OVERHAUL FREQUENCY CONVERTER No. 6 AT BUILDING 1805 IN THE U. S. COMMANDER FLEET ACTIVITIES, YOKOSUKA
Solicitation number
N4008423T0402
Issued by

About this file

This document summarizes a federal contract solicitation to overhaul frequency converter number six at Building 1805 in Yokosuka, Japan for the U.S. Navy. The solicitation requires replacing windings of a motor and generator, cables, devices and accessories, and bearings. It also requires removing existing wiring and cables from the existing frequency converter and terminal board, providing and installing new motor, generator, and control panel boards, and providing new wiring, cables, and conduits to reconnect the new control panels to the existing frequency converter and terminal board. The contractor must also provide functional testing for the completed frequency converter system. The solicitation was issued by the Department of the Navy Naval Facilities Engineering Command for repair and upgrade of electrical infrastructure at the specified building.

View the file

Other files

File Type Posted
AMEND 0003.pdf PDF
AMEND 0002.pdf PDF
AMEND 0001.pdf PDF
23T0402A.pdf PDF
Attachment 3-AcceptableID.pdf PDF
Attachment 2-PPI Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overhaul (OH) No.6 Frequency Converter (FC)

At

Bldg. 1805, In the U.S. Commander Fleet Activities Yokosuka (CFAY), JAPAN

By

Non-Recurring Contract (One Time Contract)

Prepared By: NAVFAC FE PRY 231 Name: T. Toriyama Date: 15 May 2020

Specification Approved By: NAVFAC FE PRY23 FSC Management & Facilities Services Department, FSCM

Name Date

Specification Approved By: NAVFAC FE PW2 Facility Support Contract and Facility Management Product Line Coordinator

Name Date

S/R#19117587 / ePro# 1669853 (CFAY Fund )

CONTROLLED UNCLASSIFIED INFORMATION (CUI)

CONTROLLED UNCLASSIFIED INFORMATION (CUI)

BARTON.THOMAS.JOSIAH.I

II.1159801787

Digitally signed by

BARTON.THOMAS.JOSIAH.III.115980178

BARTON.THOMAS.JOSIAH.

III.1159801787

Digitally signed by

BARTON.THOMAS.JOSIAH.III.1159801787

Date: 2020.08.31 13:06:42 +09'00'

B-1

Part I - The Schedule

SECTION B: SUPPLIES OR SERVICES AND PRICES/COSTS

Table of Contents

Para No. Title Page No.

B.1 CONTRACT LINE ITEMS AND EXHIBIT LINE ITEMS B-2

B.2 MAXIMUM QUANTITIES B-2

B.3 NON-RECURRING CONTRACT LINE ITEM QUANTITIES B-2

SCHEDULE OF PRICE B-3

B-2

PART I - THE SCHEDULE

SECTION B: SUPPLIES OR SERVICES AND PRICE/COSTS

B.1 CONTRACT LINE ITEMS AND EXHIBIT LINE ITEMS

A. Bidders/Offerors shall enter unit prices and amounts for contract line items (CLINs) and exhibit line items (ELINs) as indicated in the schedules and the accompanying exhibits, Attachment J-0200000-07.

B. In the event that there is a difference between a unit price and the extended total amount, the unit price will be held to be the intended bid/offer and the total of the CLINs or ELINs will be recomputed accordingly. The CLIN which includes recomputed contract ELINs will also be recomputed to take into account the change in the contract ELIN. If the bidder/offeror provides a total amount for a CLIN or ELIN but fails to enter the unit price, the total amount divided by the CLIN or ELIN will be held to be the intended unit price.

B.2 MAXIMUM QUANTITIES

The Government intends to award an Indefinite-Delivery Indefinite-Quantity (IDIQ) contract.

The minimum guaranteed amount is under CLIN 0001. Option years may/may not be exercised.

See the option clause for the contract. The maximum shall not be exceeded except as may be provided for by formal modification to the contract. Task/Delivery orders to be issued under CLINs 0001, 0002, 0003, 0004, and 0005, may be ordered by the Government within the maximum, not-to-exceed amount.

