This is Amendment 0006 to solicitation 36C77624R0154 for the Expansion of Medical Center Site project at the VA Medical Center in Saginaw, MI. The amendment provides responses to 61 questions received from potential offerors regarding technical specifications, construction requirements, and proposal submission details.
Key clarifications include: reducing the minimum project experience requirement from $5M to $2M for Factor 1; confirming the proposal due date remains January 31, 2025 at 1pm ET; specifying that CAD files will only be provided to the winning vendor; clarifying storm sewer specifications and structure details; confirming backflow preventer requirements for electrical manholes; providing details on railroad spur removal and ballast excavation; and addressing questions about temporary construction fencing, security fence installations, and barrier gates. The amendment also includes four attachments with updated specifications for video surveillance (282300), electronic personal protection systems (282600), site utility structures, and VA signage design manual drawings. The project scope involves site preparation, utilities, paving, security systems and other civil construction work under NAICS code 237990.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 18
0006 01-15-2025
655-401
36C776
Department of Veterans Affairs
Program Contracting Activity Central
6100 Oak Tree Blvd, Suite 490
Independence OH 44131
36C776
Department of Veterans Affairs
Program Contracting Activity Central
6100 Oak Tree Blvd, Suite 490
Independence OH 44131
To all Offerors/Bidders
36C77624R0154
11-26-2024
X
X X
X one
The purpose of this sixth solicitation amendment is to provide responses to RFI questions.
Please see responses below along with the supporting document attachments.
All other terms and conditions remain unchanged.
Proposal due date remains unchanged.
Jennifer Braaten
Contracting Officer.
RFP: 36C77624R0154
Request for Information
Project #: 655-401– Expansion of Medical Center, Minor Construction
Saginaw, MI
RFP: 36C77624R0154
1/13/2025
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
1. Please consider an extension to the bid due date
(01/03/2025) due to the holiday season and difficulty in putting together and receiving accurate quotes while people take time off of work.
Solicitation due date extended to January 31, 2025, at
1pm ET in accordance with Amendment 04.
2. Please reconsider $5M minimum requirement on
Factor 1.
Minimum requirement has been reviewed and revised to $2M minimum for Factor 1 in accordance with
Amendment 0005.
3. kindly request an extension of the bid due date to
January 13, 2025.
Solicitation due date extended to January 31, 2025, at
1pm ET in accordance with Amendment 05.
4. Have the railroads been decommissioned? is there more information about ties on railroad? Also, is there any specific site to recycle those railroad metals?
Yes, the railroad spurs near the east property line have been decommissioned, but have no information related to the ties. The railroad metals are to become the contractor’s property to dispose of according to all local and federal regulations. Check with local recyclers on acceptance of rails. The Government will provide proof of ownership.
5. Can the phasing plan be done concurrently because when we do rough grading, we are going to do it all at once?
The phasing may be adjusted with coordination and approval of the VA project representatives. All temporary parking and access paths must be maintained.
6. Will topsoil or spoils be stockpiled on site? Topsoil and spoils that will be reused may be stockpiled on site. Excess topsoil and materials not scheduled for reuse shall be removed from the site.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
7. CD102 shows clearing and grubbing for the vegetation area. Does it mean all trees along the railroad and vegetations need to be removed?
All trees within the area scheduled for clearing and grubbing according to sheet CD102 shall be removed.
Any vegetation within the railroad property to the north shall remain. Contractor shall stay out of railroad property during all phases.
8. I cannot find the drawings for Low Voltage cabling/
Fiber for cameras if possible could you let me know where it may be?
Check the SAM posting for Attachment 02-01 and 02-02.
Sheet TY601 shows all the low voltage for this project.
TS100 and TS101 show routing information. Sheet
CU118 shows all the signal structures that the low voltage cabling passes through as well as listing the type and quantity of cables. Attachment 11 on the Sam.gov site is also an excel file of this information. Specification
Sections 27 and 28 provide further requirements.
9. Ref drawing CJ108 detail #71- How many linear feet of handrails is required and where will it be located based on the site geometric plans?
See sheet CS101. There is a note near the center of the page that states, “REMOVE EXISTING HANDRAIL. FILL
HOLES WITH NON-SHRINK GROUT. REPLACE WITH NEW
HANDRAIL. SEE DETAIL #71” There is approximately 8-feet on each side of the sidewalk to be replaced (16-feet total).
