Attachment 06 - Spec 01 31 00.01 Project Management and Coordination.pdf
PDF 84 KB Posted
- Attached to
- 586-21-700 EHRM Infrastructure Upgrades - Jackson, MS Federal contract opportunity
- Solicitation number
- 36C77625B0021
About this file
This document is a Project Management and Coordination specification section that details requirements for digital project management procedures for a construction project. The specification mandates the use of a web-based project management software package (such as Procore or Oracle Primavera Submittal Exchange) with specific required features, including project data compilation, access control, document workflow planning, communication tracking, and mobile device compatibility. Key requirements include providing user licenses for the Owner, Architect, and consultants, delivering eight hours of software training, and creating a digital archive in a readable format upon project completion. The software must support tracking of RFIs, submittals, change orders, payment applications, meeting minutes, document management, and construction progress photographs, with security features to prevent unauthorized modifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C77625B0021 0004.pdf | ||
| Amendment 0003 - Tech Questions Tracker.pdf | ||
| Amendment 0003 - General Requirements Addendum.pdf | ||
| Amendment 0003 - Geo Technical Report 2.pdf | ||
| Attachment 07 - Sole Source JA 586-21-700.pdf | ||
| 36C77625B0021 0003.pdf | ||
| Amendment 0003 - Asbestos and Hazardous Materials Report.pdf | ||
| Amendment 0003 - Geo Technical Report 1.pdf | ||
| Attachment 01 - Site Visit Sign-in.pdf | ||
| Attachment 01 - Wage Rates - Hinds Co.pdf | ||
| 36C77625B0021 0001.pdf | ||
| 36C77625B0021 0002.pdf | ||
| Attachment 01 - Statement of Work.pdf | ||
| Attachment 05- Limitations on Subcontracting.pdf | ||
| Attachment 03 - Drawings.pdf | ||
| 36C77625B0021.pdf | ||
| Attachment 04 - Wage Determination Hinds Co.pdf | ||
| Attachment 02 - Specifications.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number Project Name Project Location
PROJECT MANAGEMENT AND COORDINATION
05-01-24
01 31 00.01 - 1
SECTION 01 31 00.01
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provision for coordinating construction operations on Project, including, but not limited to, the following:
1. Web-based Project management software package.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
1.3 DEFINITIONS
A. BIM: Building Information Modeling.
B. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Web-Based Project Management Software Package: Provide, administer, and use web-based
Project management software package for purposes of hosting and managing Project communication and documentation until Final Completion.
1. Basis of Specification: Procore, Oracle Primavera Submittal Exchange or other equivalent web-based project management software.
2. Web-based Project management software includes, at a minimum, the following features:
a. Compilation of Project data, including Contractor, subcontractors, Architect, Architect's consultants, Owner, and other entities involved in Project. Include names of individuals and contact information.
b. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents.
c. Document workflow planning, allowing customization of workflow between project entities.
d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, Minor
Changes in the Work, Construction Change Directives, and Change Orders.
e. Track status of each Project communication in real time, and log time and date when responses are provided.
Project Number Project Name Project Location
PROJECT MANAGEMENT AND COORDINATION
05-01-24
01 31 00.01 - 2
f. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.
g. Processing and tracking of payment applications.
h. Processing and tracking of contract modifications.
i. Creating and distributing meeting minutes.
j. Document management for Drawings, Specifications, and coordination drawings, including revision control.
k. Management of construction progress photographs.
l. Mobile device compatibility, including smartphones and tablets.
3. Provide Project management software user licenses for use of Owner, Architect, and
Architect's consultants. Provide eight hours of software training for web-based Project software users.
4. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Architect. Provide data in locked format to prevent further changes.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
- - - END - - -