Attachment 02 - Specifications.pdf

PDF 7 MB Posted

Attached to
586-21-700 EHRM Infrastructure Upgrades - Jackson, MS Federal contract opportunity
Solicitation number
36C77625B0021
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a detailed specification for traditional asbestos abatement at the G.V. (Sonny) Montgomery VA Medical Center in Jackson, Mississippi. The project involves removing approximately 32 linear feet of pipe insulation, 13 pipe fittings, 52 square feet of foil-backed duct insulation, 300 square feet of plaster ceiling/wall, and 930 square feet of miscellaneous materials (such as flooring mastic) from multiple rooms in Buildings 1 and 5.

The specification provides comprehensive requirements for asbestos removal, including detailed procedures for site preparation, worker protection, containment, negative air pressure systems, wet removal techniques, decontamination, and disposal. Key requirements include establishing regulated work areas, using specialized personal protective equipment, implementing strict decontamination protocols, maintaining negative air pressure, wet removal methods, and conducting thorough visual and air clearance testing. The contractor must comply with OSHA, EPA, and state regulations, and will be responsible for all aspects of safe asbestos removal, including transportation and disposal at an approved landfill. The project is part of the VA's EHRM (Enterprise-wide Health Resilience Modernization) Infrastructure Upgrades, with the solicitation number 36C77625B0021.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Veterans Affairs

G.V.(SONNY) MONTGOMERY

VA MEDICAL CENTER

1500 EAST WOODROW

WILSON AVE.

JACKSON MS 39216

EHRM INFRASTRUCTURE

UPGRADES

ISSUED FOR FINAL SUBMISSION

1800 Diagonal Road, Suite 600

Alexandria, VA 22314 Tel: (703) 232-1491 Fax: (866) 844-4373 www.planate.com

VA Project No. 586-21-700

CONFORMED SET 2025.03.21

PROJECT

SPECIFICATION

MANUAL

VA

CIVIL ARCHITECTURAL

STRUCTURAL MECHANICAL

ELECTRICAL FIRE PROTECTION

ENVIRONMENTAL

TELECOMMUNICATIONS PHYSICAL SECURITY

ISSUED FOR

CONSTRUCTION (FINAL)

S T

AT E I S

S I P P I

1 4 1 2 2N o.

OF M I S

ALAN WATT

S

ENG I NEE

R

R

EG

IS

TERED PROFESS

IONA

L

3/21/2025

STRUCTURAL

Digitally signed by Richard R Creavalle Date: 2025.03.20 17:52:47-04'00'

CONSTRUCTION.

03/20/2024

2025.05.19 rev*

* Revisions to pages 209, 1037, & 1056 (of 1181) addressing "SPEC WRITER NOTES".

http://www.planate.com/

VA Project No.: 586-21-700 03-21-25

G.V.(SONNY)MONTGOMERY VA MEDICAL CENTER, JACKSON MS

EHRM INFRASTRUCTURE UPGRADES

Issued for Construction (Final)

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 03-20 01 33 23 Shop Drawings, Product Data, and Samples 02-23 01 35 26 Safety Requirements 10-22 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17 02 82 11 Traditional Asbestos Abatement 01-21 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21 02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 31 13 Access Doors and Frames 04-22

00 01 10-2

08 71 00 Door Hardware 05-22 08 90 00 Louvers and Vents 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16.13 Static dissipative resilient tile flooring 01-21 09 65 16 Resilient Sheet Flooring 06-22 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21 10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 13 – SPECIAL CONSTRUCTION

13 05 41 Seismic restraint requirements for non-structural components 01-21

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 03-23

23 07 11 HVAC and Boiler Plant Insulation 02-20 23 23 00 Refrigerant Piping 03-23 23 81 23 Computer-Room Air-Conditioners 03-23

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 08 00 Commissioning of Electrical Systems 11-16 26 09 23 Lighting Controls 11-22 26 22 00 Low-Voltage Transformers 11-22 26 24 16 Panelboards 11-22 26 27 26 Wiring Devices 11-22 23 33 53 Static Uninterrupted Power Supply 11-22 26 43 13 Surge Protective Devices 11-22 26 51 00 Interior Lighting 11-22

00 01 10-3

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements For Communications Installations 11-22 27 05 26 Grounding and Bonding for Communications Systems 12-22 27 05 33 Conduits and Backboxes for Communications Systems 12-22 27 05 36 Cable Trays for Communications Systems 12-22 27 05 53 Identification for Communications Systems 12-22 27 08 00 Commissioning of communications systems 11-16 27 10 00 Structured Cabling 12-22 27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 12-22 27 11 19 Communications Termination Blocks and Patch Panels 12-22 27 11 26 Communications Rack Mounted Power Protection and Power

Strips 12-22

27 13 13 Communications Copper Backbone Cabling 12-22 27 13 13.13 Communications Copper Cable Splicing and Terminations 12-22 27 13 23 Communications Optical Fiber Backbone Cabling 12-22 27 13 23.13 Communications Optical Fiber Splicing and Terminations 12-22 27 15 13 Communications Copper Horizontal Cabling 12-22 27 16 19 Communications Patch Cords, Station Cords, and Cross-

Connect Wire 12-22

27 78 00 Closeout Submittals for Communications 03-23

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

10-11

28 08 00 Commissioning of for Electronic Safety and Security Systems

11-16

28 13 00 Physical Access Control System 10-11 28 16 00 Intrusion Detection System 10-11 28 23 00 Video Surveillance 09-11

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 90 00 Planting 08-16

- - - END - - -

VA Project. No: 586-21-700 03-21-25

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

Issued For Construction (Final)

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of contract.

