This document package includes technical specifications for a federal construction contract solicitation. The Bureau of Land Management Montana State Office is soliciting proposals to chip seal 6.2 miles of asphalt roadway, resurface day use areas, perform linear grading along 4.9 miles of roadway, and delineate a parking area. The specifications provide requirements for mobilization, surveying and staking, quality control, traffic control, clearing and grubbing, structure removal, aggregate courses, incidental construction, metal pipes, and roadside improvement materials. Proposers must follow the specifications, which modify the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects in certain sections to suit low-volume rural roads and construction environments.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Special Contract Requirements Western Montana District
McNamara / Johnsrud Chip seal Bureau of Land Management
Special Contract Requirements for Chip Sealing and Site Improvements of the
McNamara/Johnsrud Roads
Description of Work
The McNamara/Johnsrud Chip Seal and Site Improvements Project consists of chip sealing 6.2 miles of asphalt roadway, resurfacing the Blackfoot Corridor Day Use Areas, and delineating the parking area at Whitaker Bridge Day Use Area.
Applicable Standard Specifications
The following Special Contract Requirements (SCRs) are only a portion of the specifications for this project.
These SCRs amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14. The FP-14 is a separately published book. In order to understand the solicitation properly you need to have the FP-14 as well as this packet. Pay particular attention to the provisions of Subsection
104.04 in the FP-14 that explain how each of the many contract documents fit together.
One printed copy of the FP-14 will be distributed to the successful bidder.
To view the FP-14 electronically, go to: https://highways.dot.gov/federal-lands/specs
A single paper copy can also be obtained from the Research & Technology Product Distribution Center (RTPDC) by e-mail report.center@dot.gov, phone 814-239-1160, or fax 814-239-2156.
Note: These Special Contract Requirements change, supplement, or modify the FP-14 specifications to make them more applicable to BLMs low or very low volume roads and rural construction environments. Specifications are often changed to reduce their complexity, limit testing, and loosen tolerances. Specifications are called out in this way to call attention to where requirements are changed from the standard FP-14 specifications.
How to use the FP-14 specifications with the Special Contract Requirements and the contract’s bid schedule.
• Pay item no. 20401 means this work is defined in section 204 of the FP-14 specifications. For all pay items the first three digits correlate to the FP-14 section that describes that work.
• Next check Special Contract Requirements. If there is a matching section 204 then it modifies the FP-14. If there is no section listed there are no changes, the FP-14 specification is utilized in its entirety. The change direction will be underlined and italicized; the specification text will be plain.
o Example: Section 204 is listed in the Special Contract Requirements with a direction to “Delete Section 204 in its entirety and replace with the following.”
o Apply those changes. None of the original FP-14 specification will be used. Only use the content that is in the Special Contract Requirements.
https://highways.dot.gov/federal-lands/specs mailto:report.center@dot.gov
Table of Contents
PREFACE
DIVISION 100 GENERAL REQUIREMENTS
Section 101 – TERMS, FORMAT, AND DEFINITIONS
Section 102. - BID¸ AWARD¸ AND EXECUTI1ON OF CONTRACT
Section 103. - SCOPE OF WORK
Section 104. - CONTROL OF WORK
Section 105. - CONTROL OF MATERIAL
Section 106. - ACCEPTANCE OF WORK
Section 107. - LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Section 108. - PROSECUTION AND PROGRESS
Section 109. - MEASUREMENT AND PAYMENT
DIVISION 150 PROJECT REQUIREMENTS
Section 151. - MOBILIZATION
Section 152. - CONSTRUCTION SURVEY AND STAKING
Section 153. - CONTRACTOR QUALITY CONTROL
Section 156. – PUBLIC TRAFFIC
DIVISION 200 EARTHWORK
Section 201. - CLEARING AND GRUBBING
Section 201. - CLEARING AND GRUBBING
Section 203. - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
DIVISION 300 AGGREGATE AND BASE COURSES
301 - UNTREATED AGGREGATE COURSES
DIVISION 600 INCIDENTAL CONSTRUCTION
633 – PERMANENT TRAFFIC CONTROL
DIVISION 700 MATERIAL
707 – METAL PIPE
713 - ROADSIDE IMPROVEMENT MATERIAL
PREFACE
Preface. Delete Preface
DIVISION 100 GENERAL REQUIREMENTS
Section 101 – TERMS, FORMAT, AND DEFINITIONS
101.01 Meaning of Terms. Delete all references to the TAR (Transportation Acquisition Regulations) and FAR (Federal Acquisition Regulations) in the specifications.
101.03 Abbreviations. Add the following to Subsection 101.03:
(a) Acronyms.