B.3 NON-RECURRING CONTRACT LINE ITEM QUANTITIES

The estimated line item quantities for the indefinite quantity portion of the contract may be unilaterally increased by the Contracting Officer by one unit or 30%, whichever is greater, so long as the total estimated contract price is not exceeded. The Contractor is not obligated to furnish any additional quantity under a line item beyond 130%. Any quantity greater than 130% of the original contract line item may be ordered at the bid price if the Contractor agrees by signing the task order.

CUI // FEDCON

SOURCE SELECTION SENSITIVE--See FAR 2.101 and 3.104 B-3

CUI // FEDCON

NAME OF OFFEROR OR CONTRACTOR:

LINE ITEM Q'TY UNIT AMOUNT

NO.

Item 0001 OH No.6 Frequency Converter 1 LS ¥

TOTAL: ¥

CLIN 9000 Exhibit A (Base Period)

Detail line items for task order is located in Attachment J-0200000-07

CLIN = CONTRACT LINE ITEM

Q'TY = QUANTITY

SCHEDULE OF PRICE

ITEM

SOURCE SELECTION SENSITIVE--See FAR 2.101 and 3.104

C-1

SECTION C

Index Annex Sub Annex Spec Item # Title

Annex 1 0100000 1 General Information

Annex 2 0200000 2 Management and Administration

Electrical Services Annex 16 1602000 1 General Information

Annex 16 1602000 2 Management and Administration

Annex 16 1602000 3 Recurring Work …....…. Not Applicable

Annex 16 1602000 4 Non-recurring Work

SECTION C – 0100000

GENERAL INFORMATION

0100000 – General Information Spec Item Title 1 General Information

1.1 Outline of Services

1.2 Acquisition of Additional Work

1.3 Background Information

1.4 Navy PBSA Approach

1.5 Standard Template

1.6 Related Information

1.7 Verification of Workload and Conditions

1.8 Contractor's Knowledge

1.9 Technical Proposal Certification

Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at at Bldg. 1805 , in the U.S. Commander Fleet Activities Yokosuka (CFAY), Japan supported by this installation performance-based contract that is comprised of Non-Recurring Work Items.

The PWS is organized into annexes. Annex 1 is "General Information".

Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.

The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven (7) digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff Not Applicable (N/A) Annex 4 Public Safety N/A Annex 5 Air Operations N/A Annex 6 Port Operations N/A Annex 7 Ordnance N/A Annex 8 Range Operations N/A Annex 9 Health Care Support N/A Annex 10 Supply N/A Annex 11 Personnel Support N/A Annex 12 Morale, Welfare and Recreation Support N/A Annex 13 Galley N/A Annex 14 Housing N/A Annex 15 Facilities Support N/A Annex 16 Utilities Annex 17 Base Support Vehicles and Equipment N/A Annex 18 Environmental N/A

1.2 Acquisition of

Additional Work

The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.3 Background Information Commander Fleet Activities Yokosuka Our mission is to maintain and operate base facilities for the logistic, recreational, administrative support and service of the U.S. Naval Forces Japan, U.S. SEVENTH Fleet and other operating forces forward-deployed in the Western Pacific.

Commander Fleet Activities, Yokosuka comprises 568 acres and is located 43 miles south of Tokyo at the entrance of Tokyo Bay and approximately 18 miles south of Yokohama. Yokosuka is on the Miura peninsula in the Kanto Plain region of the Pacific Coast in Central Honshu, Japan. CFAY is the largest overseas U.S. Naval installation in the world and is considered to be one of the most strategically important bases in the U.S. military.

Additional information for Commander Fleet Activities Yokosuka is available at: https://www.cnic.navy.mil/Yokosuka/index.htm

1.4 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts, which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.

The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract. Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.

Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.

Specification Items 3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their price shall be allocated to the Exhibit Line Items.

1.6 Related Information There are four (4) types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors’ to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors’ may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractually binding requirement on either party.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

https://www.cnic.navy.mil/Yokosuka/index.htm

Requirement Information further describes client requirements associated with each Performance Objective.

1.7 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.

All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.

As prescribed in FAR 52.237-1, offerors’ or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

1.8 Contractor's Knowledge The Navy expects to receive insightful management from its contractors.

This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.9 Technical Proposal

Certification

The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.