10. Ref drawings CS104 & CS105- Will a sign schedule be provided? Will details be provided for each type of sign such as sign type EN-10.01, EN10.09, EN10.03, etc.…?
A sign schedule will not be provided. Signs reference US
Department of Veteran Affairs Exterior Signs document.
VA Signage Design Manual. Section 3.5 EXTERIOR
SIGNAGE DRAWINGS included with this amendment for convenience. Reference is also given to MUTCD sign standards in brackets. MUTCD has standard sign sizes, refer to single lane sign sizes.
https://www.cfm.va.gov/til/dManual/dmSignage.pdf
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
11. Ref drawing CS104- What sign bases are applicable to the various sign types?
If the sign is located within the pavement, the Portable
Sign Installation (Det #71) shall be used. If the sign is located within a grass or landscape area, the Sign
Installation (Det #40) shall be used.
12. During discussions with my IT staff, I realized the furthest camera is over 2000ft away point to point and multimode fiber is not capable of those distances.
The Bosch VG4-SFPSCKT fiber to copper media converters that are being used for this project support cabling up to 1.2 miles on multi-mode fiber. This should cover the all cabling for this project.
13. Who’s responsible for Temporary construction fence?
Temporary construction fence is the responsibility of the general contractor to erect, maintain, and move as needed.
14. Existing plan shows wetlands flagged by others. Are those areas need to be protected?
Existing wetlands on site were determined to be non-jurisdictional.
15. An excavation/site utilities subcontractor has asked us to request CAD files for this project from the engineer. Please advise.
The VA will only provide the CAD Files to the winning vendor.
16. We have an RFI regarding some discrepancies we are seeing with the structure sizes and inverts within the drawings. Looking at the inverts, rim, and structure sizes between sheet CU116 and the profile views for storm and sanitary utilities, they are showing differing values. Please advise on which sheet is correct.
See RFI response #56 for clarification.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
17. The following cameras in the SOLICITATION NO.
36C77624R0154 Expand Medical Center Site 655-
401 has been replaced with current models that meet Federally funded government projects. I have attached full data sheets for the current models as well. Based on the input from the Manufacturer for use and looks, it is recommended that you specify the most updated equipment with the latest software and firmware that will allow the best audio and video quality. I’ve attached the recommended
Commend emergency call box system
VA has updated the following Specifications.
28 23 00 Video Surveillance, Sections 2.6 G, H, I, & J.
28 26 00 Electronic Personal Protection Systems, Section 2.3 C & 3.1F
18. Ref drawing CU110 & CU116- Manhole 355 is shown to have a Rim elevation of 600.50, on drawing
CU110 the Rim is shown as 600.72. Drawing CU110 notes a 12” RCP with an invert of 595.4. Drawing
CU116 does not list 12” RCP and lists 18” and 24”.
There are other manholes that also show indifferences from profile drawing to the structure list drawing. Which is correct?
Manhole 355 shall be constructed as follows.
Rim = 600.50
EJIW 1040 Type M1 Flat Grate
Inv=594.75 SW 24” RCP
Inv=595.40 E 12” RCP
Inv=594.85 N 18” RCP
Inv=598.72 N/S 4” Perforated Pipe
Bottom=593.05
See RFI response #55 for additional clarification.
19. Ref detail #65 drawing CJ106- Neenah Foundry bollard 8401 is no longer available since Neenah no longer manufactures bollards. Will model R-7584 from Reliance Foundry be acceptable?
Yes, Reliance Foundry R-7584 is an acceptable bollard to replace Neenah bollard 8401
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
20. On plan sheet CS103 it shows a path (possibly heavy duty) to the west of the “Concrete pad for motorcycle parking” but that area is not shown as being included on plan sheet
CS102. Please clarify.
This is part of phase 2 water main and electric utility work per GC101. The area west of the proposed motorcycle parking is standard duty asphalt pavement proposed to be replaced in kind for the installation of new medium voltage conduit feed as shown on sheet
CU102. See sheet CD102 for removal notes associated with this work.