GENERAL INFORMATION

GI-001 COVER SHEET

GI-002A GENERAL INDEX SHEET - VOLUME 1

GI-002B GENERAL INDEX SHEET - VOLUME 2

GI-003 SYMBOLS, ABBREVIATIONS & NOTES

GI-004 GENERAL NOTES

GI-005 TYPICAL MOUNTING HEIGHTS AND DIMENSIONING CONVENTIONS

GI-006 UL ASSEMBLY DETAILS

GI-007 UL ASSEMBLY DETAILS

GI-008 UL ASSEMBLY DETAILS

AE302 TYPICAL DATA ROOM

AE500 WALL TYPES

AE501 WALL DETAILS

AE601 DOOR SCHEDULE & DETAILS

01-GC100 BUILDING 01 - BASEMENT FLOOR EXISTING OVERALL FLOOR PLAN

01-GC101 BUILDING 01 - 1ST FLOOR EXISTING OVERALL FLOOR PLAN

01-GC102 BUILDING 01 - 2ND FLOOR EXISTING OVERALL FLOOR PLAN

01-GC103 BUILDING 01 - 3RD FLOOR EXISTING OVERALL FLOOR PLAN

01-GC104 BUILDING 01 - 4TH FLOOR EXISTING OVERALL FLOOR PLAN

01-GC105 BUILDING 01 - BASEMENT FLOOR PLAN- ICRA

01-GC106 BUILDING 01 - 1ST FLOOR OVERALL FLOOR PLAN- ICRA

01-GC107 BUILDING 01 - 2ND FLOOR OVERALL FLOOR PLAN- ICRA

01-GC108 BUILDING 01 - 3RD FLOOR OVERALL FLOOR PLAN- ICRA

01-GC109 BUILDING 01 - 4TH FLOOR OVERALL FLOOR PLAN- ICRA

01-AE400a BUILDING 01 - BASEMENT FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE400b BUILDING 01 - BASEMENT FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE400c BUILDING 01 - BASEMENT FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE400d BUILDING 01 - BASEMENT FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE400e BUILDING 01 - BASEMENT FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE401a BUILDING 01 - 1ST FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE401b BUILDING 01 - 1ST FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE402a BUILDING 01 - 2ND FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE402b BUILDING 01 - 2ND FLOOR ENLARGED PLANS- DEMO AND NEW WORK 01-AE403a BUILDING 01 - 3RD FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE403b BUILDING 01 - 3RD FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE404a BUILDING 01 - 4TH FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE404b BUILDING 01 - 4TH FLOOR ENLARGED PLANS - DEMO AND NEW WORK 01-AE700a BUILDING 01- BASEMENT- EXISTING CEILING CONDITIONS 01-AE700b BUILDING 01- BASEMENT- REFLECTED CEILING PLANS 01-AE700c BUILDING 01- BASEMENT- REFLECTED CEILING PLANS

00 01 15 - 2

01-AE700d BUILDING 01- BASEMENT- REFLECTED CEILING PLANS 01-AE701a BUILDING 01-1ST FLOOR- EXISTING CEILING CONDITIONS 01-AE701b BUILDING 01- 1ST FLOOR- REFLECTED CEILING PLANS 01-AE701c BUILDING 01- 1ST FLOOR- REFLECTED CEILING PLANS 01-AE702a BUILDING 01- 2ND FLOOR- EXISTING CEILING CONDITIONS 01-AE702b BUILDING 01- 2ND FLOOR- REFLECTED CEILING PLANS 01-AE702c BUILDING 01- 2ND FLOOR- REFLECTED CEILING PLANS 01-AE703a BUILDING 01- 3RD FLOOR- EXISTING CEILING CONDITIONS 01-AE703b BUILDING 01- 3RD FLOOR- REFLECTED CEILING PLANS 01-AE703c BUILDING 01- 3RD FLOOR- REFLECTED CEILING PLANS 01-AE704a BUILDING 01- 4TH FLOOR- EXISTING CEILING CONDITIONS 01-AE704b BUILDING 01- 4TH FLOOR- REFLECTED CEILING PLANS 01-AE704c BUILDING 01- 4TH FLOOR- REFLECTED CEILING PLANS