Section C – 0200000

Management and Administration

0200000 – Management and Administration

2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Directives, Instructions, and References

2.3.8 Invoicing Procedures

2.3.9 Forms

2.3.10 Performance Evaluation

2.4 Government-Furnished Items

2.4.1 Government-Furnished Property (GFP)

2.4.2 Government-Furnished Facilities

2.4.3 Government-Furnished Vehicles and Equipment

2.4.4 Government-Furnished Utilities

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Safeguarding Information

2.6.2 Dissemination of Information

2.6.3 Work Reception

2.6.4 Work Control

2.6.5 Work Schedule

2.6.6 Deliverables

2.6.7 Service Interruptions

2.6.8 NAVFAC MAXIMO

2.6.9 Quality Management System (QMS)

2.6.9.1 Quality Management (QM) Plan

2.6.9.2 Quality Inspection and Surveillance

2.6.9.3 Quality Inspection and Surveillance Report

2.6.10 Property Management Plan

2.6.11 System and Equipment Replacement

2.6.12 Mobilization

2.6.12.1 Mobilization/Phase-In

2.6.12.2 Demobilization/ Phase-Out

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager

2.7.1.2.1 Quality Control Personnel

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee List

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Controlled Unclassified Information

2.8.8.1 Information Security

2.8.8.2 Information Safeguarding Requirements

2.8.8.3 Disclosure of Information Requirements

2.8.8.4 Operations Security (OPSEC) Requirements

2.8.8.5 Violation of the Information Security Requirement

2.8.9 Access to Government Information Technology (IT), Operation Technology (OT), and Facility

Related Control Systems (FRCS)

2.8.10 Access to Navy Marine Corps Intranet (NMCI)

2.8.11 Employee Status

2.9 Contractor Safety Program

2.9.1 Contractor Safety Requirements

2.9.1.1 Experience Modification Rate (EMR)

2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate

2.9.2 Accident Prevention Plan (APP)

2.9.3 Activity Hazard Analysis (AHA)

2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.4.1 Alcohol and Drug Abuse Prevention Plan

2.9.4.2 Chemical Hazard Communication Program

2.9.4.3 Confined Space Program

2.9.4.4 Critical Lift Plan

2.9.4.5 Fall Prevention and Protection Plan

2.9.4.6 Pathogen Exposure

2.9.4.7 Control of Hazardous Energy (lockout/tagout)

2.9.5 Crane Operations

2.9.5.1 Crane Inspections

2.9.5.2 Rigging Gear

2.9.5.3 Crane Operators

2.9.6 Accident and Damage Reporting

2.9.6.1 Accident Reporting and Notification Criteria

2.9.6.2 CFAY Accident Reporting Notification

2.9.7 Fire Protection

2.9.8 Monthly On-Site Labor Report

2.9.9 OSHA Citations and Violations

2.9.9 Japanese Labor Standards Inspection Office (LSIO) Citations and Violations

2.9.10 Safety Inspections and Monitoring

2.9.11 Safety Certification

2.9.12 Safety Apparel on Jobsites

2.9.13 Emergency Medical Treatment

2.9.14 Excavations

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services

2.10.2.2 ODS Requirements for Refrigerant Recycling

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Hazardous Waste Disposal

2.10.2.5 Regulated Waste Disposal

2.10.2.6 Universal Waste

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.2.11 Salvage

2.10.2.12 Asbestos Containing Material (ACM)

2.10.2.13 Air Quality

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Biobased Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Direct Material and Construction Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-recurring work ELINs

2.16 Performance Evaluation

0200000 - Management and Administration

2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0800-1645, five (5) days per week, Monday through Friday, except observed Federal holidays.

Exceptions to the regular hours of operation are detailed in subsequent sections of this performance work statement (PWS). Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the Contracting Officer (KO) prior to commencement of work.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.

Unless otherwise specified, the Contractor’s normal working days for performing contract requirements are from Monday through Friday except federal holidays, During carrier port at Berth 12, the overhaul (OH) work will not be allowed.

2.2.2 Wage

Determinations

N/A.

