ATTACHMENT 09 - 655-401 Expand Site Construction Schedule_APP.pdf

PDF 651 KB Posted

Attached to
Y1LZ--Expand Medical Center Site Saginaw Minor Construction
Solicitation number
36C77624R0154
Issued by

About this file

This is a detailed construction schedule Gantt chart for project #655-401, showing an 18-month timeline from January 2025 to July 2026 for expanding a medical center site. The schedule is broken down into 8 major phases plus preconstruction and turnover activities.

The project begins with a 3-month preconstruction phase starting January 2, 2025, including permit and submittal reviews. Construction phases include: Phase 1 - Preliminaries and North Demolition (1 month), Phase 2 - Watermain and Electrical (1.5 months), Phase 3 - South Demolition (1 month), Phase 4 - Sanitary and Storm Sewers in South Portion (1.5 months), Phase 5 - Northern Portion Utilities (0.75 months), Phase 6 - Pavement Preparation (5.75 months, including 4.5-month seasonal delay), Phase 7 - South Paving (1.25 months), and Phase 8 - North Paving and Restoration (1.5 months). The project concludes with a 1-month turnover period including punchout, commissioning, and inspections, with final completion scheduled for July 6, 2026.

View the file

Other files

File Type Posted
36C77624R0154_0008.pdf PDF
36C77624R0154_0007.pdf PDF
Amendment 0006 - ATT 4 - VA Signage DM Parking Lot Drawings Pages 538-675.pdf PDF
Amendment 0006 - ATT 3 - 282600 Electronic Personal Protection System_ Edited 12-30-2024 per RFI.pdf PDF
Amendment 0006 - ATT 2 - 282300 Video Surveillance_Edited 1-8-2025 per RFI.pdf PDF
Amendment 0006 - ATT 1 - 655-401 Expand Site - Site Utility Structures 1-8-2025.xlsx XLSX spreadsheet
36C77624R0154 0006.pdf PDF
36C77624R0154 0005.pdf PDF
Amendment 0005 - ATT 05 - Wage Rate Determination - Saginaw 010325.pdf PDF
Amendment 0004 - ATT 2 - Site Visit Sign-In Sheet 12-11-2024.pdf PDF
36C77624R0154 0004.pdf PDF
Amendment 0004 - ATT 1 - Pre Bid Conference - Saginaw.pdf PDF
36C77624R0154 0003.pdf PDF
36C77624R0154 0002.docx DOCX document
ATTACHMENT 08 - Pre-proposal Site Visit Agenda with maps REVISED 112724.pdf PDF
36C77624R0154 0001.pdf PDF
ATTACHMENT 08 - Pre-proposal Site Visit Agenda with maps.pdf PDF
ATTACHMENT 07 - 655-401 GFP Pole Mounted Radar Speed Sign.pdf PDF
ATTACHMENT 11 - 655-401 Expand Site - Site Utility Structures.xlsx XLSX spreadsheet
ATTACHMENT 02-01 - 655-401 Expand Medical Center Site Drawings_R2.pdf PDF
36C77624R0154_1_.docx DOCX document
ATTACHMENT 03 - 655-401 Geotechnical Report 10-27-2021.pdf PDF
ATTACHMENT 05 - Wage Rate Determination - Saginaw 112124.pdf PDF
ATTACHMENT 10 - 655-401 Expand Site - Light Pole Tags.xlsx XLSX spreadsheet
ATTACHMENT 02-02 - 655-401 Expand Medical Center Site Drawings_R2.pdf PDF
ATTACHMENT 06 - Brand Name Justifcation - Saginaw_Redacted.pdf PDF
ATTACHMENT 01 - 655-401 Expand Site - Specifications.pdf PDF
ATTACHMENT 04 - Limitations on Subcontracting - Construction.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish

1 655-401 Construction Schedule 18 mons Thu 1/2/25 Mon 7/6/26

2 Preconstruction 3 mons Thu 1/2/25 Thu 4/3/25

3 Contract Award 0 mons Thu 1/2/25 Thu 1/2/25

4 Permit Review 3 mons Thu 1/2/25 Thu 4/3/25

5 Submittal Review 3 mons Thu 1/2/25 Thu 4/3/25

6 Construction 15 mons Thu 4/3/25 Mon 7/6/26

7 Contractor Mobilization 0.25 mons Thu 4/3/25 Thu 4/10/25

8 Mobilize 0.25 mons Thu 4/3/25 Thu 4/10/25

9 Phase 1 - Preliminaries and North Demolition

1 mon Thu 4/10/25 Mon 5/12/25

10 Place SESC Measures 0.25 mons Thu 4/10/25 Fri 4/18/25

11 Install Temporary Construction Fencing 0.25 mons Thu 4/10/25 Fri 4/18/25

12 Perform Removals 0.75 mons Fri 4/18/25 Mon 5/12/25

13 Rough Grade 0.75 mons Fri 4/18/25 Mon 5/12/25

14 Phase 2 - Watermain and Electrical 1.5 mons Mon 5/12/25 Thu 6/26/25

15 Sanitary Sewer Mh330 – Mh332 and Water Main

0.5 mons Mon 5/12/25 Tue 5/27/25

16 Traffic Control in Existing Parking Lot for Watermain Connection and Bore and Jack

0.25 mons Tue 5/27/25 Wed 6/4/25

17 Install Storm Sewer Mh353 – Mh355 0.25 mons Tue 5/27/25 Wed 6/4/25

18 Install Temporary Electric from Previous Trailer Feed to New Construction Trailer Area

0.25 mons Wed 6/4/25 Wed 6/11/25

19 Install Electric Connection Points for Trailers

0.25 mons Wed 6/11/25 Thu 6/19/25

20 Pavement Restoration in Existing Lot 0.25 mons Thu 6/19/25 Thu 6/26/25

21 Phase 3 - South Demolition 1 mon Thu 6/19/25 Fri 7/18/25

18 mons 655-401 Construction Schedule

3 mons Preconstruction

0 mons

3 mons

3 mons

15 mons Construction

0.25 mons Contractor Mobilization

0.25 mons

1 mon Phase 1 - Preliminaries and North Demolition

0.25 mons

0.25 mons

0.75 mons

0.75 mons

1.5 mons Phase 2 - Watermain and Electrical

0.5 mons

0.25 mons

0.25 mons

0.25 mons

0.25 mons

0.25 mons

1 mon Phase 3 - South Demolition

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026

22 Move Contractor Trailers and Conex Boxes to East Lot

0.25 mons Thu 6/19/25 Thu 6/26/25

23 Construct 24’ Gravel Path And 6’ Limestone Path to Trailers

0.25 mons Thu 6/26/25 Thu 7/3/25

24 Demo Building 0.25 mons Thu 6/26/25 Thu 7/3/25

25 Remaining Demo 0.25 mons Fri 7/4/25 Fri 7/11/25

26 Rough Grade 0.25 mons Fri 7/11/25 Fri 7/18/25

27 Phase 4 - Sanitary and Storm Sewers in South Portion

1.5 mons Fri 7/18/25 Wed 9/3/25

28 Move 80 Space Parking from Southern Portion of Lot to North Area as Shown

0.25 mons Fri 7/18/25 Mon 7/28/25

29 Perform Remaining Removals from Southern Portion

0.5 mons Fri 7/18/25 Mon 8/4/25

30 Construct Sanitary Sewer 0.5 mons Mon 8/4/25 Tue 8/19/25

31 Construct Storm Sewer Including Underground Detention System

0.75 mons Mon 8/4/25 Wed 8/27/25

32 Install Traffic Control and Connect Storm and Sanitary Sewers Into 120” Combined Sewer in Weiss Road

0.25 mons Wed 8/27/25 Wed 9/3/25

33 Phase 5 - Northern Portion Utilities 0.75 mons Wed 9/3/25 Fri 9/26/25