21. HMA Specs - Penetration Grade 50/60 roughly translates to PG 64-16 according to my research. I also, found that penetration grades were developed over 100 years ago. PG 64-16 is NOT available in
Michigan. Options for common performance grade binders in Michigan are PG 58-22, PG 58-28, PG 64-
22 or PG 64-28. Could we please have the modern
PG number that the engineer is seeking?
Use PG64-28
22. Does the 72x48 building for demolition contain a slab on grade that will need to be removed as well?
Yes, concrete slab on grade will need to be removed.
23. The asphalt layout and paths are difference on the landscaping plan vs the north paving and restoration plan and also there is conflicting site geometric plans. Can you please clarify what is the correct layout for this project?
Geometric changes revised the east-west pedestrian crossing to be on the south side of the intersection. See sheet CS102.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
24. MH 345 in the Structures excel file states that it is a
72” Pre Cast Manhole. The drawing detail states MH
345 is a 96” Hydro Dynamic Separator. Are we installing both a 72” MH and the 96” separator or just one. Please clarify.
CU107 and CU116 shows manhole 345 is a 96” Hydro
Dynamic Separator. Only the 96” manhole is to be constructed at MH 345.
The excel spreadsheet was provided to help Electrical and Signal Trades locate the structures required for their cabling as they are located on CIVIL sheets and seems this may have caused some confusion. The only relevant tabs on Attachment 11 are labeled CU116 (for CIVIL structures), CU117 (for Electrical Structures), & CU118
(for Signal Structures) which are identical to those same
Drawings sheets. The other tabs on the excel spreadsheet are to be completed by the Contractor as
As-Builts. A revised sheet has been attached, however no data has been revised to correlate with the RFI changes noted in this amendment.
See RFI response #56 for additional clarification.
25. Is there a backflow preventor needed for the electrical manholes storm piping?
WBK recommends an inline 4” PVC vertical backflow preventer accessible from the electric manhole
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
26. Storm sewer profile does not identify the length of pipes between storm structures. Would you please ask engineers to revise their drawings. What I assume is that it’ll pipe length from center to center of structures. They have the same problem with sanitary and water main profile.
The drawings are scaled, and pipe lengths shall be measured center of structure to center of structure.
27. Looking at storm sewer profile, and there are two storm structures that have discrepancies regarding structures sizes and pipe inverts. Drawing CU107 :
MH-345, is 8’ Diameter structure and there is no information of 18” RCP that goes to MH 351.
Manhole 345 shall be constructed as follows.
96” Diameter Hydro Dynamic Separator
Rim = 600.41
EJIW Type A Solid Cover
Inv=593.02 N 36” RCP
Inv=592.92 S 36” RCP
Inv=595.46 E 18” RCP
Bottom=591.99
Refer to sheet CU109 for more information related to the storm work between MH345 and MH351.
See RFI response #56 for additional clarification.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
28. Will a geomembrane liner be required for retention basin as called out in sheet P2 of the CONTECH drawings?
Yes, the geomembrane line should be as shown on sheet
CJ107 on CONTECH sheet P2
29. Can CAD Files be made available for bidding purposes?
The VA will only provide the CAD Files to the winning vendor.
30. What is the existing material of the 120” combined sewer tie in?
Reinforced Concrete Pipe
31. Are there u-trap cleanouts intended to be installed with the proposed u-trap for the sanitary sewer?
The cleanouts shown on sheet CJ102, detail #22, are not required
32. Please confirm that the existing electrical is the only utility within the existing building to be demolished.
Per drawing CD101, the only utility surveyed going into the building to be removed is underground electrical. No other utilities appear to be fed to this building.
33. Please provide a detail on the connection between electrical structures and storm drainage system.
See Sheet E502 detail #1 Power Manhole Details
34. In the pre-bid it was mentioned that the relocation of Conex boxes and trailers would be excluded from this project. Please confirm that the contractor will not have to include moving trailers and Conex boxes.
No trailers or Conex boxes are required to be relocated as part of this project.
35. See detail 28/CJ103. Does the perforated pipe need to have geotextile around the pipe or around the trench stone?
Yes, a geotextile liner shall be installed around the perimeter of the stone trench
36. See detail 27/CJ103. Does the sidewalk require subbase? If so, what material and how thick?
Yes, 4 inches CIP of 21AA aggregate base course shall be installed under all proposed sidewalks. See combination curb and sidewalk detail #34 on sheet CJ103.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
37. See AD101. What are the depth and details of the existing building foundation to be demolished?
No existing drawing information is available. It should be assumed that there is an existing foundation below the standing pole barn structure of the building and that the slab on grade could be 5”, unless thickened further below building structure.