2.2.3 Requirements

Hierarchy

Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative Requirements

2.3.1 Required

Conferences and Meetings

The Contractor shall attend administrative and coordination meetings. The Pre-Performance Conference meeting shall be held within 14 calendar days after the date of award. The Contractor shall attend meetings as shown in J- 0200000-02. Submit request for the pre-performance conference per section F.

The Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Section F for review and comments. Comments received within two (2) working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F for concurrence.

Required meetings may be held remotely as directed by KO.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from Naval Facilities Engineering Systems Command (NAVFAC), the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

- The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.

2.3.3.1 Informal

Partnering

The KO shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel.

The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated by the KO. The senior Government stakeholder present will lead the meeting, however, the Contractor’s Project Manager (PM) or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.2 Contract

Partnering Administration

Upon award, the Administrative Contracting Office (ACO) will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract

Partnering Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

President/Vice President

* Project Manager (PM)

* Quality Manager (QM) Site Safety and Health Officer (SSHO)

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, host nation (Japanese), prefecture, and local laws and regulations.

The Contractor shall submit copies of Permits and Licenses per Section F.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause

52.228-5, INSURANCE – WORK ON A GOVERNMENT

INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Comprehensive General Liability: ¥50,000,000 per occurrence

Automobile Liability: ¥20,000,000 per person, ¥50,000,000 per occurrence for bodily injury, ¥3,000,000 per occurrence for property damage

Workmen's Compensation: As required by Japanese worker's compensation and occupational disease statutes

Employer's Liability coverage: ¥10,000,000

Other as required by Japanese Law

Above insurance coverage’s are to extend to Contractor personnel operating Government-owned equipment and vehicles.

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.

2.3.7 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in throughout the various Performance Work Statements and their respective J Attachments. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.8 Invoicing

Procedures

Refer to Section G for invoicing instructions. Refer to Invoice Form in J- 0200000-04 for sample, and following accessible address of WAWF's website: https://piee.eb.mil/ Login address of above:

https://piee.eb.mil/xhtml/unauth/home/login.xhtml

Invoices shall be submitted in a format compatible with the most recent Government installed Microsoft Office Version (currently 2016). Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title.

One time contract invoices required performance record, unless otherwise direction by the KO.

2.3.9 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-04.

2.3.10 Performance

Evaluation

The Contractor’s performance will be evaluated using the Contractor Performance Assessment Reporting System (CPARS) located on the website https://piee.eb.mil/ https://piee.eb.mil/xhtml/unauth/home/login.xhtml https://www.cpars.gov. On-line training for Contractor personnel is available on the website.

Prior to commencement of work the Contractor is required to provide the Government with the name, phone number and e-mail address of the “Contractor’s Representative” that will be responsible for receipt and review of draft performance evaluations prepared by the Government. It is the Contractor’s responsibility to keep this contact information current and provided changes to the KO.

2.4 Government-

Furnished Items

Except for items identified below as Government-Furnished, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services described in this PWS.

Government-Furnished Items will be provided in "AS-IS" condition and their use is at the option of the Contractor. The total or partial breakdown or failure of Government-Furnished Items shall not relieve the Contractor of the responsibility to perform the requirements of this contract.

The Contractor shall provide periodic servicing, maintenance, and repair of the Government-Furnished Items accepted for use at no additional cost to the Government. Servicing, maintenance, and repair shall be provided in accordance with the manufacturer’s recommendations. The Contractor shall generate work orders in NAVFAC Maximo per Spec Item 2.6.8 for all servicing, maintenance, and repair activities performed on Government- Furnished Items.

At the completion of the contract, all Government-Furnished Items shall be returned to the Government in the same condition as received, except for reasonable wear and tear. Government-Furnished Items, which becomes worn out due to normal wear and tear, shall be returned to the Government and its replacement shall be the responsibility of the Contractor at no additional cost to the Government. The Contractor shall be responsible for the cost of any repairs or replacement caused by Contractor negligence or abuse.

The Government may inspect Government-Furnished Items at any time and without notice.

2.4.1 Government-

Furnished Property

(GFP)

None.

2.4.2 Government-

Furnished Facilities

None.

