This is a Cost Schedule attachment for a Request for Information (RFI) issued by the Alaska Department of Fish and Game for the R/V Medeia Main Engine Repower project. The project involves the complete replacement of two existing 16V-92 main engines and MG-530 marine gears with new propulsion equipment. The scope of work is organized into eight sections: engineering and design services; procurement of new engines, gears, controls, and associated equipment; removal of existing main engines and gears; installation of new systems; dock trials, sea trials, and commissioning; stability testing and updated stability book preparation; documentation, manuals, spares, and crew training; and facility support and project management. Respondents are required to provide budgetary pricing for each of the 26 individual line items and complete an information section detailing their proposed equipment specifications, service dealer locations in Juneau, Alaska, project timeline, proposed work location, vessel out-of-service duration, warranty terms, labor rates for change work, and material markups.

This is explicitly identified as a budgetary schedule for an RFI, and prices entered are not binding bids on either the respondent or the State. All prices are to be provided in U.S. dollars and should include labor, materials, equipment, and engineering, with the exception of installed keel coolers, which are owner-furnished. Respondents must specify the suitability of their proposed engine for extended idle and light load operation, starting system configuration, propulsion controls approach, whether 24 VDC is required, and whether existing keel coolers are adequate for the proposed engine. The document indicates the work is planned for a November 2027 through March 2028 service window, with respondents required to confirm feasibility within that timeframe or propose an alternative schedule. A price validity period must be stated, and respondents are required to provide a spares list for the one-year spares package identified in Item 7.2.

View the file

Other files

File Type Posted
21_Photo_2019-01_Port-Main-Replacement_Deck-Opening-Cut-Above-ER.jpg JPG image
27_Photo_Prior-Deck-Opening_Exhaust-Manifold-Lowered-Through-Deck.jpg JPG image
33_Photo_2026-07_Port-Gear-Nameplate_Twin-Disc-MG530_Full.jpg JPG image
Attachment 2 - Stablility Booklet.pdf PDF
47_Photo_2026-07_Machinery-Data-Card_Handwritten.jpg JPG image
20_Deck-Crane_North-American-MCK-1240_Load-Chart.pdf PDF
39_Photo_2026-07_Stbd-Gear-Nameplate_Ratio-and-Serial.jpg JPG image
16_Maxim-Silencers_M42-Super-Critical_Data-Sheet.pdf PDF
01_EBDG-26075-062-0_Repower-Conceptual-Study_RevP0.pdf PDF
ADFG Request for Information (RFI) - RV Medeia Repower.pdf PDF
38_Photo_2026-07_Stbd-Gear-Nameplate_Model-and-BOM.jpg JPG image
25_Photo_Prior-Deck-Opening_Cut-Line-Layout.jpg JPG image
23_Photo_2019-01_Port-Main-Replacement_ER-Through-Opening-After-Removal.jpg JPG image
29_Photo_2026-07_ER-Main-Engine_Gear-End-and-Exhaust-Lagging.jpg JPG image
32_Photo_2026-07_ER-Marine-Gear-Top-with-Exhaust-Risers-Above.jpg JPG image
45_Photo_2026-07_ER-Looking-Aft_Mains-and-Exhaust-Risers-1.jpg JPG image
28_Photo_2026-07_ER-Overview_Between-Mains-Looking-Along-Centerline.jpg JPG image
40_Photo_2026-07_ER-Main-Engine_Exhaust-Risers-and-Cooling-Piping.jpg JPG image
42_Photo_2026-07_ZF-MicroCommander-Control-Processor_Stbd.jpg JPG image
02_EBDG-26075-256-2_FW-Cooling-System-Mods_RevP1-Preliminary.pdf PDF
11_Dwg-C2412-1_Hydrostatic-Curves-of-Form.pdf PDF
43_Photo_2026-07_ZF-MicroCommander-Control-Processor_Port.jpg JPG image
10_Dwg-U193-3_Lines-Plan.pdf PDF
09_Dwg-S2-192_Small-Vessel-Transverse-Frames.pdf PDF
19_Port-Main_Engine-Run-In-Report_Pacific-Power-Group_2018-11.pdf PDF
08_Dwg-U184-56_Transverse-Frames-and-Longitudinal-Section.pdf PDF
30_Photo_2026-07_ER-Main-Engine_Outboard-Side-and-Piping.jpg JPG image
12_Dwg-C2412-2_Cross-Curves.pdf PDF
18_Detroit-Diesel_Exhaust-System-Data_16V-92N-Highlighted.pdf PDF
05_Dwg-U192-S1_General-Scantling.pdf PDF
06_Dwg-U192-S4_Transverse-Frames.pdf PDF
04_Dwg-U192-MI_Shafting-Installation.pdf PDF
15_Silencer-Drawing_Stbd_8in-ANSI150_2022-10-12.pdf PDF
41_Photo_2026-07_ER-Main-Engine_Exhaust-Risers-and-Air-Cleaner.jpg JPG image
46_Photo_2026-07_ER-Looking-Aft_Mains-and-Exhaust-Risers-2.jpg JPG image
17_Detroit-Diesel_16V-92_Engine-Performance-Curve_E4-8162-12-6.pdf PDF
37_Photo_2026-07_Port-Main_Block-Casting-Number-Closeup.jpg JPG image
24_Photo_2019-01_Port-Main-Replacement_Old-Engine-and-Gear-on-Deck.jpg JPG image
35_Photo_2026-07_Port-Gear-Nameplate_Ratio-and-Serial.jpg JPG image
44_Photo_2026-07_Port-Exhaust-Elbow_Material-ID-Tag.jpg JPG image
14_Silencer-Drawing_Port_8in-ANSI150_2022-10-12.pdf PDF
03_Duramax_SC-424PFDP_Keel-Cooler-Installation-Drawing.pdf PDF
26_Photo_Prior-Deck-Opening_Opening-From-Above.jpg JPG image
07_Dwg-U192-S5_Transverse-Frames.pdf PDF
31_Photo_2026-07_ER-Marine-Gear-and-Foundation.jpg JPG image
22_Photo_2019-01_Port-Main-Replacement_Old-Engine-Visible-Through-Opening.jpg JPG image
34_Photo_2026-07_Port-Gear-Nameplate_Model-and-BOM.jpg JPG image
36_Photo_2026-07_Port-Main_Block-Casting-Number.jpg JPG image
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R/V Medeia Main Engine Repower RFI – Bid Schedule | Page 1 of 3

