Attachment 1 - Construction Final SOW-EHRM Data Drops Power Outlets.docx
DOCX document 47 KB Posted
- Attached to
- 656-26-702 EHRM DDPO 2. 0 Federal contract opportunity
- Solicitation number
- 36C26326B0028
About this file
This is a Construction Scope of Work for the installation of data drops and power outlets at the St. Cloud VA Medical Center in St. Cloud, Minnesota. The contractor must furnish all labor, materials, and equipment to install ten (10) additional Category 6A data drops with basic pathway installation, five (5) additional generic normal power outlets, and five (5) additional generic emergency power outlets to support Electronic Health Record (EHR) equipment deployment. All work must comply with BICSI standards (ANSI/NECA/BICSI 568), ANSI/TIA-1179 Healthcare Facility Telecommunications Infrastructure standards, TIA 568.2-D, TIA TSB-184-A, and NFPA-70 Section 725.144. Data drops must be terminated to identified RJ-45 patch panels and wall plates with machine-generated labels, certified for compliance with TIA-EIA-568-C.2, and installed using continuous cable lengths not exceeding 90 meters with one-foot service loops. Power outlets and conduit must follow NEC maximum fill requirements and be labeled according to VAMC standards.
The period of performance is 90 calendar days following Notice to Proceed (NTP), with all work including testing, certification, as-builts, and closeout required to be completed no later than November 15, 2026. Work shall occur during normal business hours of 8:00 AM to 4:30 PM, Monday through Friday, excluding federal holidays, though after-hours and weekend work is encouraged with prior COR coordination. The anticipated cost range is between $100,000 and $250,000. Key submittals include product data and cable samples, as-built drawings for data and power locations with one-line diagrams and panel schedules, cable certification reports reflecting appropriate labeling schemes, and system warranties covering installed cabling against defects in workmanship, components, and performance. The contractor is required to submit a labeling plan for approval, maintain aggressive progress to meet the 90-day construction window, and verify field conditions during a pre-bid site walk.
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION SCOPE OF WORK
EHRM INSTALLATION OF DATA DROP AND POWER OUTLETS (DDPO)
PROJECT NO: 656-26-702
PROJECT NAME: EHRM Installation of Data Drops and Power Outlets – St. Cloud, MN
1. GENERAL INTENT:
The Contractor shall furnish all labor, materials and equipment to prepare the site identified on St. Cloud VA Medical Center campus, 4801 Veterans Dr, St. Cloud, MN 56303 for the installation of additional data drops, power outlets and equipment bracing for equipment deployment of the Electronic Health Record (EHR).
2. STATEMENT OF WORK (SOW):
Provide and install normal and emergency power outlets, data drops, and required equipment bracing to support EHR equipment deployment on the St. Cloud VA campus as shown and described in the project drawings and specifications. A list of data drops and power outlets is provided in Attachment 2: DDPO 2.0 Design 04132026.
a. The Offeror shall include a Contract Line-Item Number (CLIN) for each of the following items:
1. Ten (10) additional data drops, including basic pathway installation.
2. Five (5) additional generic normal power outlets.
3. Five (5) additional generic emergency power outlets.
These items may be coordinated by the Contracting Officer’s Representative (COR) as necessary, to address any additional needs identified by the St. Cloud VAMC to complete DDPO 2.0.
b. Cost Range: The anticipated cost range for this project is between $100,000 and $250,000.
c. Recommend Offerors verify field conditions during the pre-bid site walk.
d. Work shall be completed during normal hours, 8:00 AM to 4:30 PM, Monday through Friday, excluding Federal Holidays. Work may also be performed after normal business hours and on weekends with prior coordination and approval of the COR. After-hours and weekend work is encouraged when necessary to minimize disruption to VA patient care and operations. Any deviation from the normal working hours must be clearly noted in the contractor’s bid and approved in advance by the COR.
e. Observed Federal Holidays:
1. New Year’s Day
2. Birthday of Martin Luther King Jr.
3. Washington’s Birthday
4. Memorial Day
5. Juneteenth National Independence Day
6. Independence Day
7. Labor Day
8. Columbus Day
9. Veterans Day
10. Thanksgiving Day
11. Christmas Day
f. Schedule (Calendar Days)
| Contract Award |
| D |
| Post Award Conference |
| D+14 |
| Badging Submissions |
| D+25 |
| Submittal Submissions |
| D+25 |
| Notice to Proceed (NTP) |
| D+30 |
| Construction Start |
| D+45 |
| Substantial Completion / Final Completion |
| 90 Calendar Days after NTP |
| Period of Performance (POP) End Date |
| November 15, 2026 |
g. PERIOD OF PERFORMANCE:
1. Work timelines and completion progress shall be communicated to the COR for tracking purposes.
2. Work described in Section 2 shall be completed within 90 days following Notice to Proceed (NTP). Note: All work, including testing, certification, as-builts, and closeout, must be fully completed no later than November 15, 2026. The contractor is required to maintain aggressive progress to meet the strict 90-day construction window following NTP.
2.1 Data Drops
2.1.1 Install Cat 6A cabling and data drops in accordance with attachments, location drawings, and specifications. List of devices shown in Attachment 2: DDPO 2.0 Design 04132026. Locations shown in attached design drawings.
2.1.2 Horizontal cabling shall be Category 6A (Cat6A) (ANSI/TIA-1179 Healthcare Facility Telecommunications Infrastructure).
