This is a Statement of Work (SOW) for construction services related to window replacement at Mann-Grandstaff VA Medical Center in Spokane, Washington (Project No. 668-24-102). The Veterans Affairs Spokane Healthcare System requires the contractor to replace existing pre-1990 exterior windows in Building 1, the main hospital building comprising nine occupied floors (Basement through Eighth Floor), a mechanical penthouse (Ninth Floor), and an elevator machine room (Tenth Floor). The contractor must provide all labor, materials, equipment, supervision, and services necessary for complete window replacement, including asbestos and lead paint abatement. The contractor is responsible for procuring new materials per manufacturer's installation instructions, conducting field verification of existing conditions, obtaining operation and maintenance documentation, providing a one-year warranty on materials and installation, and removing construction debris and hazardous materials in compliance with Department of Veterans Affairs infection control procedures and Federal and State Environmental Protection regulations. The contractor must also initiate and facilitate applicable utility rebates or incentives on the VA's behalf.

The work must be phased to minimize disruption to hospital operations and must be completed within 483 days. The place of performance is Mann-Grandstaff VA Medical Center, located at 4815 North Assembly Street, Spokane, Washington 99205. Normal construction work hours are 7:00 AM to 4:00 PM Monday through Friday, with modifications requiring written approval from the Contracting Officer Representative (COR). No work is permitted on Federal Holidays or weekends when a Federal Holiday falls on Monday or Friday. The contractor must coordinate all deliveries through the M&O Loading Dock Building 1, provide construction dumpsters with safety fencing, and protect pavement from loading and unloading damage. All equipment and supplies are the contractor's responsibility, as no Government-Furnished Equipment will be provided. The COR will evaluate all work and testing to ensure items are in clean condition and acceptable working order.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--CON-NRM-668-24-102 Replace Windows Building 1, newest first.
File Type Posted
36C26026R0011 0004.docx DOCX document
668-24-102 Technical Questions Consolidated Responses updated 4-3-2026.pdf PDF
Attachment 11- Cost Division Breakout Version 1.xlsx XLSX spreadsheet
24-046.2 MGVAMC Summer 2024 AHERA 3-Year Reinspection Rpt_.pdf PDF
82-1000 VA Spokane Windows HazMat Survey Report _no dwgs.pdf PDF
36C26026R0011 - 668-24-102 - Questions with Consolidated Responses.pdf PDF
36C26026R0011_1 Solicitation Page 27.pdf PDF
36C26026R0011 0003.docx DOCX document
36C26026R0011 0002.docx DOCX document
668-24-102 Pre-Bid Walk-Through Sign In.pdf PDF
Attachment 13 - 668-24-102 - Site Visit Area Map - Revised.pdf PDF
36C26026R0011 0001.docx DOCX document
36C26026R0011_1.docx DOCX document
Attachment 12 - 668-24-102 - Spokane Wage Determination 1_23_26.pdf PDF
Attachment 9 - 668-24-102 - Contractor Rules of Behavior.pdf PDF
Attachment 4 - 668-24-102 - PCRA_VHA PCRA.pdf PDF
Attachment 13 - 668-24-102 - Site Visit Area Map.pdf PDF
Attachment 6 - 668-22-102 - LEVEL 3 Window project VHA ICRA.pdf PDF
Attachment 2 - 668-24-102 - BID SET DRAWINGS.pdf PDF
Attachment 11 - 668-24-102 - Cost Division Breakout.xls XLS spreadsheet
Attachment 10 - 668-24-102 - Past Performance Questionnaire.docx DOCX document
Attachment 8 - 668-24-102 - Limitations on Subcontracting-Construction.pdf PDF
Attachment 7 - 668-24-102 - Hazardous Survey Report.pdf PDF
Attachment 5 - 668-24-102 - LEVEL 2 Window project VHA ICRA.pdf PDF
Attachment 3 - 668-24-102 - BID SET SPECIFICATIONS 2_18_26.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

STATEMENT OF WORK FOR CONSTRUCTION SERVICES

Replace Windows Building 1 Project No. 668-24-102

Mann-Grandstaff VA Medical Center Spokane, WA

February 10, 2026

1. Contract Title. 668-24-102 Replace Windows Building 1

2. General.

The Veterans Affairs (VA) Spokane Healthcare System, Spokane, WA requires labor, materials, equipment, and other services as necessary for the replacement of windows in Building 1. Scope of work is indicated below.

3. Scope.

In accordance with the Drawings and Specifications, this project will replace the existing pre-1990 exterior windows of Building 1 at Mann-Grandstaff VA Medical Center (MGVAMC).

Building 1 is the main hospital building with nine (9) occupied floors (Basement – Eighth Floor), a mechanical penthouse (Ninth Floor) and an elevator machine room (Tenth Floor).

Some of the Building 1 exterior windows have been replaced post-1990 and will not be addressed in this project. The contractor shall provide all supervision, labor, tools and materials, installation, Operation and Maintenance (O&M) documentation, and one-year warranty of materials and installation in addition to all other warranty requirements per the project specifications.

3.1. Contractor work includes asbestos and lead paint abatement.

3.2. Contractor shall do a field verification to ensure all equipment, parts and materials are identified and verify all the existing conditions.

3.3. The materials to be installed shall be new and installed per Manufacturer’s

Installation instructions.

3.4. With execution of the Contract, and approval of the submittals the Contractor is authorized to procure materials immediately thereafter.

3.5. The existing windows and associated components of end item, once removed, becomes the property of the Contractor.

3.6. Construction debris and hazardous materials must be removed and disposed of in accordance with the Department of Veteran Affairs Infection Control Procedures, Federal and State Environmental Protection Procedures, and the published construction waste management policy for contractor work on a VA Campus.

Contractor is responsible for initiating and facilitating any applicable rebates or incentives on the VA’s behalf with the local utility company or any other program where rebates or incentives are available.

3.7. This work shall be phased to reduce and mitigate disruption to hospital operations.

4. Deliverables

2 | P a g e

Inspection, testing, and warranty documents and manuals in accordance with the specifications.

5. Performance Monitoring The COR will evaluate all work and testing performed. Items must be in a clean state and in an acceptable working condition.

6. Additional Requirements

6.1. Project number and the contract number in the subject line of all emails.

6.2. Contractors shall comply with the Veterans Administration Smoking Policy.

6.3. Normal construction work hours are 7:00AM to 4:00PM Monday through Friday, unless other specified in the SOW.

6.4. Normal work hours can be modified only by written approval of the COR.

6.5. No work by the Contractor on Federal Holidays, and no work on the weekend when the Federal Holiday is on the respective Monday or Friday.

6.6. Deliveries and Parking: Deliveries into Building 1 only at the M&O Loading Dock Building 1, and coordinated with the Contracting Officer Representative (COR). At time of delivery: remove the vehicle as soon as delivery is complete.

6.7. Contractors shall provide construction dumpsters with a surrounding safety fence.

Pavement to be protected from damage of loading and unloading the dumpster and dumpster weight.

7. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI).

The Contractor will not have access to any Government-Furnished Equipment. All equipment and supplies used under the terms of this contract will be the responsibility of the Contractor.

8. Place of Performance.

Mann-Grandstaff VA Medical Center, located at 4815 North Assembly Street, Spokane Washington 99205.

9. Period of Performance.

The Contractor has 483 days to perform all described work.

Replace Windows Building 1
2. General.
3. Scope.
4. Deliverables
5. Performance Monitoring
6. Additional Requirements
7. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI).
8. Place of Performance.
9. Period of Performance.