ATTACHMENT 1 – COST SCHEDULE

ALASKA DEPARTMENT OF FISH AND GAME

R/V Medeia Main Engine Repower

BID SCHEDULE (BUDGETARY) — Respondent shall enter a budgetary price for each work item. Prices are understood to be estimates for planning purposes and are not binding. All prices include labor, materials, equipment, and engineering, in U.S. Dollars. The installed keel coolers are the only Owner-furnished equipment; everything else is Contractor-furnished.

Item # Work Item Description Budgetary Price

(USD)

SECTION 1: ENGINEERING, SHIP CHECK, AND DESIGN

1.1 Ship check and field verification (engine room, exhaust, deck above engine room, control stations, electrical)

1.2 Propulsion match and driveline engineering (engine rating, gear ratio, propeller and shaft check, torsional vibration analysis from OEM, rotation and flywheel housing confirmation)

1.3 Foundation design (new or modified engine and gear foundations, drawings and calculations)

1.4 Exhaust, cooling, ventilation, and fuel system engineering (exhaust design and backpressure calculation; keel cooler capacity check and piping design;

ventilation evaluation; fuel supply and return check)

1.5 Electrical, controls, and starting system engineering (24 VDC system if required, control and monitoring, ZF control integration, CO2 shutdown tie-in, air or electric start)

1.6 Weight and stability log and preliminary stability check; design submittals to Owner

TOTAL — Work Item #1 Engineering $

SECTION 2: MAIN ENGINES, MARINE GEARS, CONTROLS, AND ASSOCIATED EQUIPMENT

2.1 Two (2) new main engines, with marine accessories, engine room panels, wheelhouse monitoring display, and aft deck rpm readouts — make, model, and rating as stated in the Information table below

2.2 Two (2) new marine gears with couplings, mounts, and driveline hardware — make, model, and ratio as stated in the Information table below

2.3 Propulsion control equipment for the wheelhouse and wheelhouse aft deck stations (new ZF control processors compatible with existing control heads, or complete replacement control system); trolling valve or similar if recommended

2.4 24 VDC system, batteries, chargers, and distribution (if required by the proposed engines); starting system components

2.5 Exhaust components engine to silencers, piping, valves, hangers, wiring, and consumables; freight to Contractor's facility; receiving and storage

TOTAL — Work Item #2 Equipment $

SECTION 3: REMOVAL OF EXISTING MAIN ENGINES AND MARINE GEARS

3.1 Drain and dispose of fluids; disconnect; cut temporary deck openings and protect; lift out both 16V-92 engines and MG-530 gears; remove foundations, piping, ducting, wiring, and brackets not reused; record weights and locations;

clean and prime disturbed steel

3.2 Removal of old engines and gears from the vessel and Owner's custody;

retention, resale, or disposal by Contractor

3.3 CREDIT — Salvage value of old engines and gears, if any (enter as a negative number or $0)

TOTAL — Work Item #3 Removal (net of salvage credit) $

R/V Medeia Main Engine Repower RFI – Bid Schedule | Page 2 of 3

Item # Work Item Description Budgetary Price

(USD)

