B7712

The Contractor shall install approximately 800 feet (Included Maintenance Loop) of

12-strand SM FOC from HH-44 to B7712. Terminate 12-strand SM FOC in the new

12-port FODP in B7712.

FROM TO

Approx.

Distance

(Feet)

Notes

HH-44 HH-43 550 In available inner-duct

HH-43 B7712 200 In available inner-duct

5.0 SPLICE: In HH-44, the Contractor shall splice the following three 12-strand SM FOC into new 36 strand SM FOC feeder cable by providing a new splice case

One each 12-strand SM FOC going to B7701

One each 12-strand SM FOC going to B7704

One each 12-strand SM FOC going to B7712