03-GC100 BUILDING 03- FIRST FLOOR EXISTING OVERALL FLOOR PLAN

03-GC101 BUILDING 03- 1ST FLOOR OVERALL FLOOR PLAN - ICRA

03-AE400 BUILDING 03- 1ST FLOOR ENLARGED PLANS - DEMO AND NEW WORK

03-AE700 BUILDING 03- 1ST FLOOR- EXISTING CEILING CONDITIONS

03-AE701 BUILDING 03- 1ST FLOOR- ENLARGED RCP PLANS - DEMO AND NEW WORK

05-GC100 BUILDING 05 - SUB-BASMENT AND BASEMENT FLOOR

EXISTING OVERALL FLOOR PLAN

05-GC101 BUILDING 05 - 1ST AND 2ND FLOOR EXISTING OVERALL FLOOR PLAN

05-GC102 BUILDING 05 - 3RD AND 4TH FLOOR EXISTING OVERALL FLOOR PLAN

05-GC103 BUILDING 05 - SUB-BASEMENT AND BASEMENT FLOORS- ICRA PLANS

05-GC104 BUILDING 05 - 1ST AND 2ND FLOORS- ICRA PLANS

05-GC105 BUILDING 05 - 3RD AND 4TH FLOORS- ICRA PLANS

05-AE401 BUILDING 05 - BASEMENT FLOOR ENLARGED PLANS - DEMO AND NEW WORK

05-AE402 BUILDING 05 - 2ND FLOOR ENLARGED PLANS - DEMO AND NEW WORK

05-AE403 BUILDING 05 - 3RD FLOOR ENLARGED PLANS - DEMO AND NEW WORK

05-AE404 BUILDING 05 - 4TH FLOOR ENLARGED PLANS - DEMO AND NEW WORK

05-AE700

BUILDING 05 - BASEMENT AND SUB BASMENT EXISTING CEILING

CONDITIONS

05-AE701 BUILDING 05 - BASEMENT ENLARGED RCP PLANS - DEMO AND NEW WORK

05-AE702 BUILDING 05 - 1ST & 2ND FLOOR - EXISTING CEILING CONDITIONS

05-AE703 BUILDING 05 - 2ND FLOOR ENLARGED RCP PLANS - DEMO AND NEW WORK

05-AE704 BUILDING 05 - 3RD & 4TH FLOOR - EXISTING CEILING CONDITIONS

05-AE705 BUILDING 05 - 3RD FLOOR ENLARGED RCP PLANS - DEMO AND NEW WORK

05-AE706 BUILDING 05 - 4TH FLOOR ENLARGED RCP PLANS - DEMO AND NEW WORK

06-GC100 BUILDING 06 GROUNDS BUILDING - FIRST FLOOR PLAN

07-GC100 BUILDING 07 CLC - GROUND FLOOR EXISTING OVERALL FLOOR PLAN

07-GC101 BUILDING 07 CLC - 1ST FLOOR EXISTING OVERALL FLOOR PLAN

07-GC102 BUILDING 07 CLC - GROUND FLOOR - ICRA PLAN

07-GC103 BUILDING 07 CLC - 1ST FLOOR - ICRA PLAN

07-AE400 BUILDING 07- GROUND FLOOR ENLARGED PLANS - DEMO AND NEW WORK

00 01 15 - 3

07-AE401 BUILDING 07- 1ST FLOOR ENLARGED PLANS - DEMO AND NEW WORK

07-AE700 BUILDING 07- GROUND FLOOR - EXISTING CEILING CONDITIONS

07-AE701 BUILDING 07- 1ST FLOOR ENLARGED RCP PLANS - DEMO AND NEW WORK

07-AE702 BUILDING 07- 1ST FLOOR - EXISTING CEILING CONDITIONS

07-AE703 BUILDING 07- 1ST FLOOR ENLARGED RCP PLANS - DEMO AND NEW WORK

LIFE SAFETY

GJ101 LIFE SAFETY PLAN CODE REVIEW AND CODE ANALYSIS

GJ102 BUILDING 01, 05, & 07 BASEMENT FLOOR - LIFE SAFETY PLAN

GJ103 BUILDING 01, 05, & 07 1ST FLOOR - LIFE SAFETY PLAN

GJ104 BUILDING 01 & 05 2ND FLOOR - LIFE SAFETY PLAN

GJ105 BUILDING 01 & 05 3RD FLOOR - LIFE SAFETY PLAN

GJ106 BUILDING 01 & 05 4TH FLOOR - LIFE SAFETY PLAN

CIVIL

CJ101 NOTES & DETAILS

CD101 OVERALL EXISTING SITE CONDITIONS & DEMOLITION PLAN

CD102 DETAILED DEMOLITION PLAN 1

CS101 OVERALL SITE PLAN

CS102 DETAILED SITE PLAN 1

CG101 EROSION CONTROL PLAN

CU101 OVERALL UTILITY PLAN

CU102 DETAILED UTILITY PLAN 1

CK101 CIVIL DETAILS

S001 STRUCTURAL GENERAL NOTES, STRUCTURAL LOADS, MISCELLANEOUS

DETAILS

S501 STRUCTURAL DETAILS

MECHANICAL

MH001

MECHANICAL GENERAL NOTES, PIPING GENERAL NOTES, ABBREVIATIONS,

SYMBOLS

01-M101 BUILDING 01 - BASEMENT NEW VRF LOCATION PLAN

01-M101a

BUILDING 01 - BASEMENT MCR B-14 DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M101b

BUILDING 01 - BASEMENT ROOMS M-02 & A-5 DEMOLITION PLAN AND NEW

VRF LAYOUT

01-M101c

BUILDING 01 - BASEMENT ROOM B-14A DEMOLITION PLAN AND NEW VRF

01-M101d

BUILDING 01 - BASEMENT ROOMS J-1A & C-45 DEMOLITION PLAN AND NEW

01-M102 BUILDING 01 - 1ST FLOOR NEW VRF LOCATION PLAN

01-M102a

BUILDING 01 - 1ST FLOOR ROOMS 1220 & A-110A DEMOLITION PLAN AND

NEW VRF LAYOUT

00 01 15 - 4

01-M102b

BUILDING 01 - 1ST FLOOR ROOM E-135 DEMOLITION PLAN AND NEW VRF

01-M102c

BUILDING 01 - 1ST FLOOR ROOM F-126 DEMOLITION PLAN AND NEW VRF

01-M103 BUILDING 01 - 2ND FLOOR NEW VRF LOCATION PLAN

01-M103a

BUILDING 01 - 2ND FLOOR ROOM 243 DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M103b