2.4.3 Government-

Furnished Vehicles and Equipment

None.

2.4.4 Government-

Furnished Utilities

The Government will make available water and electricity at existing outlets required for the work to be performed under the contract. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, https://www.cpars.gov/

State, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.

The Contractor is responsible for the cost of all utilities at all Government-provided facilities and any additional Contractor-owned facilities, at prevailing Naval Station rates. The Contractor will be billed directly for all utilities provided to all Contractor occupied facilities. Utility rates billed to the Contractor will be at the following rates:

1. Electrical - the current rate for electrical services is $242.01 MWH

2. Water - the current rate for water is $13.74 per KGAL

3. Wastewater (Sewage) - the current rate for sewage services is $8.88 per

KGAL, based on 100% of the water consumption

Variations in Rates: Utility rates are subject to change. Changes in one or more utility rates shall not be basis for adjustment to the contract price or a claim unless the deviation from the quoted price for a utility rate exceeds 15%. When a utility rate varies by more than 15%, the contract price will be adjusted to reflect the amount the actual charge exceeds the rate quoted;

however, the Government will only be liable for the amount of cost exceeding 15% of the rate quoted. For example, if a quoted rate increases by 16%, the Government will only be liable for 1% of the rate increase. Vice versa if the quoted rate decreases by 16%.

Historically, electrical and water utility consumption at the Facilities provided of Contractor use has averaged approximately 351 MWH of electricity and 316 KGAL annually. However, historical data associated with contracts prior to this solicitation may present data that may not be representative of the requirements specified in this contract.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.

Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Safeguarding

Information

The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP 800-171, SECNAV Defense Industrial Base (DIB) Memo, DoDI 5200.48, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800-

171. Refer to Spec Item 2.8.8.3 Disclosure of Information Requirements, and

DI-MGMT-82247 Contractor’s System Security Plan and Associated Plans of Action to Implement NIST SP 800-171 on a Contractor’s Internal Unclassified Information System, for more detailed information.

Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management Framework (RMF).

The Contractor shall develop Plans of Action and Milestones (POA&Ms) per NIST SP 800-171, track accomplishment, and submit to the Government per Section F.

If a cybersecurity incident is encountered or suspected related to any (Contractor or Government) Information Technology (IT) or Operating Technology (OT) systems, including Monitoring and Control Systems, the Contractor shall notify the Government per Section F.

2.6.2 Dissemination of

Information

DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.

2.6.3 Work Reception Unless otherwise specified hereinafter, the Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls/order and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.

2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.

The Contractor shall provide work schedules for both Recurring and Non- Recurring Work per Section F. At a minimum, work schedules shall include:

• Description of service(s) to be accomplished

• Location

• Date service(s) are scheduled to be accomplished

2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business.

In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall provide written notification of any difficulty in scheduling work due to Government controls per Section F. At a minimum, the notification shall include the following:

• The date and time the work was initially coordinated.

• The name and phone number of the Government person with whom the work was initially coordinated.

• The name and phone number of the Government person who prevented the work from being performed as previously coordinated.

• The alternative date and time, the Government person requested the work be accomplished.

2.6.6 Deliverables Except where otherwise stated, deliverable requirements are specified in Sections C, F, H, I, J, and within the Directives, Instructions, and References.

The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government. All Contractor submittals shall be in English or may be submitted in Japanese with English translations.

Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office 2016 or Current Version compatible format. Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable. Refer to DoDI 5200.48 for marking requirements (as applicable).

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

The Government shall take ownership of all the Management and Administration submittals to include but not limited to those listed in Section F. The Contractors including relating OEM, agency and personnel shall not claim any ownership of the submittals to the Government.

The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website. Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.

2.6.7 Service

Interruptions

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures.

If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, affected tenants, and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.

The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.

