This is a Schedule of Items pricing template for a federal contract solicitation for the Black Hills National Forest Tatanka Hotshot Base Siding Replacement project. The schedule establishes the basis for contractor pricing and cost proposals.

The solicitation includes three base bid items, all measured as lump sum (LS) work with a quantity of one unit each: Mobilization, Demolition, and Installation. Contractors must provide total pricing for each base bid item. Additionally, the solicitation includes one increase/decrease bid item for Sheathing (Item ID1), measured in each (EA) units with a base quantity of 10 units. Contractors are required to provide a unit price for sheathing to accommodate potential changes in quantity higher or lower than the listed quantity, as specified in the project specifications. The final total cost is calculated by summing all base bid items and any applicable increase/decrease bid items with adjusted quantities.

View the file

Other files

File Type Posted
1240LT26Q0034 A0002.pdf PDF
Tatanka Siding 2nd Site Visit SignIn.pdf PDF
Q and A.pdf PDF
Tatanka Siding Site Visit SignIn.pdf PDF
Attachment 1 SOI v2.pdf PDF
1240LT26Q0034 A0001.pdf PDF
1240LT26Q0034.pdf PDF
Attachment 2 SOW.pdf PDF
Attachment 3 Specs.pdf PDF
Attachment 4 Drawings.pdf PDF
Attachment 6 Wage Determination.pdf PDF
Attachment 5 Map.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF ITEMS

BLACK HILLS NATIONAL FOREST

TATANKA HOTSHOT BASE SIDING REPLACEMENT

Item Number Description Type

Msrmt Unit Quantity Unit Price Total

Black Hills NF Tatanka Hotshot Base Siding Replacement

THE FOLLOWING ARE BASE BID ITEMS:

1 Mobilization. LS LS 1 $ $ 2 Demolition LS LS 1 $ $ 3 Installation LS LS 1 $ $

THE FOLLOWING ARE INCREASE/DECREASE BID ITEMS: Contractor to provide unit price for Change in Quantity higher or lower than Quantities listed as stated in the project Specifications

ID1 Sheathing AQ EA 10 $ $

TOTAL = $

Description:
Unit:
Quantity:
Unit Price:
Total:
Black Hills NF Tatanka Hotshot Base Siding Replacement:
THE FOLLOWING ARE BASE BID ITEMS:
Mobilization:
fill_9:
fill_10:
Demolition:
fill_12:
fill_13:
Installation:
fill_15:
fill_16:
Sheathing:
fill_18:
fill_19:
TOTAL:

File details come from the government source that posted it. Updated .