Attachment 1 - Final SOW 657A5-19-903 Modernize Elevators.pdf

PDF 86 KB Posted

Attached to
Y1DA--Modernize Elevators 1 through 4 Marion IL VAMC (P/N 657A5-19-903) (VA-20-00084527)
Solicitation number
36E77621B0001
Issued by

About this file

This document provides details on a federal contract opportunity to modernize elevators at the Marion VA Medical Center in Illinois. The project involves upgrading four existing overhead traction elevators, including mechanical, electrical, communication, and HVAC system modernizations. Minor architectural and hazardous material mitigation work is also required. Offerors must complete all construction activities within 255 calendar days from the notice to proceed. The solicitation will be issued as an Invitation for Bid and advertised as a total Service-Disabled Veteran-Owned Small Business set-aside, with offers from other than SDVOSB concerns not being considered. The NAICS code is 236220 with a size standard of $39.5 million. Questions must be submitted in writing by November 5, 2020 and the estimated value is between $1 million to $5 million.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Marion Illinois VA Medical Center

Project Name:

Modernize Elevators 1-4

Project Number:

657A5-19-903

Funding (2237) Number:

657-20-4-2080-0287

Statement of Work:

This project is a modernization of (4) existing overhead traction elevators on the Marion VAMC campus. The elevators in question are located adjacent to the wall which separates buildings 1 and 38. There are (2) paired elevators in building 1 (designated Elevators 1 & 2) and (2) paired elevators in building 38 (designated Elevators 3 & 4). The Building 1 elevators were originally installed in 1971 and upgraded in 1988 when the Building 38 elevators were added.

The work will include all tasks indicated or implied by the project drawings and specifications.

The basic scope will consist of mechanical, electrical and communication upgrades to all elevator systems as well as upgrades to the HVAC systems which regulate the environment in the elevator machine rooms as well as upgrades to the electrical power distribution network which serves the elevator systems. Minor architectural and hazardous material mitigation activities are also part of the work scope.

Phasing will also be required as part of the project scope. The phasing will consist of leaving two units (one in each building pair) functioning at any given time.

The project requires completion of all construction activity within 252 calendar days from initiation of contract performance period.