AA
AAN
AAR
ABA
ACPA
ADA
AFPA
AI
AIA
ARA
AREA
ASCE
ASCII
ASLA
BLM
FTMS
GSA
IEEE
MIL
MSHA
NESC
NFPA
PCA
SAE
USFS
USGS
USPS
Aluminum Association American Association of Nurserymen Association of American Railroad Architectural Barriers Act American Concrete Pavement Association Americans with Disabilities Act American Forest and Paper Association Asphalt Institute American Institute of Architects American Railway Association American Railway Engineering Association American Society of Civil Engineers American Standard Code for Information Interchange American Society of Landscape Architects Bureau of Land Management Federal Test Method Standard General Services Administration Institute of Electrical and Electronic Engineers Military Specifications Mine Safety and Health Administration National Electrical Safety Code National Forest Products Association Portland Cement Association Society of Automotive Engineers United States Forest Service United States Geological Survey United States Postal Service
WCLIB
WWPI
West Coast Lumber Inspection Bureau Western Wood Preservers Institute
Add the following to (b) U.S. Customary unit abbreviations and symbols:
hr mp ppm
Hour Milepost Part Per Million
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume
STA station location
101.04 Definitions. Make the following changes to Subsection 101.04:
Delete these definitions:
Bid
Bidder
Delete this definition and substitute the following:
Contract Time –
Period of Performance (POP) – The specified time allowed for completion of contract work.
Add the following:
Maximum Particle Size – The smallest sieve opening through which all particles in the material will pass.
Neat Line – A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road – Temporary construction access built along the route of the project.
Protected Streamcourse – A drainage shown on the plans that requires designated mitigation measures.
Right-of-Way – A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Utilization Standards – The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Holidays — Holidays occur on the following days:
• 1st day of January - New Years’ Day;
• 3rd Monday of January - Martin Luther King, Jr. Day;
• 3rd Monday of February - Presidents' Day;
• Last Monday of May - Memorial Day;
• 4th day of July - Independence Day;
• 1st Monday of September - Labor Day;
• 2nd Monday of October - Columbus Day;
• 11th day of November – Veterans’ Day;
• 4th Thursday of November - Thanksgiving Day;
• 25th day of December - Christmas Day;
• Other days declared holidays by the Congress or the President; and
• If a holiday occurs on a Saturday, the preceding Friday is also a legal holiday. If a holiday occurs on a Sunday, the Monday following is also a legal holiday.
Add Figure 101-1—Illustration of road structure terms:
Section 102. - BID¸ AWARD¸ AND EXECUTI1ON OF CONTRACT
Section 102. Delete Section 102 in its entirety.
Section 103. - SCOPE OF WORK
Section 103. Delete all of Section 103 except Subsection 103.01 Intent of Contract.
Section 104. - CONTROL OF WORK
Section 104. Remove all references to the FAR.
104.04 Coordination of Contract Documents. Delete Subsection
Section 105. - CONTROL OF MATERIAL
Section 105. Remove all references to the FAR.
105.02(a) and (b). Delete Subsections
105.05 Use of Material Found in the Work. Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.
Section 106. - ACCEPTANCE OF WORK
Section 106. Delete Section
Section 107. - LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Section 107. Delete Section
Section 108. - PROSECUTION AND PROGRESS
Section 108. Delete Section
Section 109. - MEASUREMENT AND PAYMENT
Section 109. Delete Subsections 109.06, 109.07, 109.08, and 109.09:
109.01 Measurement of Work. Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:
Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.
Table 109-1
Decimal Accuracy of Quantities for Final Payment
Pay Item Level of Precision Linear Foot 1
Exception--Timber, Steel, and concrete Piles 0.1 Station 0.1 Mile 0.01 Square Foot 0.1 Square Yard 0.1 Each 1 Acre 0.01 Gallon 1 M-Gals. 0.1
Cubic Yard 1 Exception--Structure Excavation; Sheathing Materials; Bedding, Bed Course, and Backfill Materials; Gabions;
0.1
Exception--Concrete; Masonry 0.01 Pound 1 Ton 0.1
Exception--Calcium Chloride;
Sodium Chloride; Hydrated Lime;
Bituminous Materials; Pavements;
Bed Course Materials
0.01
Hour 0.1
MFBM 0.01
Station Yard 1 Cubic Yard Mile 1 Ton Mile 1
DIVISION 150 PROJECT REQUIREMENTS
Section 151. - MOBILIZATION
Section 151. Delete Subsections 151.03(b), 151.03(c), and 151.03(d) Replace 151.03(b) with the following:
151.03 (b) Up to 25 percent of the original contract amount may be paid upon mobilization to the jobsite prior to any other work being completed. Any portion of the mobilization pay item in excess of 25 percent of the original contract amount will be paid after final acceptance.