34 Move 80 Temporary Parking Stalls Back to Southern Portion of Lot as Shown

0.25 mons Wed 9/3/25 Thu 9/11/25

35 Install / Complete Utilities in Northern Portion of Site

0.5 mons Thu 9/11/25 Fri 9/26/25

36 Phase 6 - Pavement Preparation 5.75 mons Fri 9/26/25 Fri 3/20/26

37 Construct 24’ Wide North Access to Temporary Parking And 6’ Wide Limestone Path

0.25 mons Fri 9/26/25 Fri 10/3/25

38 Move 80 Space Parking from Southern Portion of Lot to North Area as Shown

0.25 mons Fri 9/26/25 Fri 10/3/25

39 SEASONAL DELAY (ESTIMATED) -

ASPHALT PLANTS & WEATHER

4.5 mons Fri 10/3/25 Wed 2/18/26

40 Perform Fine Grading for Pavement Area 0.25 mons Wed 2/18/26 Thu 2/26/26

41 Place Curb and Gutter 0.25 mons Thu 2/26/26 Thu 3/5/26

42 Place Sidewalk 0.25 mons Thu 3/5/26 Fri 3/13/26

0.25 mons

0.25 mons

0.25 mons

0.25 mons

0.25 mons

1.5 mons Phase 4 - Sanitary and Storm Sewers in South Portion

0.25 mons

0.5 mons

0.5 mons

0.75 mons

0.25 mons

0.75 mons Phase 5 - Northern Portion Utilities

0.25 mons

0.5 mons

5.75 mons Phase 6 - Pavement Preparation

0.25 mons

0.25 mons

4.5 mons

0.25 mons

0.25 mons

0.25 mons

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

43 Place Gravel Base 0.25 mons Fri 3/13/26 Fri 3/20/26

44 Phase 7 - South Paving 1.25 mons Fri 3/20/26 Tue 4/28/26

45 Install Utilities on East Side of City Lot 0.25 mons Fri 3/20/26 Mon 3/30/26

46 Mill Remaining Portion of Existing City Lot Asphalt

0.25 mons Mon 3/30/26 Mon 4/6/26

47 Place Remaining Curb and Gutter and Sidewalk

0.5 mons Mon 3/30/26 Mon 4/13/26

48 Pave Shaded Areas 0.25 mons Mon 4/13/26 Tue 4/21/26

49 Install Landscaping, Signage and Lighting 0.5 mons Mon 4/13/26 Tue 4/28/26

50 Phase 8 - North Paving and Restoration 1.5 mons Tue 4/28/26 Fri 6/12/26

51 Fine Grade North Lot 0.25 mons Tue 4/28/26 Wed 5/6/26

52 Place Curb and Gutter 0.25 mons Tue 4/28/26 Wed 5/6/26

53 Place Sidewalk 0.25 mons Tue 4/28/26 Wed 5/6/26

54 Place Aggregate Base 0.25 mons Wed 5/6/26 Wed 5/13/26

55 Pave North Lot 0.25 mons Wed 5/6/26 Wed 5/13/26

56 Stripe North Lot, Install Landscaping, Signage, Lighting and Permanent Perimeter Fencing

0.5 mons Wed 5/13/26 Thu 5/28/26

57 Turf Establishment 1 mon Wed 5/13/26 Fri 6/12/26

58 Project Cleanup 0.25 mons Thu 5/28/26 Fri 6/5/26

59 Turnover 1 mon Fri 6/5/26 Mon 7/6/26

60 Punchout 0.5 mons Fri 6/5/26 Mon 6/22/26

61 Commissioning 1 mon Fri 6/5/26 Mon 7/6/26

62 Inspections 0.5 mons Mon 6/22/26 Mon 7/6/26

63 Turnover 0 mons Mon 7/6/26 Mon 7/6/26

0.25 mons

1.25 mons Phase 7 - South Paving

0.25 mons

0.25 mons

0.5 mons

0.25 mons

0.5 mons

1.5 mons Phase 8 - North Paving and Restoration

0.25 mons

0.25 mons

0.25 mons

0.25 mons

0.25 mons

0.5 mons

1 mon

0.25 mons

1 mon Turnover

0.5 mons

1 mon

0.5 mons

0 mons

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep