Attachment 1 - SON_27 Jun 24.pdf

PDF 161 KB Posted

Attached to
Cathodic Protection Beale AFB
Solicitation number
FA468624R0032
Issued by

About this file

This document is a Statement of Need (SON) for a federal contract opportunity to repair the cathodic protection system for 7 water supply wells at Beale Air Force Base. The SON provides background information on the existing cathodic protection system, which was previously abandoned, and outlines the scope of work for the contractor to design and install a new complete functional cathodic protection system. Key details include:

The contractor shall provide a 65% and 100% design package, including construction drawings, specifications, and a detailed scope of work. The contractor will be responsible for all necessary coordination, site visits, and reporting to understand the existing site conditions. The contractor shall install the new cathodic protection system in accordance with applicable standards and environmental regulations. The anticipated period of performance is 60 days for design and 90 days for construction. The total estimated cost range for this project is $300,000 to $500,000. The solicitation number is FA468624R0032 and the proposal due date is August 21, 2024.

View the file

Other files

File Type Posted
Solicitation Amendment FA468624R00320002 SF 30.pdf PDF
Solicitation Amendment - FA468624R00320002.pdf PDF
Pre-bid RFIs .xlsx XLSX spreadsheet
Attachment 9 - Sec L - 30 Jul 2024.docx DOCX document
Attachment 8 - Hold Harmless Agreement - Cathodic Protection Wells.docx DOCX document
Solicitation Amendment - FA468624R00320001.pdf PDF
Solicitation Amendment FA468624R00320001 SF 30.pdf PDF
Attachment 10 - Sec M - 30 Jul 24.docx DOCX document
Attachment 3 - Site plan-CP direction - 29 Jan 24.xlsx XLSX spreadsheet
Attachment 7 - Past Performance Questionnaire - Cathodic Protection Wells.pdf PDF
Solicitation - FA468624R0032 - signed.pdf PDF
Attachment 14 - Well Data -Table.JPG JPG image
Attachment 6 - AF 3052 Supplemental guidance.docx DOCX document
Attachment 11 - CONTRACTOR EAL 2024.xlsx XLSX spreadsheet
Attachment 8 - Hold Harmless Agreement - Cathodic Protection Wells.docx DOCX document
Attachment 4 - Cathodic Protection AF Form 813 - 23 May 24.pdf PDF
Attachment 12 - Site Map- Utilities.pdf PDF
Attachment 2 - AF 66 - 29 JAN 24.xlsx XLSX spreadsheet
Attachment 13 - Well CP as-built.pdf PDF
Attachment 5 - AF 3052 Cost Estimate Breakdown.xlsx XLSX spreadsheet
Attachment 10 - Sec M - 30 Jul 24.docx DOCX document
Attachment 9 - Sec L - 30 Jul 2024.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract #: TBD Project Title: Repair Cathodic Protection for Wells Project #: 1135097 Date: 27/June/2024

STATEMENT OF NEED

1. Purpose of section. The Statement of Need (SON) explains the general intent of the contract named above. It documents the major line items of work the Government expects to see accomplished, but it does not attempt to explain the exact details and/or method of execution for the contractor. The Contractor will be responsible for providing specific performance details in their resulting proposal and Statement of Work (SOW).

2. Background Information.

There are 7 water supply wells with approximately 300 ft deep and 16” diameter steel casings, on the well fields area at Beale AFB (See the site plan for location and the table for further wells and casings information). All wells were protected from corrosion by an impressed current cathodic protect (CP) system before, with a central anode bed/rectifier installed in 1971. (The location of the old anode bed is around 600 ft to the south of well #8, and shown on the as built provided), Wells 1,2,4,5, and 6 were bonded by the existing abandoned underground metal pipe which was bonded to the central anode bed/rectifier system. Wells 8 and 9 were combined back to the metal pipe conductor by an overhead bonding wire over the power poles. None of these wells currently have a functioning or operational CP system. In 2023, the overhead power system protecting wells 1,2,4,5, and 6was removed and replaced with an underground wiring system. The CP bonding wire for wells 8, and 9 were also removed when the overhead power lines were taken down.

The transformer and rectifier, that fed into the central CP system, were also removed at that time. Outside of the provided as-builts, there is no additional information or specifications detailing the transformer and rectifier.

(See the attached as built of the old CP system).

Well #1 has been replaced recently and below is the updated information.

Casing depth – 300ft.

Casing width – 16” Existing Underground Utilities and site conditions.

The underground in-service water, Electrical and communication utilities are existed within the navigating gravel roads on the area (See the attached map for the locations of the underground utilities). Site verification of the underground utilities within the fenced area around wells is required prior to digging.

3. General Scope: The Contractor shall furnish all labor, supervision, transportation, materials, testing, analysis, reports, permits, hauling, tools, equipment, and professional services to complete the design and construction of the project in accordance with the contract documents.

4. Scope of work:

a. Design: All plans and specification shall be prepared and stamped by a CP engineer and the CP engineer of record shall oversee all aspects of construction and installation.

b. The contractor shall provide a complete set of 65%, and 100%+IFC design phases including construction drawings, Specifications, detailed scope of work, design analysis, and bases of design report to construct and install a complete usable CP system for wells 1,2,4,5,6,8, and 9.

c. Design shall conform with the applicable standards and environmental regulation listed below in section 19.

d. Contractor shall perform all necessary coordination, meetings, site visits, survey, studies and reporting to clearly understand the historic and existing site condition to provide an appropriate design.

e. Contractor shall provide the as-built design drawings at the project completion.

5. Construction/Installation. Contractor shall install a complete functional cathodic protection system to protect casings of wells 1,2,4,5,6,8, and 9, according to the design, specification (provided by contractor), and following the applicable codes and standards provided in section 19.

6. Environmental/Permits: Contractor must comply to the regulations and requirements provided through the AF-813 including digging restrictions, protection of sensitive species, wetlands, BMP (Best Management Practices), safety, security, road closing and so on. Sensitive habitat surrounds the work areas and requirements to protect these habitats are extensive. A detailed review of the AF813 and conformance with requirements is essential to a successful project.

AF-103, including dig permit will also be required prior to start of construction. AF-103 is typically filed, processed, and signed by Beale AFB. Contractor shall provide the work clearance with reference number from USA North and submit to CE, 30 days before beginning of construction.

7. Government Furnished Equipment and Documents. the following documents are Attached with the bid documents are provided for information purposes only. All information is to be field verified.

• A site plan, showing the locations of wells and the existing underground utilities, in the area.

• As built drawing showing the old CP system.

• Environmental regulations permit (AF-813) dated 8 May 2024

• Wells data table.

8. Timetable requirement. Since a topographic or high-level geotechnical survey for this contract is not required; we anticipate 60 days for the design and 90 days for construction works to be completed. Extension or change of the schedule will be negotiated and approved up on requirement and needs of the request.

9. Authorized Work. Work shall be accomplished in accordance with all contractually incorporated documents. Any work that is accomplished outside of the contractual documents, unless authorized by a contracting officer, is accomplished at the contractor’s own risk.

10. Base Access. All contractor vehicles must enter the base via the Wheatland Gate and shall be subject to inspection. All contractor personnel must obtain base passes or be listed on the Entry Access List (EAL) throughout duration of work performance. Expect 72 hours minimum to process EAL’s. Any persons in the EAL are required to bring two (2) forms of identification or REAL ID to access the base.

11. Waste disposal. All waste materials will be disposed of and removed off base by Contractor. Contractor will practice good housekeeping during project. The Contractor shall provide C&D Debris Diversion and Disposal Report to CEIE.

12. Materials Submittals. The Contractor shall fill out and submit a Schedule of Materials Submittals (AF 66) with the proposed project schedule. A template will be provided, and contractor can add as needed by the design requirements. Submittals must contain detailed information of the item, and links to the applicable standards used for the material or equipment.

13. Utility Outages. All utility outages need to be thoroughly coordinated in advance.

Outage plan will be approved within two to four weeks from the date submitted. It is requested that building outages for tie-in of the switches be conducted after hours or on weekends. All precautions will be taken to protect existing equipment from damage.

Outages will be coordinated through the AF form 103 approval by base.

14. Tests and Reports: Contractor is responsible to perform the required tests and provide report for government acceptance. Project’s specification shall include the list of tests required for the project by following the UFGS 26-42017.

15. Contractor is responsible to provide the weekly work progress report including two weeks look ahead expectancy.

16. Project Management. Contractor is responsible to conduct weekly or bi-weekly coordination meeting, with Base personal, provide notes and work on the action items that comes up at the meetings.

Submittals, permits, reports, and other relevant documentations must be provided and submitted in a timely manner.

17. Expected Warranties and Guarantees. All warranties and guarantees will be industry standards. This will include as a minimum a standard 1-year warranty of construction in addition to any standard manufacturer's warranties more than this period.

18. Licenses and permits. (If identified), Contractor is responsible for acquiring all necessary permits and paying all required fees for the legal construction and operation of any installed equipment or systems.

19. APPLICABLE STANDARDS. The Contractor shall adhere to the following requirements including all recommended practices documented in these standards.

Although some publication dates are given, work shall be in compliance with current references and standards. All work accomplished by the Contractor shall comply with these criteria unless a waiver is obtained from the Air Force when conditions warrant such consideration, including but not limited to the following references:

i. Unified Facility Criteria (UFC) Sections 3 570 01, 3 570 02, 3 570 06.

ii. UFGS 26 42 13, and 26 42 17.

iii. AF-813, environmental regulations.

iv. DOD Building Codes- UFC 1-200-01, Chapter-4

v. ASTM Standards where applicable.

vi. ANSI Standards where applicable.

vii. AFR 127-12 Air Force Occupational Safety & Health

viii. National Electrical Code where applicable.

ix. Department of Defense (DOD) 8500.01 Cyber Security

Where Code previsions or ordinances conflict or overlap, whichever imposes the more stringent regulation shall prevail.

Contract #: TBD