This Statement of Work (SOW) details a renovation project for the Sterile Processing Service (SPS) located in Building 1 at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The contract (668-22-104) requires a contractor to renovate 1,200 square feet, addressing architectural, life safety, mechanical, electrical, plumbing, and data system deficiencies to restore full functional capacity of the SPS department. The project scope includes providing all labor, materials, and equipment, with a total project duration of 180 calendar days, and requires the contractor to perform field verification, installation, system testing, commissioning, training for VA personnel, and provide a one-year warranty on materials and installation.
Key deliverables include inspection and testing documents, operation and maintenance manuals, and warranty documents. The contractor must provide a qualified manufacturer's representative to verify installation conformance, run an operating test in the presence of the Contracting Officer's Representative (COR), and demonstrate system operation and calibration. The work will be performed at the VA Medical Center located at 4815 North Assembly Street in Spokane, Washington, with the contractor responsible for all equipment and supplies used under the contract terms.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
Mann-Grandstaff VA Medical Center
Spokane, WA March 20, 2025
1. Contract Title. 668-22-104 Renovate Building 1 SPS and Lab Space
2. General.
The Veterans Affairs (VA) Spokane Healthcare System, Spokane, WA requires labor, materials, and equipment for the renovation of the Sterile Processing Service located in Building 1 (Main Hospital). Scope of work is indicated below. Total project duration shall be 180 calendar days.
3. Scope.
In accordance with the Drawings and Specifications, this project will renovate 1,200 square feet and correct deficiencies and incomplete work resulting from a Minor project in the Sterile Processing Service department located in Building 1E, 2nd floor (west wing of the main hospital). Contractor is required to address: architectural and life safety concerns, mechanical/HVAC, electrical power distribution, plumbing omissions and water distribution inefficiencies, data and other building system deficiencies which are preventing full functional capacity of the SPS. The contractor shall provide all supervision, labor, tools and materials, installation, programming, startup, training, O&M documentation and one-year warranty of materials and installation. The contractor shall do a field verification to ensure all equipment, parts and materials are identified and verify all the existing conditions.
3.1. The contractor shall provide a qualified manufacturer’s representative to check complete installation for conformance to manufacturer’s recommendation, to place the system into service, to make all adjustments required for full conformance to design and specified requirements and to perform all demonstrations and testing.
3.2. An operating test shall be run in the presence of the Contracting Officer’s Representative (COR).
3.3. The contractor shall provide Commissioning documentation.
3.4. The contractor shall provide demonstration and training for VA personnel.
3.5. The contractor shall verify locations for space requirements.
4. Deliverables:
Inspection, testing documents, and manuals and warranty documents per section 3 above.
5. Performance Monitoring
The COR will evaluate all work and testing performed. Items must be in a clean state and in proper and acceptable working condition.
6. Government-Furnished Equipment (GFE)/Government-Furnished Information
(GFI).
The Contractor will not have access to any Government-Furnished Equipment. All equipment and supplies used under the terms of this contract will be the responsibility of the Contractor.
7. Inspection and Acceptance Criteria.
As part of final system acceptance, a systems demonstration is required. Prior to start of this demonstration, the contractor is to perform a complete validation of all aspects of the Controls and Instrumentation System. System operation and calibration shall be demonstrated by the installer in the presence of the COR.
8. Place of Performance.
VA Medical Center Spokane Washington, located at 4815 North Assembly Street, Spokane Washington 99205.
9. Period of Performance.
The Contractor has 180 days to perform all described work.