BUILDING 01 - 2ND FLOOR ROOM B-233A DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M103c

BUILDING 01 - 2ND FLOOR ROOM 250A DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M104 BUILDING 01 - 3RD FLOOR NEW VRF LOCATION PLAN

01-M104a

BUILDING 01 - 3RD FLOOR ROOM A-363 DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M104b

BUILDING 01 - 3RD FLOOR ROOM B-347C DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M104c

BUILDING 01 - 3RD FLOOR ROOM C-339 DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M105 BUILDING 01 - 4TH FLOOR NEW VRF LOCATION PLAN

01-M105a BUILDING 01 - 4TH FLOOR ROOM 4031 DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M105b BUILDING 01 - 4TH FLOOR ROOM 4305 DEMOLITION PLAN AND NEW VRF

LAYOUT

01-M105c BUILDING 01 - 4TH FLOOR ROOM 4292 DEMOLITION PLAN AND NEW VRF

03-M101

BUILDING 03 - 1ST FLOOR PLAN AND ROOM 118 - DEMOLITION AND NEW

05-M101

BUILDING 05 - BASEMENT FLOOR - LOCATION & DEMOLITION AND NEW VRF

LAYOUT PLAN

05-M102

BUILDING 05 - 1ST FLOOR - NEW VRF LOCATION PLAN, DEMOLITION &

NEW VRF LAYOUT PLAN

05-M103

BUILDING 05 - 2ND FLOOR - NEW VRF LOCATION PLAN, DEMOLITION &

NEW VRF LAYOUT PLAN

05-M104

BUILDING 05 - 3RD FLOOR - NEW VRF LOCATION PLAN, DEMOLITION &

NEW VRF LAYOUT PLAN

05-M105

BUILDING 05 - 4TH FLOOR - NEW VRF LOCATION PLAN, DEMOLITION &

NEW VRF LAYOUT PLAN

06-M101 BUILDING 06 - 1ST FLOOR DEMOLITION AND NEW HVAC LAYOUT

07-M101

BUILDING 07 - GROUND FLOOR - NEW VRF LOCATION, DEMOLITION PLAN &

VRF LAYOUT PLAN

07-M102

BUILDING 07 - 1ST FLOOR - NEW VRF LOCATION, DEMOLITION PLAN &

VRF LAYOUT PLAN

M201 MECHANICAL CONDENSING UNIT LOCATION PLAN

M501 MECHANICAL DETAILS

00 01 15 - 5

M502 MECHANICAL DETAILS

M601 EQUIPMENT SCHEDULE

M602 BUILDING 01 - VRF SCHEMATIC DIAGRAM_

M603 BUILDING 03, 05, & 07 VRF SCHEMATIC DIAGRAM

M604 VRF SYSTEM CONTROL POINTS AND DIAGRAM

ELECTRICAL

E001 ELECTRICAL SYMBOLS, LEGENDS, ABBREVIATIONS AND GENERAL NOTES

01-E101 BUILDING 01 - OVERALL BASEMENT ELECTRICAL PLAN

01-E101a

BUILDING 01 - BASEMENT ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E101b

BUILDING 01 - BASEMENT ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E101c

BUILDING 01 - BASEMENT ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E101d

BUILDING 01 - BASEMENT ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E101e

BUILDING 01 - BASEMENT ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E101f

BUILDING 01 - BASEMENT ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E102 BUILDING 01 - OVERALL 1ST FLOOR ELECTRICAL PLAN

01-E102a

BUILDING 01 - 1ST FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E102b

BUILDING 01 - 1ST FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E102c

BUILDING 01 - 1ST FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E102d

BUILDING 01 - 1ST FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E102e

BUILDING 01 - 1ST FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E103 BUILDING 01 - OVERALL 2ND FLOOR ELECTRICAL PLAN

01-E103a

BUILDING 01 - 2ND FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E103b

BUILDING 01 - 2ND FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E103c

BUILDING 01 - 2ND FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E104 BUILDING 01 - OVERALL 3RD FLOOR ELECTRICAL PLAN

01-E104a

BUILDING 01 - 3RD FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E104b

BUILDING 01 - 3RD FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E104c

BUILDING 01 - 3RD FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E105 BUILDING 01 - OVERALL 4TH FLOOR ELECTRICAL PLAN

01-E105a

BUILDING 01 - 4TH FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E105b

BUILDING 01 - 4TH FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

00 01 15 - 6

01-E105c

BUILDING 01 - 4TH FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

01-E201 ELECTRICAL CONDENSING UNIT ROOF PLAN

01-E501 ELECTRICAL LIGHTING CALCULATIONS (TYPICAL TR & MCR)

