This is a Performance Work Statement (PWS) dated March 3, 2026, for Unexploded Ordnance (UXO) dud survey and clearance services at Remagen Hand Grenade Range, Fort Jackson, South Carolina. The contract is structured as a non-personal services contract with on-call capability, allowing the Government to issue task orders as needed for range clearance operations. The contractor must provide all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary to perform systematic sweeps to locate and clear explosive hazards on or below the surface in accordance with applicable safety and environmental regulations.

The primary deliverables and performance requirements include: (1) Surface sweep and clearance using 100% metal detector coverage of designated areas within the four hand grenade throwing bays; (2) Sub-surface sweep and clearance using geophysical detection instruments to specified depths, with investigation of all anomalies through careful excavation; (3) On-site demolition of all located explosive hazards consolidated to minimize demolition events, conducted per AR 385-63; and (4) Final Clearance Reports submitted within 24 hours of completing each service call. All deployed personnel must maintain current EOD or civilian UXO Technician certification (DDESB TP-18 compliant). The contractor must establish a Quality Control Plan within 10 days of award, submit an Accident Prevention Plan and Activity Hazard Analysis prior to work initiation, and complete required training including Anti-Terrorism Level I and iWATCH within 30 days. The Government will provide a staging area, parking, equipment parking space, and electrical outlets for battery charging. Contractor support hours are 0700-1800 Monday through Sunday as required, with government facility hours 0700-1630 Monday-Friday excluding federal holidays. All contractor employees require Fort Jackson installation access through the Installation Access Control System and must complete Level I OPSEC training within 30 days of employment.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWS DATE: 3 March 2026

PERFORMANCE WORK STATEMENT (PWS)

Unexploded Ordnance (UXO) Dud Survey and Clearance Services

Remagen Hand Grenade Range, Fort Jackson, SC

PART 1 – GENERAL INFORMATION

1. GENERAL: This is a non-personal services contract to provide Unexploded Ordnance (UXO) dud survey and clearance at the Remagen Hand Grenade Range. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 DESCRIPTION OF SERVICES/INTRODUCTION: The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, and other non-personal services necessary to perform on-call Unexploded Ordnance (UXO) range sweep and clearance services for Remagen Range at Fort Jackson, SC.

1.2 BACKGROUND: U.S. Army training activities necessitate the use of live ordnance on various ranges. To ensure continued safety and make training areas available for different types of use, it is periodically necessary to conduct systematic sweeps to locate and clear any potential explosive hazards that may remain on or below the surface. This PWS establishes the requirements for a flexible, on-call capability to perform these clearance operations.

1.3 SCOPE: The Contractor shall perform scheduled or on-demand range clearance operations as directed by individual task orders. This includes providing EOD/UXO-qualified personnel to systematically survey designated areas, identify all surface and sub-surface explosive hazards, and safely demolish any located ordinance onsite in accordance with all applicable safety and environmental regulations.

1.4 GENERAL INFORMATION:

1.4.1 QUALITY CONTROL PLAN (QCP): The Contractor shall develop and maintain an effective QCP to ensure services are performed in accordance with this PWS. The Contractor shall implement procedures to identify, prevent, and ensure non-recurrence of defective services. The QCP shall be submitted to the Contracting Officer (KO) via the Contracting Officer’s Representative (COR) within ten (10) calendar days after contract award [Deliverable A001]. The Government will review and provide acceptance or comments within five (5) calendar days. If comments are provided, the Contractor shall submit a Final QCP within five (5) calendar days of receipt. The QCP shall, at a minimum, detail:

(a) An organizational chart showing lines of authority and the names, qualifications, and responsibilities of the Quality Control Team.

(b) Procedures for monitoring performance to ensure compliance with all contract deliverables, timelines, and specifications.

(c) Procedures for ensuring all contractor personnel possess and maintain required qualifications and certifications.

(d) A plan for identifying, investigating, correcting, and preventing non-conforming performance.

(e) A method for saving all Quality Control related documents for the life of the contract plus five (5) years.

1.4.2 QUALITY ASSURANCE: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP).

1.4.3 RECOGNIZED HOLIDAYS: Work shall not be performed on U.S. federally recognized holidays unless directed by the KO.

* New Year’s Day (January 1)

* Martin Luther King Jr.’s Birthday (Third Monday in January)

* Washington’s Birthday / Presidents’ Day (Third Monday in February)

* Memorial Day (Last Monday in May)

* Juneteenth National Independence Day (June 19)

* Independence Day (July 4)

* Labor Day (First Monday in September)

* Columbus Day (Second Monday in October)

* Veterans Day (November 11)

* Thanksgiving Day (Fourth Thursday in November)

* Christmas Day (December 25)

1.4.4 OPERATING HOURS:

* Government Facility Office Hours: 0700 to 1630, Monday through Friday, excluding federal holidays.

* Contractor Support Hours: The Contractor shall provide support between the hours of 0700 to 1800, Monday through Sunday, as required to fulfill the tasks of this PWS. Services are not required when the Government facility is closed due to emergencies or administrative closings.

1.4.5 PLACE OF PERFORMANCE: The work will be performed at the Remagen Hand Grenade Range located within the Fort Jackson Training Complex, Fort Jackson, South Carolina.

1.5 SECURITY REQUIREMENTS:

1.5.1 INSTALLATION ACCESS: Contractor employees shall comply with all applicable installation access control requirements. Access to Fort Jackson is contingent upon meeting security criteria, including background checks through the Installation Access Control System (IACS). The Government is not liable for costs associated with performance delays due to the Contractor’s failure to comply with processing requirements. The Contractor shall provide an initial Installation Pass Log to the COR within three (3) calendar days after contract award [Deliverable A002].

1.5.2 OPERATIONS SECURITY (OPSEC): The Contractor shall comply with all facility OPSEC procedures. Government-issued badges shall not be worn where visible to the general public. Suspicious activities must be reported immediately. All Contractor employees shall complete Level I OPSEC training within 30 days of employment and annually thereafter [Deliverable A003].

1.6 POST AWARD CONFERENCE/PERIODIC PROGRESS MEETINGS: The Contractor shall attend any post-award conference and periodic progress meetings convened by the contracting activity to review performance and resolve any outstanding issues.

1.7 CONTRACTING OFFICER’S REPRESENTATIVE (COR): A COR will be designated by the KO to monitor all technical aspects of the contract and assist in administration. The COR is not authorized to make any commitments or changes that affect price, quality, quantity, delivery, or any other term or condition of the contract.

1.8 KEY PERSONNEL: The Contractor shall appoint a Contract Manager and an Alternate Contract Manager who have full authority to act for the Contractor on all contract matters.

A Curriculum Vitae (CV) for each individual shall be provided to the KO no later than five (5) days after award [Deliverable A004].

* Contract Manager / Alternate Contract Manager: The CV must demonstrate experience relevant to managing contracts of similar scope and complexity.

* Special Qualifications: All personnel deployed to the range for survey and clearance operations must possess and maintain current EOD certification (or equivalent civilian UXO Technician certification compliant with DDESB TP-18) throughout the contract period of performance.

1.9 SAFETY: The Contractor shall comply with FAR 52.236-13, Accident Prevention, and the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1). The

Contractor shall submit a site-specific Accident Prevention Plan (APP) and an Activity Hazard Analysis (AHA) for Government review and acceptance prior to the initiation of work [Deliverable A005].

1.10 ENVIRONMENTAL COMPLIANCE: The Contractor shall perform all operations in strict conformance with all applicable federal, state, and local environmental laws, as well as USAG Fort Jackson environmental policies. The Contractor shall immediately report any hazardous substance spills to Range Operations at 803-751-7171 and is responsible for the cleanup of any contamination caused by its activities.

1.11 REQUIRED TRAINING: All contractor employees shall complete Anti-Terrorism (AT) Level I Training [Deliverable A006] and iWATCH Training [Deliverable A007] within 30 days of contract start and annually as required.

PART 2 – DEFINITIONS & ACRONYMS

2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.

Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.

Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”

Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.

Day – means, unless otherwise specified, a calendar day.

Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.

Deliverable – means anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.

Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract

Government Property - means all property owned or leased by the Government.

Government property includes both Government-furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.

Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.

High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown

Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.

Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.

Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.

Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order.

The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to Government document.

Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s).

Statements focus on “what” is to be accomplished; however, they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.

Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.

Work Day - The number of hours per day the Contractor provides services in accordance with the contract.