Section 152. - CONSTRUCTION SURVEY AND STAKING
Section 152. Make the following changes:
Remove all references to the FAR.
Remove all references to contractor responsibility for surveying and staking. All surveying and staking services will be provided by the government.
Section 153. - CONTRACTOR QUALITY CONTROL
153.03.03 Quality Control Plan. Delete Subsection
153.04 Prosecution of Work. Add the following to Subsection 153.04(a) (2):
At a minimum the contractor shall provide project submittals as shown on the Submittal Log below.
Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.
Submittal Log
Log No.
Indirect payment to Pay
Item(s) Description of Submittal Type of
Submittal
Requirement found in
Specification No.
/Drawings
Additional Specification References
1 40711-0100 3/8” Chip seal Type 1C 407
2 30115-0000 Surface Course Aggregate Geotechnical/Material Report 301
3 25101-0000 Placed riprap, Class 7 251
4 63501-0000 Traffic Control Plan 156, 635
Section 156. – PUBLIC TRAFFIC
156.01. Remove all references to the FAR.
156.04 Accommodating Traffic During Work. Add the following:
Provide traffic control plan that allows access to all public and private lands for administrative and public use through the duration of the project. At a minimum, single lane access must be provided throughout the project boundaries.
DIVISION 200 EARTHWORK
Section 201. - CLEARING AND GRUBBING
Section 201. Delete Section 201 in its entirety and replace with the following:
Section 201. - CLEARING AND GRUBBING
Description
201.01 This work consists of clearing and grubbing within the clearing limits designated in the plans.
Material
201.02 Conform to the following Subsection:
Backfill material 704.03
Construction Requirements
201.03 General. Construct erosion control measures according to Section 157. Perform work within designated limits.
Do not damage vegetation designated to remain. If damage occurs, repair or replace the vegetation in an acceptable manner. Where possible, preserve vegetation adjacent to bodies of water. Treat cuts or scarred surfaces of trees and shrubs with tree wound dressing.
201.04 Clearing. Within the clearing limits clear trees, brush, and other vegetation as follows:
(a) Cut trees so they fall within the clearing limits;
(b) In areas of cut slope rounding, cut stumps flush with or below the finished ground line;
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 6 inches of the ground; and
(d) Trim tree branches that extend over the road surface and shoulders to attain a clear height of 14 feet. Trim tree limbs as near flush with the trunk as practicable.
201.05 Grubbing. Grub deep enough to remove stumps, roots, buried logs, moss, turf, or other vegetative matter as follows:
(a) Grub areas to be excavated, except for cut slope rounding areas;
(b) Grub embankment areas. Undisturbed stumps less than 24 inches in diameter may be left in place if they protrude less than 6 inches above the original ground and will be covered with more than 48 inches of embankment. Remove all other stumps;
(c) Grub pits, channel changes, and ditches only to the depth necessary for the excavation;
(d) Backfill stump holes and other grubbing holes with backfill material to the level of the surrounding ground according to Subsection 209.09. Compact backfill according to Subsection 209.10;
and
(e) Utilization standards for merchantable timber are listed below. Fall and buck merchantable material into lengths not to exceed 40 feet. Pieces (logs) meet utilization standards when such pieces would have met Utilization Standards if bucking lengths were varied to include such material.
Minimum Utilization Standards
Length = 16 feet.
Diameter (Inside Bark) at small end = 7 inches
33-1/3 Net Scale in % Gross for Sawlog
201.06 Disposal. Dispose of clearing and grubbing debris according to Subsection 203.05.
201.07 Acceptance. Clearing and grubbing will be evaluated under Subsection 106.02.
Material for tree wound dressing will be evaluated under Subsection 106.03.
Backfilling and compacting of stumps and grubbing holes will be evaluated under Section 209.
Measurement
201.08 Measure the Section 201 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:
Do not make deductions from the area computation unless excluded areas are shown on the plans.
Do not measure clearing and grubbing of borrow sources.
Payment
201.09 The accepted quantities will be paid at the contract price per unit of measurement for the Section 201 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Section 203. - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
203.05 Disposing of Material. Add the following to Subsection 203.05:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees.
(f) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs.
Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.
(g) Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking. Remove brush from designated log deck areas. Limb and top logs.
Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than <4> feet and decked in designated log deck location.
Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).
Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps.
DIVISION 300 AGGREGATE AND BASE COURSES
301 - UNTREATED AGGREGATE COURSES
301.05 Compacting. Delete Section 301.05 and replace with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.
Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
(a) Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
(b) Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
(c) Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(b) Placement Method 2.