01-E502 ELECTRICAL CONSTRUCTION DETAILS

01-E503 ELECTRICAL CONSTRUCTION DETAILS

01-E504 ELECTRICAL CONSTRUCTION DETAILS

01-E505 ELECTRICAL CONSTRUCTION DETAILS

01-E506 ELECTRICAL CONSTRUCTION DETAILS

01-E601 BUILDING 01 - POWER RISER DIAGRAM

01-E602 BUILDING 01 - POWER RISER DIAGRAM

01-E603 ELECTRICAL PANELBOARD SCHEDULES

01-E604 ELECTRICAL PANELBOARD SCHEDULES

01-E605 ELECTRICAL PANELBOARD SCHEDULES

01-E606 ELECTRICAL PANELBOARD SCHEDULES

01-E607 ELECTRICAL PANELBOARD SCHEDULES

01-E608 ELECTRICAL PANELBOARD SCHEDULES

01-E609 ELECTRICAL PANELBOARD SCHEDULES

01-E610 ELECTRICAL PANELBOARD SCHEDULES

01-E611 ELECTRICAL PANELBOARD SCHEDULES

01-E612 BUILDING 01 - ELECTRICAL STUDIES - I

01-E613 BUILDING 01 - ELECTRICAL STUDIES - II

03-E101 BUILDING 03 - OVERALL 1ST FLOOR ELECTRICAL PLAN

03-E101a

BUILDING 03 - 1ST FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

03-E501 ELECTRICAL CONSTRUCTION DETAILS

03-E601 ELECTRICAL RISER & PANELBOARD SCHEDULES

05-E101 BUILDING 05 - EXISTING OVERALL BASEMENT FLOOR PLAN

05-E101b

BUILDING 05 - BASEMENT ENLARGED ELECTRICAL PLANS - DEMO AND NEW

WORK

05-E102 BUILDING 05 - OVERALL 1ST AND 2ND FLOOR PLAN

05-E102b

BUILDING 05 - 2ND FLOOR ENLARGED ELECTRICAL PLANS - DEMO AND NEW

WORK

05-E103 BUILDING 05 - OVERALL 3RD AND 4TH FLOOR PLAN

05-E103a

BUILDING 05 - 3RD FLOOR ENLARGED ELECTRICAL PLANS - DEMO AND NEW

WORK

05-E103b

BUILDING 05 - 4TH FLOOR ENLARGED ELECTRICAL PLANS - DEMO AND NEW

WORK

05-E501 ELECTRICAL CONSTRUCTION DETAILS

05-E502 ELECTRICAL CONSTRUCTION DETAILS

05-E601 BUILDING 05 - POWER RISER DIAGRAM

05-E602 ELECTRICAL PANELBOARD SCHEDULES

05-E603 ELECTRICAL PANELBOARD SCHEDULES

05-E604 ELECTRICAL PANELBOARD SCHEDULES

05-E605 ELECTRICAL PANELBOARD SCHEDULES

00 01 15 - 7

06-E101 BUILDING 06 - OVERALL 1ST FLOOR ELECTRICAL PLAN

06-E501 ELECTRICAL CONSTRUCTION DETAILS

06-E601 BUILDING 06 - ELECTRICAL RISERS AND SCHEDULES

07-E101 BUILDING 07 - OVERALL GROUND FLOOR ELECTRICAL PLAN

07-E101a

BUILDING 07 - GROUND FLOOR ENLARGED ELECTRICAL PLANS - DEMO AND

NEW WORK

07-E102 BUILDING 07 - OVERALL 1ST FLOOR ELECTRICAL PLAN

07-E102a

BUILDING 07 - 1ST FLOOR ENLARGED ELECTRICAL PLANS

DEMO AND NEW WORK

07-E501 ELECTRICAL CONSTRUCTION DETAILS

07-E502 ELECTRICAL CONSTRUCTION DETAILS

07-E601 BUILDING 07 - POWER RISER DIAGRAM

07-E602 BUILDING 07 - GROUND RISER DIAGRAM

07-E603 ELECTRICAL PANELBOARD SCHEDULES

FIRE PROTECTION

F001 FIRE ALARM & FIRE SPRINKLER LEGEND, NOTES, AND RISER

01-F101 BUILDING 01 - EXISTING OVERALL BASEMENT FLOOR PLAN

01-F101a BUILDING 01 - BASEMENT FLOOR SPRINKLER LAYOUT - MCR B-14

01-F101b BUILDING 01 - BASEMENT FLOOR SPRINKLER LAYOUT - M-02, A-5, J-1A, C-45, & B-14A

01-F102 BUILDING 01 - EXISTING OVERALL 1ST FLOOR PLAN & ENLARGED FLOOR

PLANS

01-F102a BUILDING 01 - 1ST FLOOR SPRINKLER LAYOUT - 1220, A-110, E-135, & F-126

01-F103 BUILDING 01 - EXISTING OVERALL 2ND FLOOR PLAN & ENLARGED FLOOR

PLANS

01-F103a BUILDING 01 - 2ND FLOOR SPRINKLER LAYOUT - 243, B-233A & C250A

01-F104 BUILDING 01 - EXISTING OVERALL 3RD FLOOR PLAN & ENLARGED FLOOR

PLANS

01-F104a BUILDING 01 - 3RD FLOOR SPRINKLER LAYOUT - A-363, B-347C, & C339

01-F105 BUILDING 01 - EXISTING OVERALL 4TH FLOOR PLAN & ENLARGED FLOOR

PLANS

01-F105a BUILDING 01 - 4TH FLOOR SPRINKLER LAYOUT - 4031, 4305, & 4292

03-F101 BUILDING 03 - EXISTING 1ST FLOOR PLAN

05-F101 BUILDING 05 - EXISTING OVERALL BASEMENT FLOOR PLAN

05-F102 BUILDING 05 - EXISTING OVERALL 1ST AND 2ND FLOOR PLAN

05-F103 BUILDING 05 - EXISTING OVERALL 3RD AND 4TH FLOOR PLAN

06-F101 BUILDING 06 - EXISTING 1ST FLOOR PLAN

07-F101 BUILDING 07 CLC - EXISTING OVERALL GOUND FLOOR PLAN

07-F102 BUILDING 07 CLC - EXISTING OVERALL 1ST FLOOR PLAN

TELECOMMUNICATOINS

00 01 15 - 8

T-000 TELECOMMUNICATIONS SYMBOLS AND ABBREVIATIONS

T-001 SITE PLAN

T-002 SITE PLAN 2

T-003

01 - BASEMENT LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-004

01 - FIRST LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-005

01 - SECOND LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-006

01 - THIRD LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-007

01 - FOURTH LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-008

05 - BASEMENT AND SUB-BASEMENT LEVEL FLOOR PLAN - OVERALL -

INTRA-BUILDING FIBER ROUTING DIAGRAM

T-009

05 - FIRST LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-010

05 - SECOND LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-011

05 - THIRD LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-012

05 - FOURTH LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-013

06 - FIRST LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-014

07 - FIRST LEVEL FLOOR PLAN - OVERALL - INTRA-BUILDING FIBER

ROUTING DIAGRAM

T-015 FIBER RISER DIAGRAM - A SIDE AND B SIDE

T-016 FIBER RISER DIAGRAM - MCR AND DMARC CABLES

01-TD100

BASEMENT LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

01-TD100A

BASEMENT LEVEL FLOOR PLAN - AREA A - DEMOLITION -

TELECOMMUNICATIONS

01-TD100B

BASEMENT LEVEL FLOOR PLAN - AREA B - DEMOLITION -

TELECOMMUNICATIONS

01-TD100C

BASEMENT LEVEL FLOOR PLAN - AREA C - DEMOLITION -

TELECOMMUNICATIONS

01-TD100D

BASEMENT LEVEL FLOOR PLAN - AREA D - DEMOLITION -

TELECOMMUNICATIONS

01-TD100E

BASEMENT LEVEL FLOOR PLAN - AREA E - DEMOLITION -

TELECOMMUNICATIONS

01-TD100F

BASEMENT LEVEL FLOOR PLAN - AREA F - DEMOLITION -

TELECOMMUNICATIONS

01-TD100G

BASEMENT LEVEL FLOOR PLAN - AREA G - DEMOLITION -

TELECOMMUNICATIONS

01-TD100H

BASEMENT LEVEL FLOOR PLAN - AREA H - DEMOLITION -

TELECOMMUNICATIONS

01-TD100I

BASEMENT LEVEL FLOOR PLAN - AREA I - DEMOLITION -

TELECOMMUNICATIONS

01-TD100J

BASEMENT LEVEL FLOOR PLAN - AREA J - DEMOLITION -

TELECOMMUNICATIONS

00 01 15 - 9

01-TD101

FIRST LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

01-TD101A

FIRST LEVEL FLOOR PLAN - AREA A - DEMOLITION -

TELECOMMUNICATIONS

01-TD101B

FIRST LEVEL FLOOR PLAN - AREA B - DEMOLITION -

TELECOMMUNICATIONS

01-TD101C

FIRST LEVEL FLOOR PLAN - AREA C - DEMOLITION -

TELECOMMUNICATIONS

01-TD101D

FIRST LEVEL FLOOR PLAN - AREA D - DEMOLITION -

TELECOMMUNICATIONS

01-TD101E

FIRST LEVEL FLOOR PLAN - AREA E - DEMOLITION -

TELECOMMUNICATIONS

01-TD101F

FIRST LEVEL FLOOR PLAN - AREA F - DEMOLITION -

TELECOMMUNICATIONS

01-TD101G

FIRST LEVEL FLOOR PLAN - AREA G - DEMOLITION -

TELECOMMUNICATIONS

01-TD101H

FIRST LEVEL FLOOR PLAN - AREA H - DEMOLITION -

TELECOMMUNICATIONS

01-TD101I

FIRST LEVEL FLOOR PLAN - AREA I - DEMOLITION -

TELECOMMUNICATIONS

01-TD101J

FIRST LEVEL FLOOR PLAN - AREA J - DEMOLITION -

TELECOMMUNICATIONS

01-TD101K

FIRST LEVEL FLOOR PLAN - AREA K - DEMOLITION -

TELECOMMUNICATIONS

01-TD102

SECOND LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

01-TD102A

SECOND LEVEL FLOOR PLAN - AREA A - DEMOLITION -

TELECOMMUNICATIONS

01-TD102B

SECOND LEVEL FLOOR PLAN - AREA B - DEMOLITION -

TELECOMMUNICATIONS

01-TD102C

SECOND LEVEL FLOOR PLAN - AREA C - DEMOLITION -

TELECOMMUNICATIONS

01-TD102D

SECOND LEVEL FLOOR PLAN - AREA D - DEMOLITION -

TELECOMMUNICATIONS

01-TD102E

SECOND LEVEL FLOOR PLAN - AREA E - DEMOLITION -

TELECOMMUNICATIONS

01-TD102F

SECOND LEVEL FLOOR PLAN - AREA F - DEMOLITION -

TELECOMMUNICATIONS

01-TD102J

SECOND LEVEL FLOOR PLAN - AREA J - DEMOLITION -

TELECOMMUNICATIONS

01-TD103

THIRD LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

01-TD103A

THIRD LEVEL FLOOR PLAN - AREA A - DEMOLITION -

TELECOMMUNICATIONS

01-TD103B

THIRD LEVEL FLOOR PLAN - AREA B - DEMOLITION -

TELECOMMUNICATIONS

01-TD103C

THIRD LEVEL FLOOR PLAN - AREA C - DEMOLITION -

TELECOMMUNICATIONS

01-TD103D

THIRD LEVEL FLOOR PLAN - AREA D - DEMOLITION -

TELECOMMUNICATIONS

01-TD103E

THIRD LEVEL FLOOR PLAN - AREA E - DEMOLITION -

TELECOMMUNICATIONS

01-TD103F

THIRD LEVEL FLOOR PLAN - AREA F - DEMOLITION -

00 01 15 - 10

01-TD104

FOURTH LEVEL FLOOR PLAN - AREA A - DEMOLITION -

TELECOMMUNICATIONS

01-TD104A

FOURTH LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

01-TD104B

FOURTH LEVEL FLOOR PLAN - AREA B - DEMOLITION -

TELECOMMUNICATIONS

01-TD104C

FOURTH LEVEL FLOOR PLAN - AREA C - DEMOLITION -

TELECOMMUNICATIONS

01-TD104D

FOURTH LEVEL FLOOR PLAN - AREA D - DEMOLITION -

TELECOMMUNICATIONS

01-TD104E

FOURTH LEVEL FLOOR PLAN - AREA E - DEMOLITION -

TELECOMMUNICATIONS

01-TD104F

FOURTH LEVEL FLOOR PLAN - AREA F - DEMOLITION -

01-TD400 ENLARGED TELECOMMUNICATIONS ROOM - DEMO

01-TD401 ENLARGED TELECOMMUNICATIONS ROOM - DEMO

01-TD402 ENLARGED TELECOMMUNICATIONS ROOM - DEMO

01-TD403 ENLARGED TELECOMMUNICATIONS ROOM - DEMO

01-TN100 BASEMENT LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

01-TN100A BASEMENT LEVEL FLOOR PLAN - AREA A - TELECOMMUNICATIONS

01-TN100B BASEMENT LEVEL FLOOR PLAN - AREA B - TELECOMMUNICATIONS

01-TN100C BASEMENT LEVEL FLOOR PLAN - AREA C - TELECOMMUNICATIONS

01-TN100D BASEMENT LEVEL FLOOR PLAN - AREA D - TELECOMMUNICATIONS

01-TN100E BASEMENT LEVEL FLOOR PLAN - AREA E - TELECOMMUNICATIONS

01-TN100F BASEMENT LEVEL FLOOR PLAN - AREA F - TELECOMMUNICATIONS

01-TN100G BASEMENT LEVEL FLOOR PLAN - AREA G - TELECOMMUNICATIONS

01-TN100H BASEMENT LEVEL FLOOR PLAN - AREA H - TELECOMMUNICATIONS

01-TN100I BASEMENT LEVEL FLOOR PLAN - AREA I - TELECOMMUNICATIONS

01-TN100J BASEMENT LEVEL FLOOR PLAN - AREA J - TELECOMMUNICATIONS

01-TN101 FIRST LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

01-TN101A FIRST LEVEL FLOOR PLAN - AREA A - TELECOMMUNICATIONS

01-TN101B FIRST LEVEL FLOOR PLAN - AREA B - TELECOMMUNICATIONS

01-TN101C FIRST LEVEL FLOOR PLAN - AREA C - TELECOMMUNICATIONS

01-TN101D FIRST LEVEL FLOOR PLAN - AREA D - TELECOMMUNICATIONS

01-TN101E FIRST LEVEL FLOOR PLAN - AREA E - TELECOMMUNICATIONS

01-TN101F FIRST LEVEL FLOOR PLAN - AREA F - TELECOMMUNICATIONS

01-TN101G FIRST LEVEL FLOOR PLAN - AREA G - TELECOMMUNICATIONS

01-TN101H FIRST LEVEL FLOOR PLAN - AREA H - TELECOMMUNICATIONS

01-TN101I FIRST LEVEL FLOOR PLAN - AREA I - TELECOMMUNICATIONS

01-TN101J FIRST LEVEL FLOOR PLAN - AREA J - TELECOMMUNICATIONS

01-TN101K FIRST LEVEL FLOOR PLAN - AREA K - TELECOMMUNICATIONS

01-TN102 SECOND LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

01-TN102A SECOND LEVEL FLOOR PLAN - AREA A - TELECOMMUNICATIONS

01-TN102B SECOND LEVEL FLOOR PLAN - AREA B - TELECOMMUNICATIONS

01-TN102C SECOND LEVEL FLOOR PLAN - AREA C - TELECOMMUNICATIONS

01-TN102D SECOND LEVEL FLOOR PLAN - AREA D - TELECOMMUNICATIONS

00 01 15 - 11

01-TN102E SECOND LEVEL FLOOR PLAN - AREA E - TELECOMMUNICATIONS

01-TN102F SECOND LEVEL FLOOR PLAN - AREA F - TELECOMMUNICATIONS

01-TN102J SECOND LEVEL FLOOR PLAN - AREA J - TELECOMMUNICATIONS

01-TN103 THIRD LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

01-TN103A THIRD LEVEL FLOOR PLAN - AREA A - TELECOMMUNICATIONS