SECTION 4: INSTALLATION OF NEW MAIN ENGINES, MARINE GEARS, CONTROLS, AND ASSOCIATED

SYSTEMS

4.1 Fabricate and install foundations; set engines and gears; align to existing shaft line; fit couplings; record alignment

4.2 Exhaust engine to silencers, expansion joints, supports, lagging; any silencer or stack piping changes identified under Item 1

4.3 Cooling: engine room piping to installed keel coolers, place aftercooler coolers in service, isolation valves, flex connections, expansion tanks with low-level alarms;

flush, fill, pressure test, bleed; any additional cooling identified under Item 1

4.4 Fuel and lube: connections, filtration, flex connections, any fuel system changes identified under Item 1; initial fill of lube and gear oil

4.5 Electrical, controls, and monitoring: 24 VDC system if required, engine room panels, wheelhouse monitoring and controls, aft deck controls and rpm readouts, CO2 shutdown tie-in, starting system, all wiring

4.6 Ventilation changes identified under Item 1 $

4.7 Deck restoration to original scantlings, watertight, coated; reinstall deck equipment and fittings in way of the opening

4.8 Close-up: reinstall deck plates, rails, insulation; prepare and paint disturbed steel;

clean engine room

TOTAL — Work Item #4 Installation $

SECTION 5: DOCK TRIALS, SEA TRIALS, AND COMMISSIONING

5.1 Dock trials and OEM commissioning of engines and gears; alarms, shutdowns, CO2 tie-in, controls from both stations and engine room panels

5.2 Sea trials (not less than 4 hours at rated load with recorded data, maneuvering, control response) with OEM representatives aboard; written trials report

TOTAL — Work Item #5 Trials $

SECTION 6: STABILITY TEST AND UPDATED STABILITY BOOK

6.1 Digital hull model from lines plan with field verification; capture of house, stacks, and gantry profile

6.2 Inclining experiment per ASTM F1321 (procedure, certified weights, crane, berth, instruments, personnel, naval architect on site)

6.3 Inclining report and updated stability book (up to six Owner-identified operating conditions, trawl and pot loads, gantry, operating guidance)

TOTAL — Work Item #6 Stability $

SECTION 7: DOCUMENTATION, MANUALS, SPARES, AND CREW TRAINING

7.1 As-built drawings (PDF and native CAD), manuals, commissioning and alignment records, TVA, trials report

7.2 Spares package — manufacturers' recommended one-year spares for engines and gears, plus special tools (attach list)

7.3 Crew training, not less than one day, hands-on $

TOTAL — Work Item #7 Documentation and Spares $

SECTION 8: FACILITY AND SUPPORT

8.1 Safe lay berth, shore power, gangway, crane or lift service beyond the ship's crane, shop support, and project management for the duration of the work

TOTAL BUDGETARY PRICE — ALL WORK ITEMS (Items 1–8): $

R/V Medeia Main Engine Repower RFI – Bid Schedule | Page 3 of 3

INFORMATION — Respondent shall complete the following. These entries are part of the response and are needed to compare approaches.

Item Respondent's Entry Proposed main engine (make, model, rating, hp and rpm, duty rating, emissions tier)

Proposed marine gear (make, model, ratio, input rating, clutch duty; trolling valve yes/no)

Authorized engine parts and service dealer in Juneau, Alaska

Authorized gear parts and service dealer in Juneau, Alaska

Naval architect / engineering firm Location where the work would be done Engine and gear lead time from order to delivery Vessel out-of-service duration required (days), not counting transit

Can the work be done in the November 2027 – March 2028 window? If not, when?

Suitability of proposed engine for extended idle and light load (brief explanation)

Starting system proposed (tie into existing air start / electric)

Propulsion controls proposed (new ZF processors with existing heads / full replacement)

Is 24 VDC required? If so, how would it be provided?

Are the installed keel coolers adequate for the proposed engine? If not, what is added?

Engine warranty terms Gear warranty terms Contractor workmanship warranty Hourly labor rate for change work (straight time) Material markup for change work Price validity period

Notes: This is a budgetary schedule for a Request for Information; prices entered are not bids and do not bind the respondent or the State. Items are priced separately so the Owner can see where the cost sits and adjust scope before a formal solicitation. The salvage credit on Item 3.3 is optional; enter $0 if none is offered. Items 1.4, 4.3, and

4.6 should include anything the respondent believes the installed keel coolers or the existing ventilation cannot cover for the proposed engine, with a note explaining what was added. Where a respondent's approach does not fit a line as written, use the nearest line and explain in the response narrative. Attach the spares list for Item 7.2.