38. Can you clarify what class of Ductile Iron you are looking for, for watermain piping?
Thickness Class 52
39. Can you please give some more detail/information on the Sump Pump Removal shown on CD102?
The sump pump was a temporary drainage solution to alleviate flooding near the property line in the area. A temporary power line and pedestal was installed to the area to power a small pump (pump size unknown, but likely ½ HP). The pump was placed in a shallow sump and the discharge pipe ran stormwater to the north toward the wetland area. Once the new drainage ditch and system is in place, the contractor shall remove this temporary power line, pump, and discharge pipe. This is a 120V 20-amp circuit ran with type UF cable back to the electrical panels that feed the construction trailers.
40. Ref drawing CU102 and Specification 33 51 00- A new natural gas line is shown from building 17 which runs north and east to service future buildings. When contacting Consumers Energy at number shown on drawing VA101, I am told they need the total connected load in MCFH for each future building that will be constructed, the delivery pressure, and the estimated annual usage in
MCF/year OR estimated operation schedule (for example 24 hours a day for 365 days a week or 16 hour days on weekdays) to be able to provide a cost estimate. Will this information be forthcoming?
This is privately owned, and consumers will not be involved in the installation. Calculations for sizes and pressures have already been completed for future connections.
Final pressure to the future buildings would be 2psi and once constructed, dropped to 7-14 in wc at the building entry.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
41. Is Camera 29 a License plate Camera. Yes, Camera 29 is a Fixed License Plate reader. Keynote
2 is applies to this camera.
42. In accordance with Solicitation the project type is identified as a 237990 NAICS Code Heavy Civil
Construction. This is the first Solicitation we have encountered being issued under this NAICS code.
The project involves multiple trades and required coordination requiring the Prime Contractor to perform the “primary and vital” requirements of
NAICS code for General Contracting which is
“management, supervision, and oversight of the project, including coordinating the work of various subcontractors, but not actual construction performed”. We have identified subtrades involved to include Earthwork, asphalt, concrete, site utilities, electrical, etc.
We respectfully request that the NAICS Code that this project falls under be revised to 236220 for
General Contracting. This will result in more competitive bids by qualified General Contractors.
We believe that the requirements of the Technical
Section requiring past performance of (2) awards under the 237990 exceeding $3.5mm will exclude the majority if not all of the SDVOSBs currently interested in this Solicitation.
Careful consideration was given to choosing the most appropriate NAICS of this acquisition as it relates directly to the project specifications and details found in
RFP package.
The code 237990 – other heavy and civil engineering construction was chosen because it contains the highest relevance and dollar values associated to work identified in the cost estimate, specs, and drawings; specifically earthwork, utilities, heavy machine operators, and low voltage supply and install. Only a small portion of building construction is present, which is best represented by 236220 – commercial and institutional building construction. Although most VHA projects are building construction, this project is mostly civil-based.
There may be more SDVOSB firms with 236220, but
SDVOSB competition also exists under 237990. The contracting teams sustains its decision to solicit and award with NAICS 237990 to best support the project while also meeting Veteran’s First contracting laws.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
43. We have multiple ground up civil site projects in the medical and commercial sector. Water and Sewer
Line and Related Structures Construction and Other
Heavy and Civil Engineering Construction. This work is for public and private customers outside of the
Government NAICs coded work. All projects meet the $3.5M in value requirement. Please confirm this is acceptable for Factor 1, Project Experience requirement.
A. Technical Proposal Requirements: The proposal must address the following submission requirements for Factor 1 Project Experience
(Technical)
1. Factor 1, Project Experience (Technical):
Offerors shall provide a minimum of two and no more than five prior projects that meet the minimum requirements defined below. Project experience shall be within the last seven (7) years from the date of RFP posting.