Work Week - Monday through Friday, unless otherwise specified.

2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.

ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis AOR Area of Responsibility AR Army Regulation AT Anti-terrorism ATCTS Army Training Certification Tracking System CAC Common Access Card CCE Contracting Center of Excellence CFE Conventional Forces Europe CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer’s Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DoD Department of Defense FAR Federal Acquisition Regulation GFP Government Furnished Property HLO High Level Objective HIPAA Health Insurance Portability and Accountability Act of 1996 IA Information Awareness IAC Installation Access Control IACO Installation Access Control Office ID Identification IGCE Independent Government Cost Estimate

IT Information Technology JTR Joint Travel Regulation JPAS Joint Personnel Adjudication System KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs OPSEC Operations Security PA Property Administrator PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program RA Requiring Activity RCO Regional Contracting Office SIGE Safety and Health Protection Plan TE Technical Exhibit USAG United States Army Garrison UOM Unit of Measure UXO Unexploded Ordinance

PART 3 – GOVERNMENT PROPERTY (GP) AND SERVICES

3.1 FACILITIES: The Government will provide a staging area at the Remagen Range for Contractor parking and equipment.

3.2 UTILITIES: The Government will provide electrical outlets for charging of batteries. The Contractor is responsible for all necessary resources.

3.3 TRAINING: The Government will provide access to online training modules for AT Level I, OPSEC, and iWATCH training.

PART 4 – CONTRACTOR FURNISHED ITEMS AND SERVICES

4.1 GENERAL: Except for those items specified in Part 3, the Contractor shall furnish all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary to perform the services described in this PWS.

4.2 MATERIALS: The Contractor shall provide all necessary Personal Protective Equipment (PPE), office supplies, and explosives required for demolition operations.

4.3 EQUIPMENT: The Contractor shall provide all necessary UXO detection and survey equipment, vehicles, and other equipment required to perform the work. All equipment shall meet federal, state, and local safety and environmental standards.

PART 5 – SPECIFIC TASKS

5.1 GENERAL: The Contractor shall have the capability to perform the following tasks upon issuance of a BPA call order, which will specify the location, the total acreage, and the type of sweep required.

5.2 TASK 1: SURFACE SWEEP AND CLEARANCE: When directed, the Contractor shall perform a 100% metal detector sweep of the designated area. This task includes:

* 5.2.1: Establishing survey lanes to ensure total area coverage within the four (4) hand grenade throwing bays.

* 5.2.2: Detecting dud grenades with metal detectors and visually identifying all munitions and explosives of concern (MEC), munitions debris (MD), or other explosive hazards on the surface.

* 5.2.3: Safely marking the location of all identified hazards for subsequent disposal.

5.3 TASK 2: SUB-SURFACE SWEEP AND CLEARANCE: When directed, the Contractor shall perform an instrument-aided sweep of the designated area to the depth specified in the call order (commensurate with the expected ordnance type). This task includes:

* 5.3.1: Using appropriate geophysical detection instruments (e.g., magnetometers, electromagnetic induction sensors) to scan 100% of the designated area.

* 5.3.2: Investigating all detected sub-surface anomalies by carefully excavating to determine the source.

* 5.3.3: Identifying all located dud grenades, UXO, MEC, or other explosive hazards and safely marking their location for disposal.

5.4 TASK 3: DEMOLITION OPERATIONS: The Contractor shall conduct on-site demolition of all explosive hazards located during sweep operations. This shall be done in a consolidated manner to minimize the number of demolition events. All operations must be conducted in strict accordance with AR 385-63 and all other applicable regulations.

5.5 TASK 4: FINAL REPORTING: Upon completion of each call order, the Contractor shall provide a Final Clearance Report to the COR [Deliverable A008]. This report shall include, at a minimum:

* A map and description of the area cleared.

* The type of sweep performed (surface or sub-surface) and the depth achieved.

* A detailed list of all explosive hazards found and their grid coordinates.

* A summary of all demolition activities.

* A signed certification that the area has been cleared to the specifications of the call order.

5.6 CONTRACTOR PROJECT MANAGEMENT: The Contractor shall manage all work performed under this contract to ensure all tasks are completed safely, on schedule, and in accordance with the PWS.

