ATTACHMENT 09 - 655-401 Expand Site Construction Schedule_APP.pdf
PDF 651 KB Posted
- Solicitation number
- 36C77624R0154
About this file
This is a detailed construction schedule Gantt chart for project #655-401, showing an 18-month timeline from January 2025 to July 2026 for expanding a medical center site. The schedule is broken down into 8 major phases plus preconstruction and turnover activities.
The project begins with a 3-month preconstruction phase starting January 2, 2025, including permit and submittal reviews. Construction phases include: Phase 1 - Preliminaries and North Demolition (1 month), Phase 2 - Watermain and Electrical (1.5 months), Phase 3 - South Demolition (1 month), Phase 4 - Sanitary and Storm Sewers in South Portion (1.5 months), Phase 5 - Northern Portion Utilities (0.75 months), Phase 6 - Pavement Preparation (5.75 months, including 4.5-month seasonal delay), Phase 7 - South Paving (1.25 months), and Phase 8 - North Paving and Restoration (1.5 months). The project concludes with a 1-month turnover period including punchout, commissioning, and inspections, with final completion scheduled for July 6, 2026.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish
1 655-401 Construction Schedule 18 mons Thu 1/2/25 Mon 7/6/26
2 Preconstruction 3 mons Thu 1/2/25 Thu 4/3/25
3 Contract Award 0 mons Thu 1/2/25 Thu 1/2/25
4 Permit Review 3 mons Thu 1/2/25 Thu 4/3/25
5 Submittal Review 3 mons Thu 1/2/25 Thu 4/3/25
6 Construction 15 mons Thu 4/3/25 Mon 7/6/26
7 Contractor Mobilization 0.25 mons Thu 4/3/25 Thu 4/10/25
8 Mobilize 0.25 mons Thu 4/3/25 Thu 4/10/25
9 Phase 1 - Preliminaries and North Demolition
1 mon Thu 4/10/25 Mon 5/12/25
10 Place SESC Measures 0.25 mons Thu 4/10/25 Fri 4/18/25
11 Install Temporary Construction Fencing 0.25 mons Thu 4/10/25 Fri 4/18/25
12 Perform Removals 0.75 mons Fri 4/18/25 Mon 5/12/25
13 Rough Grade 0.75 mons Fri 4/18/25 Mon 5/12/25
14 Phase 2 - Watermain and Electrical 1.5 mons Mon 5/12/25 Thu 6/26/25
15 Sanitary Sewer Mh330 – Mh332 and Water Main
0.5 mons Mon 5/12/25 Tue 5/27/25
16 Traffic Control in Existing Parking Lot for Watermain Connection and Bore and Jack
0.25 mons Tue 5/27/25 Wed 6/4/25
17 Install Storm Sewer Mh353 – Mh355 0.25 mons Tue 5/27/25 Wed 6/4/25
18 Install Temporary Electric from Previous Trailer Feed to New Construction Trailer Area
0.25 mons Wed 6/4/25 Wed 6/11/25
19 Install Electric Connection Points for Trailers
0.25 mons Wed 6/11/25 Thu 6/19/25
20 Pavement Restoration in Existing Lot 0.25 mons Thu 6/19/25 Thu 6/26/25
21 Phase 3 - South Demolition 1 mon Thu 6/19/25 Fri 7/18/25
18 mons 655-401 Construction Schedule
3 mons Preconstruction
0 mons
3 mons
3 mons
15 mons Construction
0.25 mons Contractor Mobilization
0.25 mons
1 mon Phase 1 - Preliminaries and North Demolition
0.25 mons
0.25 mons
0.75 mons
0.75 mons
1.5 mons Phase 2 - Watermain and Electrical
0.5 mons
0.25 mons
0.25 mons
0.25 mons
0.25 mons
0.25 mons
1 mon Phase 3 - South Demolition
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026
22 Move Contractor Trailers and Conex Boxes to East Lot
0.25 mons Thu 6/19/25 Thu 6/26/25
23 Construct 24’ Gravel Path And 6’ Limestone Path to Trailers
0.25 mons Thu 6/26/25 Thu 7/3/25
24 Demo Building 0.25 mons Thu 6/26/25 Thu 7/3/25
25 Remaining Demo 0.25 mons Fri 7/4/25 Fri 7/11/25
26 Rough Grade 0.25 mons Fri 7/11/25 Fri 7/18/25