Include all the following:
• Provide examples of previous performance on at least two (2) construction projects under NAICS
237* that are at least $3.5M in value. (*Any project with NAICS 237110 – 237990 is acceptable)
Please see Amendment 0005 which revises the original
Factor 1, Project Experience to:
A. Technical Proposal Requirements: The proposal must address the following submission requirements for
Factor 1 Project Experience (Technical)
1. Factor 1, Project Experience (Technical):
Offerors shall provide a minimum of two and no more than five prior projects that meet the minimum requirements defined below. Project experience shall be within the last seven (7) years from the date of RFP posting.
Include all the following:
• Provide examples of previous performance on at least two (2) construction projects performing site preparation and site improvements that are at least $2M in value, each. (*examples of site preparation and site improvements may include: clearing, grubbing, tree removal, earthwork, cut and fill, parking lots, curbs and gutters, bases, compaction, pavement, or other industry standard aspects of site preparation and site improvements.)
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
44. Can the past performance required under 2.8C of the solicitation be projects performed by the prime contractor’s subcontractor or do the projects have to exclusively be self-performed or managed by the prime contractor on a previous job?
The offeror needs to demonstrate successful prime capability. This can be self-performed or subcontractor management of the following attributes:
Offerors shall provide a minimum of two and no more than five prior projects that meet the minimum requirements defined below. Project experience shall be within the last seven (7) years from the date of RFP posting.
Include all of the following:
- Provide examples of previous performance on at least two (2) construction projects performing site preparation and site improvements that are at least $2M in value, each. (*examples of site preparation and site improvements may include: clearing, grubbing, tree removal, earthwork, cut and fill, parking lots, curbs and gutters, bases, compaction, pavement, or other industry standard aspects of site preparation and site improvements.)
- Provide an example of prior experience on at least one (1) construction project that executed specified phasing.
- Provide an example of prior experience on at least one (1) construction project that required traffic control for an active medical facility.
- Provide an example of prior experience on at least one (1) construction project that required civil infrastructure work which included relocation of existing utilities.
Provide an example of Project Management software used on a project, e.g. Submittals, meeting minutes, correspondence, etc.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
45. Is a CPARS required for the projects provided in the technical proposal?
CPARS is not required to be provided in the technical proposal as past performance is not included in the LPTA evaluation factors. However, contractors are required to be registered in the CPARS database.
46. Is the construction management software indicated under 01 00 00 – 1.34 of the specifications a licensee provided by the VAMC or is the prime contractor responsible for the cost?
The Prime is responsible for providing this service then providing access to the AE and the VA and its team.
47. Can the quality control manager or site safety health officer indicated under 01 35 26 – 1.9 be performed by one individual at each site or are these roles to be separate? Are triple hatting efforts of superintendent, quality control manager, and SSHO acceptable on this project?
It is acceptable for the Site Superintendent to perform multiple duties such as SSHO, however the QCM must be a separate qualified individual.
48. Can the contractor’s consultant indicated under 01
32 16.15 – 1.3A be a scheduling assistant in house of the prime contractor or does this individual need to be a 3rd party consultant separate from the prime contractor?
01 32 16.15 Section 1.2 C The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
49. CD 101 shows underground electric needs to be removed, can you please tell me if it is direct buried or duct bank? What’s the depth of removal?
The underground electric shown for removal on CD 101 appears to feed the outlet which is powering the sump pump discussed in response #39. No records were available as this was a temporary fix to flooding issues.
Power for the pole barn is 1” Pvc conduit, 24” deep, not in duct bank. Power for the sump pump is direct burial type UF cable 24” deep. Power to the transformer (T-20) is connected via the existing duct bank from EMH-185 to
EHH-305 then to the transformer disconnect in 3” pvc conduit not in duct bank. The Raceways to provide power for construction trailers are in pvc conduit 24” deep not in duct bank.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
50. CD 101 and CD 102 show asphalt removal, can you please provide the thickness of asphalt removal on
Weiss St and existing site.?
Soil boring logs indicate 2 to 4 inches, more specific information is not available.
51. CD 101 shows concrete slab at warehouse, and project site, please provide slab thickness and foundation depth at warehouse and those slabs from previous structures.
No existing drawing information is available. It should be assumed that there is an existing foundation below the standing pole barn structure of the building and that the slab on grade could be 5”, unless thickened further below building structure.