The Contractor shall request approval of service interruptions in writing per Section F. As soon as the request is approved by the KO/Security/Fire Department or other Department, the Contractor shall notify the affected tenants, and customers of the outage or closure. Depending on the scale of the work, the Contractor may have to submit the request much earlier than per Section F prior to the requested date. The Contractor shall consult with the KO for scheduling through the COR in advance of service interruption. The Contractor shall consult with the Fire Department for any fire protection system outage and shall obtain permission and instruction from the Fire Department per J-0200000-04 through the COR. Fire protection system outage required during any of the Contractor’s work shall not exceed four hours in a 24 hour period. If more than a four hour system outage is needed, the Contractor shall obtain prior permission from Base Fire Department by providing an approved alternate protection including but not limited to, adequate fire watch during the outage period (exceeding the four hour period) in accordance with NFPA 101, Chapter 9.

2.6.8 NAVFAC

MAXIMO

N/A.

2.6.9 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

• Accurate documentation of work processes, procedures, and output measures.

• A systematic procedure for assessing compliance with performance objectives and standards.

• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

The Contractor QMS Pre-Performance Review Checklist for compliance with this requirement is provided in J-0200000-04.

2.6.9.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the Contractor shall submit the revised QM Plan for acceptance per Section F.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel/employee o Organization chart o Responsibilities & lines of authority o Training and qualifications o Quality manager resume

• Approach to assuring quality of services provided and conformance with performance objectives and standards

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services to include all contractual requirements.

o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.9.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Section F.

2.6.9.3 Quality Inspection

and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. E.g. Updates for incorrect or missing information discovered in maintenance inventories provided.

The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

2.6.10 Property

Management Plan

The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Items, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, key control, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.

2.6.11 System and

Equipment Replacement

The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work.

Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.

2.6.12 Mobilization

2.6.12.1 Mobilization/Phase

-In The Contractor shall develop and submit a Mobilization/Phase-In Plan per Section F for Government review and acceptance. The plan shall include at a minimum, a time line on how the Contractor will mobilize/phase-in, 60 calendar days prior to full contract performance. The Contractor shall phase-in in accordance with the Government-accepted Mobilization Plan and in partnership with the outgoing Contractor so as to minimize disruption to the mission of BOSC clients. The new Contractor shall be allowed access to Government facilities to familiarize key personnel and top functional managers with property, existing operations, and procedures. However, to preclude interference with the work efforts of the incumbent Contractor, arrangements for access to Government facilities shall be made with the KO.

2.6.12.2 Demobilization/

Phase-Out

The Contractor shall submit a Demobilization/Phase-Out Plan per Section F for Government review and acceptance. The plan shall include at a minimum, a time line on how the Contractor will demobilize/phase-out, 60 calendar days prior to contract end. The Contractor shall phase out in accordance with the Government-accepted Demobilization Plan and in partnership with the incoming Contractor so as to minimize disruption to the mission of BOS clients. The plan shall include the Contractor’s plan to familiarize the incoming Contractor’s key personnel and top functional managers with existing operations, property, and procedures, completing a Reconciliation Survey, and the Contractor’s strategy for transferring work-in-progress to the new Contractor. The plan shall also provide for Contractor contingency services during the Demobilization/Phase-Out period in the event of:

(1) a work disruption or stoppage or

(2) the incumbent’s inability to fill a vacated position during the

Demobilization/Phase-Out period.

During the Demobilization/Phase-Out period, the Contractor shall be responsible for full performance of all sub-annexes through the last day of the contract.

The Government reserves the right to conduct site visits in all Contractor operated facilities in conjunction with the solicitation of offers for the follow-on contract. In the event the follow-on contract is awarded to other than the incumbent, the incumbent Contractor shall cooperate to permit an orderly changeover to the successor Contractor. A recruitment notice may be placed by the successor Contractor in each facility during the Phase-In period of the follow-on contract.

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below.

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract.

The key personnel shall be revised as applicable for the contract. >>

The Contractor shall provide complete resumes for proposed substitutes and any additional information requested by the KO. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.

Key personnel shall be able to speak, read and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures or an interpreter shall be made available at no additional cost to the Government.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who shall have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be available on-site within one day after the Government requests.

The PM shall have at least five years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate who shall be on-site within one day after the Government request. The Quality Manager or designated alternate shall report directly to a senior corporate official and shall not report directly to the PM. The Quality Manager shall not be the same person as the Project Manager.

The Quality Manager or designated alternate shall have fulfilled the following pre-requisite training and experiences…