About this file

This document outlines requirements for demolition and removal services at Shaw Air Force Base. The solicitation seeks bids for six line items involving demolition of underground storage tanks and associated infrastructure at Facility 111, including removal of dispensers, underground piping, and a pump. There are also two optional line items to address potential contaminated soil and water removal. The period of performance is not specified. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Omaha as solicitation number W9128F-24-R-0018. Pricing is to be provided on a firm-fixed-price basis for all line items.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Demolition Diesel Underground Storage Tank – Facility 111OSDU

FFP

All work to demolish underground storage tank.

FOB: Destination

PSC CD: XXXX

NET AMT _____________________________

0002 1 Job Demolition Jet-A Underground Storage Tank – Facility 111OSUJ

FFP

All work to demolish underground storage tank.

0003 1 Job Demolition of Fencing, Concrete Pads, and Roads – Facility 9085

FFP

All work to demolish and remove all concrete and fencing from area to include backfill and leveling.

0004 1 Job Removal of Diesel and JET-A Dispenser from site to storage location – Facility 111

FFP

All work to remove Dispensers and transfer to storage location provided by installation. Work should include demolition of any items that cannot be reused.

0005 1 Job Removal of underground Piping from UST to dispensers – Facility 111PLFU

FFP

All work to remove and scrap underground piping at fueling site. Work should include demolition of any items that cannot be reused.

0006 1 Job Removal of Pump – Facility 111PLSF

FFP

All work to remove pump. Work should include demolition of any items that cannot be reused.

OPTIONAL CLINS

0007 CY $_____/CY

Removal of Contaminated Soil

FFP

All work complete for stockpiling, handling, and proper disposal of petroleum contaminated soil and notification to regulatory agencies for petroleum contaminated soil that cannot be reused on-site for backfill purposes. The Government reserves the right to exercise this option at any time during the contract performance period. Exercising this option will not extend the period of performance.

0008 GA $____/Gallon Removal of Contaminated Water

FFP

All work complete for containerizing, proper disposal, and notification to regulatory agencies for petroleum contaminated groundwater that cannot be discharged to sanitary sewer. The Government reserves the right to exercise this option at any time during the contract performance period. Exercising this option will not extend the period of performance.