(d) Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
(e) Compaction E. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 180, method C or D.
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures.
DIVISION 600 INCIDENTAL CONSTRUCTION
633 – PERMANENT TRAFFIC CONTROL
633.01. Add the following to this Subsection:
Parking delineation may be designated as wood, steel, concrete, or other material utilized for traffic control and parking orientation. Delineation shall be installed according to plans and as directed by government in the field.
633.06 Delineators and Object Markers. Add the following to this Subsection:
633.06.(a) Install delineation according to plans and as directed by government in the field.
When utilizing 6” carbon steel pipe as delineation, pipe shall be installed at 3” depth and secured by #5 rebar.
DIVISION 700 MATERIAL
707 – METAL PIPE
707.09. Reserved. Delete Subsection in its entirety and replace with the following:
707.09. Carbon Steel Pipe.
(a) 6” diameter
(b) Schedule 40
1. Steel pipe as parking delineation.
a. Pipe shall be installed at minimum ½ the diameter depth and secured by #5 rebar.
713 - ROADSIDE IMPROVEMENT MATERIAL
713.04 Seed. Add the following:
Only government provided seed mixture is to be used on federal lands.
| PREFACE |
| Preface. Delete Preface |
| DIVISION 100 GENERAL REQUIREMENTS |
| Section 101 – TERMS, FORMAT, AND DEFINITIONS |
| 101.01 Meaning of Terms. Delete all references to the TAR (Transportation Acquisition Regulations) and FAR (Federal Acquisition Regulations) in the specifications. |
| 101.03 Abbreviations. Add the following to Subsection 101.03: |
| 101.04 Definitions. Make the following changes to Subsection 101.04: |
| Section 102. - BID¸ AWARD¸ AND EXECUTI1ON OF CONTRACT |
| Section 103. - SCOPE OF WORK |
| Section 104. - CONTROL OF WORK |
| 104.04 Coordination of Contract Documents. Delete Subsection |
| Section 105. - CONTROL OF MATERIAL |
| Section 105. Remove all references to the FAR. |
| 105.02(a) and (b). Delete Subsections |
| 105.05 Use of Material Found in the Work. Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following: |
| Section 106. - ACCEPTANCE OF WORK |
| Section 107. - LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC |
| Section 107. Delete Section |
| Section 108. - PROSECUTION AND PROGRESS |
| Section 108. Delete Section |
| Section 109. - MEASUREMENT AND PAYMENT |
| Section 109. Delete Subsections 109.06, 109.07, 109.08, and 109.09: |
| 109.01 Measurement of Work. Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following: |
| DIVISION 150 PROJECT REQUIREMENTS |
| Section 151. - MOBILIZATION |
| Section 151. Delete Subsections 151.03(b), 151.03(c), and 151.03(d) Replace 151.03(b) with the following: |
| Section 152. - CONSTRUCTION SURVEY AND STAKING |
| Section 152. Make the following changes: |
| Remove all references to the FAR. |
| Remove all references to contractor responsibility for surveying and staking. All surveying and staking services will be provided by the government. |
| Section 153. - CONTRACTOR QUALITY CONTROL |
| 153.03.03 Quality Control Plan. Delete Subsection |
| 153.04 Prosecution of Work. Add the following to Subsection 153.04(a) (2): |
| Section 156. – PUBLIC TRAFFIC |
| 156.01. Remove all references to the FAR. |
| 156.04 Accommodating Traffic During Work. Add the following: |
| DIVISION 200 EARTHWORK |
| Section 201. - CLEARING AND GRUBBING |
| Section 201. Delete Section 201 in its entirety and replace with the following: |
| Section 201. - CLEARING AND GRUBBING |
| Section 203. - REMOVAL OF STRUCTURES AND OBSTRUCTIONS |
| 203.05 Disposing of Material. Add the following to Subsection 203.05: |
| DIVISION 300 AGGREGATE AND BASE COURSES |
| 301 - UNTREATED AGGREGATE COURSES |
| 301.05 Compacting. Delete Section 301.05 and replace with the following: |
| DIVISION 600 INCIDENTAL CONSTRUCTION |
| 633 – PERMANENT TRAFFIC CONTROL |
| 633.01. Add the following to this Subsection: |
| 633.06 Delineators and Object Markers. Add the following to this Subsection: |
| DIVISION 700 MATERIAL |
| 707 – METAL PIPE |
| 707.09. Reserved. Delete Subsection in its entirety and replace with the following: |
| 707.09. Carbon Steel Pipe. |
| 713 - ROADSIDE IMPROVEMENT MATERIAL |
| 713.04 Seed. Add the following: |