52. GC 102 (Phase 3) shows 6’ & 24’ Wide Road, can you please provide thickness of those roads, and can
21AA limestone be used as temporary stone at 24’
Wide Road?
All temporary drives and parking areas for parking lot staging and VA access shall be a minimum of 6 inches thick. All temporary walking paths to be a minimum of 4 inches thick. 21AA limestone would meet the material expectation.
53. #37 / CJ 103 shows excavated materials during underground utilities excavations can be used as backfill where pipes are laid under green belt areas.
Can you please verify if materials are suitable for backfilling and not contaminated?
Details 36, 37, and 38 show backfill requirements.
Contractors shall expect to bring in MDOT Class III materials for backfilling under pavements as native soils will not meet requirements for Class III. Existing soils may only be reused as backfill outside of pavement if they are not wet and unstable.
54. When we strip topsoil, can we stockpile stripped topsoil on site?
7. CD 101 shows a detail for railroad spur removal, can you please provide how deep we need to excavate the ballast?
Yes, stripped topsoil may be stockpiled on site as long as stockpiles are not in areas of ongoing work, temporary parking, or staging and stockpiles are maintained from soil erosion.
The ballast depth is not known but shall be completely removed.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
55. Sheet AD101 Note 3 directs the contractor to remove and salvage all existing equipment and furniture. What type and approximate quantity of equipment and furniture should be anticipated?
This building contains miscellaneous construction materials and equipment. Contractor to plan on providing two 40 yard dumpsters and dispose of the items doesn’t not want to salvage.
56. Summary from design team regarding stormwater:
RFI questions 18, 24, and 27 related to clarifications to the proposed storm sewer system. Revised plans will be sent prior to construction to the awarded contractor, but we wanted to clarify a few specific items for bid purposes. If there are discrepancies between plan and profile sheets vs. CU 116, the plan and profile sheets shall govern.
See RFI response 18 for MH 355, response 24 and 27 for MH 345.
• INL-339 W invert shall be 12” RCP
• MH-340 E invert shall be 8” PVC
• INL-354 shall have a 4” S invert to connect to nearby electric manhole. There will also be two N inverts. One for 8” PVC from INL-362 and one 6” perforated higher for the ditch underdrain
• INL-362 shall have 8” PVC inverts for E, W, and S inverts
• INL-366 Rim elevation on CU-116 is incorrect, refer to plan and profile and grading plan.
• MH-347 shall be a 60” DIA MH
• INL-350 N and S inverts shall be 6” perforated pipe
• MH-356 is a MH, not an INL, and shall be 48”
DIA
• All drainage lines from electric manholes shall be 4” if only one line is connected. Drainage lines shall have a 8”x4” reducer and 8”x4” wye when two or more drainage lines are connected.
All storm manholes that are at low points in pavement shall be installed with 4” drainage tiles.
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
57. Verify that the only barrier gate is the 18x2 at the south main entrance.
Also, if the material is galvanized or black vinyl coated?
See sheet CJ106. Details #66 & #67 apply to the South main entrance only.
2” SS40 Galvanized Framework powder coated black with reflective tape on all horizontal sections.
58. The 2x6 timber at the bottom of the security fence where stone is not desired on opposite side, where can I find these locations?
The north fence line and east/west fence line adjacent to the construction trailers will require the 2x6 timber at the bottom.
59. Do you know how many ditch crossings there are along the security fence line?
There are two ditch crossings on the north fence line.
60. Will I be able to install the fence before the fiberoptic lines are buried next to the fence lines?
Coordinate with the low voltage contractor, however the fence is primarily on the property line so there shouldn’t be any issues.
61. What section of the fence are these temporary fence arrows pointing at? Looks like both are pointing at the 7’ security fence.
The temporary fence is between the arrows, approximately 274 ft.
See attached document: Amendment 0006 - ATT 1 - 655-401 Expand Site - Site Utility Structures 1-8-
2025.
See attached document: Amendment 0006 - ATT 2 - 282300 Video Surveillance_Edited 1-8-2025 per
RFI.
See attached document: Amendment 0006 - ATT 3 - 282600 Electronic Personal Protection System_
Edited 12-30-2024 per RFI.
See attached document: Amendment 0006 - ATT 4 - VA Signage DM Parking Lot Drawings Pages 538-
675.
End of Document