PART 6 – APPLICABLE PUBLICATIONS

6.1 The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.

6.1.1 Department Of Defense Contract Security Classification Specification (DD Form 254)

6.1.2 Department of Defense Security Agreement (DD Form 441)

6.1.3 National Industrial Security Program Operating Manual (DoD 5220.22-M)

6.1.4 Installation Access Control (AE Reg 190-16)

6.1.5 The Army Physical Security Program (AR 190-13)

6.1.6 Contractor Identification (AE Reg 27-715)

6.1.7 Information Assurance Workforce Improvement Program (DoD 8570-M)

6.1.8 Information Assurance Training Certification and Workforce Management Directive (DoDD 8570.01)

6.1.9 Information Assurance (AR 25-2)

6.1.10 Electromagnetic Compatibility Directive (2004/108/EC)

6.1.11 Policies and Procedures for Property Accountability (AR 735-5)

6.1.12 Range Safety (AR 385-63)

PART 7 – ATTACHMENT AND TECHNICAL EXHIBIT LISTING

7.1 Technical Exhibit A: Performance Requirements Summary (PRS)

7.2 Technical Exhibit B: Deliverables Schedule

7.3 Attachment 1: Site Map of Remagen Hand Grenade Range

TECHNICAL EXHIBIT A: PERFORMANCE REQUIREMENTS SUMMARY (PRS)

Performance Objective

PWS

Paragraph

Performance Standard

Acceptable Quality Level

(AQL)

Method of Surveillance

Area Coverage (Surface/Sub- Surface)

5.2, 5.3 100% of the designated acreage must be systematically swept and cleared according to the call order.

Zero deviation.

100% coverage is mandatory.

COR review of daily progress reports, GPS data logs, and Final Clearance Report map.

Hazard Identification & Demolition

5.3 All located explosive

hazards must be identified and disposed of IAW all safety regulations (e.g., AR 385-63).

Zero safety violations. Zero deviation from regulatory procedures.

100% inspection and COR observation of demolition planning and execution. Review of demolition report.

Final Reporting 5.4 Submit an accurate and complete Final Clearance Report within 5 business days of completing on-site work.

Report is 100% complete and accurate with no more than one correction required per submission.

100% inspection of submitted report.

Required Certifications

1.8 All deployed

personnel must maintain current

100% compliance.

Zero deviations.

Periodic inspection of certification records.

EOD/UXO

qualifications at all times while performing work.

Safety Compliance

1.9 Adherence to the

approved Accident Prevention Plan (APP) and EM 385-1-1 at all times. No safety violations.

Zero Class A or B accidents. No more than two minor safety infractions per service call.

Random inspection, COR observation, review of accident/incident reports.

TECHNICAL EXHIBIT B: DELIVERABLES SCHEDULE

Deliverable

Deliverable Title PWS Para.

Frequency Submit To

A001 Quality Control Plan (QCP) 1.4.1 Once, within 10 days of award

COR

A002 Installation Pass Log 1.5.1 Once, within 3 days of award;

updated as changes occur

COR

A003 OPSEC Training Certificates 1.5.2 Within 30 days of award/hire;

annually thereafter

COR

A004 Key Personnel Resumes 1.8 Once, within 5 days of award COR

A005 Accident Prevention Plan (APP) / Activity Hazard Analysis (AHA)

1.9 Prior to start of on-site work COR

A006 AT Level I Training Certificates 1.11 Within 30 days of award/hire;

annually thereafter

COR

A007 iWATCH Training Roster 1.11 Within 30 days of award/hire COR

A008 Survey Completion Report 5.1.4 Within 24 hours of completing each service call

COR

Prepared by: Matt Aragon, Range Officer, USAG Fort Jackson, DPTMS.

Attachment 1: Site Map of Remagen Hand Grenade Range

UNCLASSIFIEDForging the Warrior Spirit Starts Here Range Operations

Fort Jackson Hand Grenade Data for UXO Clearance

0.30 acres Areas requiring no dud confirmation Total .3 x 4 = 1.2 acres

Throwing Pits Ability to drive & park onsite

40’

130’

180’

Location: https://maps.app.goo.gl/HXipj5Q5gh4RiQRu8

End

2026-03-06T11:37:27-0500
ARAGON.MATTHEW.ALVIN.1255724610

File details come from the government source that posted it. Updated .