2.1.3 Installation shall be compliant with the BICSI standards (ANSI/NECA/BICSI 568, Standard for Installing Commercial Building Telecommunications Cabling and ANSI/TIA-1179-A Healthcare Facility Telecommunications Infrastructure for new installations).
2.1.3.1 New cable installations additionally shall be compliant with TIA 568.2-D, TIA TSB-184-A, and NFPA-70 Section 725.144 to prevent PoE heat accumulation. Provide certification reports to the COR.
2.1.3.2 Alternatively, new UTP cabling shall carry a UL listed "LP" (Limited Power) rating.
2.1.3.3 Cat6A cable shall be terminated to identified RJ-45 patch panel in IT closet and CAT6A RJ-45 jack at wall plate and labeled at both ends.
2.1.3.4 Use a cable analyzer to determine cable length (max cable length 90M/295 linear feet) and certify that cable meets or exceeds TIA-EIA-568-C.2.
2.1.3.5 Cables shall be installed in continuous lengths from origin to destination, no splices with a 1’ service loop.
2.1.5 Cable management shall be implemented for all patch cables in accordance with Infrastructure Standard for Telecommunications Spaces (latest version on the TIL), ensuring proper bend radius, bundling, airflow, support and labeling.
2.1.6 Copper structured cabling shall be certified as meeting or exceeding TIA-EIA-568.1-D (max fixed cable length 90M/295 linear feet) independent of media type.
2.1.7 Use existing raceways as much as possible. Cable shall be installed in accordance with manufacturers’ recommendations and best industry practices. Existing raceways shall not be filled greater than the NEC maximum fill for the raceway type.
2.1.8 Install and label outlets, faceplates and patch panels in accordance with specifications and VAMC standard. Patch panel labels shall include room #, outlet #, jack #. The Contractor shall submit a labeling plan for outlets, faceplates and patch panels to the COR for approval prior to initiating installation. All label printing shall be machine generated.
2.1.9 Confirm locations, including installation height, with COR.
2.1.10 Patch and finish disturbed surfaces to match existing.
2.1.11 All new cable installations shall be tested and certified. Provide the certification report to COR.
2.2 Power Outlets
2.2.1 Install conduit and conductors in accordance with attachments, location drawings, and specifications. List of devices shown in Attachment 2: DDPO 2.0 Design 04132026; Locations shown in Attachment 3: List of EUD for Install (End User Devices).
2.2.2 Use existing raceways as much as possible. Conductors shall be installed in accordance with manufacturer’s recommendations and best industry practices. Existing raceways shall not be filled greater than the NEC maximum fill for the raceway type.
2.1.8 Install and label outlets, faceplates and power panels in accordance with specifications and VAMC standard. The Contractor shall submit a labeling plan for outlets, faceplates and power panels to the COR for approval prior to initiating installation. All label printing shall be machine generated.
2.2.3 Confirm locations, including installation height, with COR.
2.2.4 Patch and finish disturbed surfaces to match existing.
2.3 Equipment and Mounting Hardware
2.3.1 List of equipment and mounting hardware requiring installation is located at Locations are shown on Attachment 2: DDPO 2.0 Design 04132026 but shall be verified with COR prior to installation.
2.3.2 Install units in accordance with manufacturer’s installation instructions.
2.3.3 Patch and finish disturbed surfaces to match existing.
3. SUBMITTALS:
3.1 In addition to submittals required by specifications, the contractor shall submit the following submittals for review:
3.1.1 Product data and sample of cable.
3.1.2 As-built drawings for all data locations and labels. The Contractor shall provide the central drawing set to the Owner at the end of the project. The marked-up drawing set will accurately depict the as-built status of the system including termination locations, cable routing, and all administration labeling for the cabling system. In addition, a narrative will be provided that describes any areas of difficulty encountered during the installation that could potentially cause problems with the telecommunications system.
3.1.3 As-built drawings for new power locations. Include one line diagram depicting which circuits feed new outlets and panel schedules for panels feeding new outlet locations.
3.1.4 Certification report. All testing documents shall reflect the appropriate labeling scheme.
3.1.5 Warranties of installation and cabling system. The Contractor shall provide a system warranty covering the installed cabling system against defects in workmanship, components, and performance, and covering follow-on support after project completion.
4. REFERENCES:
4.1 VA OEHRM Site Infrastructure and End User Device (EUD) Requirements (Attachment 4: VA OEHRM Site Infrastructure and End User Device (EUD) Requirements (SIEUDR)).
4.2 Infrastructure Standards for Telecommunications Spaces
4.3 Telecommunications and Special Telecommunications Systems Design Manual, https://www.cfm.va.gov/til/dManual/dmTelecomm.pdf.
5. ATTACHMENTS; File name
5.1 Attachment 2: DDPO 2.0 Design 04132026
5.2 Attachment 3: List of EUD for Install (End User Devices)
5.3 Attachment 4: VA OEHRM Site Infrastructure and End User Device (EUD) Requirements (SIEUDR)
5.4 Attachment 5: Specifications
5.5 Attachment 6: ASC Boom Arm detail drawings
5.6 Attachment 7: As Built records from EHRM Infrastructure (Parts I through V, five (5) total).
The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for this project. Contractor shall refer to drawings and specifications for comprehensive construction requirements.
End of SOW