27 Phase 4 - Sanitary and Storm Sewers in South Portion
1.5 mons Fri 7/18/25 Wed 9/3/25
28 Move 80 Space Parking from Southern Portion of Lot to North Area as Shown
0.25 mons Fri 7/18/25 Mon 7/28/25
29 Perform Remaining Removals from Southern Portion
0.5 mons Fri 7/18/25 Mon 8/4/25
30 Construct Sanitary Sewer 0.5 mons Mon 8/4/25 Tue 8/19/25
31 Construct Storm Sewer Including Underground Detention System
0.75 mons Mon 8/4/25 Wed 8/27/25
32 Install Traffic Control and Connect Storm and Sanitary Sewers Into 120” Combined Sewer in Weiss Road
0.25 mons Wed 8/27/25 Wed 9/3/25
33 Phase 5 - Northern Portion Utilities 0.75 mons Wed 9/3/25 Fri 9/26/25
34 Move 80 Temporary Parking Stalls Back to Southern Portion of Lot as Shown
0.25 mons Wed 9/3/25 Thu 9/11/25
35 Install / Complete Utilities in Northern Portion of Site
0.5 mons Thu 9/11/25 Fri 9/26/25
36 Phase 6 - Pavement Preparation 5.75 mons Fri 9/26/25 Fri 3/20/26
37 Construct 24’ Wide North Access to Temporary Parking And 6’ Wide Limestone Path
0.25 mons Fri 9/26/25 Fri 10/3/25
38 Move 80 Space Parking from Southern Portion of Lot to North Area as Shown
0.25 mons Fri 9/26/25 Fri 10/3/25
39 SEASONAL DELAY (ESTIMATED) -
ASPHALT PLANTS & WEATHER
4.5 mons Fri 10/3/25 Wed 2/18/26
40 Perform Fine Grading for Pavement Area 0.25 mons Wed 2/18/26 Thu 2/26/26
41 Place Curb and Gutter 0.25 mons Thu 2/26/26 Thu 3/5/26
42 Place Sidewalk 0.25 mons Thu 3/5/26 Fri 3/13/26
0.25 mons
0.25 mons
0.25 mons
0.25 mons
0.25 mons
1.5 mons Phase 4 - Sanitary and Storm Sewers in South Portion
0.25 mons
0.5 mons
0.5 mons
0.75 mons
0.25 mons
0.75 mons Phase 5 - Northern Portion Utilities
0.25 mons
0.5 mons
5.75 mons Phase 6 - Pavement Preparation
0.25 mons
0.25 mons
4.5 mons
0.25 mons
0.25 mons
0.25 mons
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
43 Place Gravel Base 0.25 mons Fri 3/13/26 Fri 3/20/26
44 Phase 7 - South Paving 1.25 mons Fri 3/20/26 Tue 4/28/26
45 Install Utilities on East Side of City Lot 0.25 mons Fri 3/20/26 Mon 3/30/26
46 Mill Remaining Portion of Existing City Lot Asphalt
0.25 mons Mon 3/30/26 Mon 4/6/26
47 Place Remaining Curb and Gutter and Sidewalk
0.5 mons Mon 3/30/26 Mon 4/13/26
48 Pave Shaded Areas 0.25 mons Mon 4/13/26 Tue 4/21/26
49 Install Landscaping, Signage and Lighting 0.5 mons Mon 4/13/26 Tue 4/28/26
50 Phase 8 - North Paving and Restoration 1.5 mons Tue 4/28/26 Fri 6/12/26
51 Fine Grade North Lot 0.25 mons Tue 4/28/26 Wed 5/6/26
52 Place Curb and Gutter 0.25 mons Tue 4/28/26 Wed 5/6/26
53 Place Sidewalk 0.25 mons Tue 4/28/26 Wed 5/6/26
54 Place Aggregate Base 0.25 mons Wed 5/6/26 Wed 5/13/26
55 Pave North Lot 0.25 mons Wed 5/6/26 Wed 5/13/26
56 Stripe North Lot, Install Landscaping, Signage, Lighting and Permanent Perimeter Fencing
0.5 mons Wed 5/13/26 Thu 5/28/26
57 Turf Establishment 1 mon Wed 5/13/26 Fri 6/12/26
58 Project Cleanup 0.25 mons Thu 5/28/26 Fri 6/5/26
59 Turnover 1 mon Fri 6/5/26 Mon 7/6/26
60 Punchout 0.5 mons Fri 6/5/26 Mon 6/22/26
61 Commissioning 1 mon Fri 6/5/26 Mon 7/6/26
62 Inspections 0.5 mons Mon 6/22/26 Mon 7/6/26
63 Turnover 0 mons Mon 7/6/26 Mon 7/6/26
0.25 mons
1.25 mons Phase 7 - South Paving
0.25 mons
0.25 mons
0.5 mons
0.25 mons
0.5 mons
1.5 mons Phase 8 - North Paving and Restoration
0.25 mons
0.25 mons
0.25 mons
0.25 mons
0.25 mons
0.5 mons
1 mon
0.25 mons
1 mon Turnover
0.5 mons
1 mon
0.5 mons
0 mons