01-TN103B THIRD LEVEL FLOOR PLAN - AREA B - TELECOMMUNICATIONS

01-TN103C THIRD LEVEL FLOOR PLAN - AREA C - TELECOMMUNICATIONS

01-TN103D THIRD LEVEL FLOOR PLAN - AREA D - TELECOMMUNICATIONS

01-TN103E THIRD LEVEL FLOOR PLAN - AREA E - TELECOMMUNICATIONS

01-TN103F THIRD LEVEL FLOOR PLAN - AREA F - TELECOMMUNICATIONS

01-TN104 FOURTH LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

01-TN104A FOURTH LEVEL FLOOR PLAN - AREA A - TELECOMMUNICATIONS

01-TN104B FOURTH LEVEL FLOOR PLAN - AREA B - TELECOMMUNICATIONS

01-TN104C FOURTH LEVEL FLOOR PLAN - AREA C - TELECOMMUNICATIONS

01-TN104D FOURTH LEVEL FLOOR PLAN - AREA D - TELECOMMUNICATIONS

01-TN104E FOURTH LEVEL FLOOR PLAN - AREA E - TELECOMMUNICATIONS

01-TN104F FOURTH LEVEL FLOOR PLAN - AREA F - TELECOMMUNICATIONS

01-TN400 ENLARGED TELECOMMUNICATIONS ROOM - TR A-5

01-TN401 ENLARGED TELECOMMUNICATIONS ROOM - TR B-14A

01-TN402 ENLARGED TELECOMMUNICATIONS SERVER ROOM - TR B-14

01-TN403 ENLARGED TELECOMMUNICATIONS SERVER ROOM - TR B-14

01-TN404 ENLARGED TELECOMMUNICATIONS SERVER ROOM - TR B-14

01-TN405

ENLARGED TELECOMMUNICATIONS SERVER ROOM EAST ELEVATION VIEW PLAN

TR B-14

01-TN406 ENLARGED TELECOMMUNICATIONS ROOM - TR C-45

01-TN407 ENLARGED TELECOMMUNICATIONS ROOM - TR J-1A

01-TN408 ENLARGED TELECOMMUNICATIONS ROOM - TR M-02

01-TN409 ENLARGED TELECOMMUNICATIONS ROOM - TR 1220

01-TN410 ENLARGED TELECOMMUNICATIONS ROOM - TR A-110A

01-TN411 ENLARGED TELECOMMUNICATIONS ROOM - TR E-135

01-TN412 ENLARGED TELECOMMUNICATIONS ROOM - TR F-126

01-TN413 ENLARGED TELECOMMUNICATIONS ROOM - TR E-243

01-TN414 ENLARGED TELECOMMUNICATIONS ROOM - TR 250A

01-TN415 ENLARGED TELECOMMUNICATIONS ROOM - TR B-235A

01-TN416 ENLARGED TELECOMMUNICATIONS ROOM - TR A363

01-TN417 ENLARGED TELECOMMUNICATIONS ROOM - TR B-347C

01-TN418 ENLARGED TELECOMMUNICATIONS ROOM - TR C-339

01-TN419 ENLARGED TELECOMMUNICATIONS ROOM - TR 4305

01-TN420 ENLARGED TELECOMMUNICATIONS ROOM - TR B4031

01-TN421 ENLARGED TELECOMMUNICATIONS ROOM - TR 4292

01-TN700

BUILDING 01 - BASEMENT FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

01-TN701

BUILDING 01 - 1ST FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

00 01 15 - 12

01-TN702

BUILDING 01 - 2ND FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

01-TN703

BUILDING 01 - 3RD FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

01-TN704

BUILDING 01 - 4TH FLOOR PLAN - TELECOMMUNICATIONS - CABLE

03-TN700

BUILDING 03 - 1ST FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

03-TD101

FIRST LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

03-TD400 ENLARGED TELECOMMUNICATIONS ROOM - DEMO

03-TN100 FIRST LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

03-TN400 ENLARGED TELECOMMUNICATIONS ROOM - TR 118

05-TD100

BASEMENT AND SUB-BASEMENT LEVEL FLOOR PLAN - OVERALL -

DEMOLITION - TELECOMMUNICATIONS

05-TD101

FIRST LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

05-TD102

SECOND LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

05-TD103

THIRD LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

05-TD104

FOURTH LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

05-TD400 ENLARGED TELECOMMUNICATIONS ROOM - DEMO

05-TD401 ENLARGED TELECOMMUNICATIONS EXISTING ROOM - DEMO

05-TN100

BASEMENT AND SUB-BASEMENT LEVEL FLOOR PLAN - OVERALL -

TELECOMMUNICATIONS

05-TN101 FIRST LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

05-TN102 SECOND LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

05-TN103 THIRD LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

05-TN104 FOURTH LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

05-TN401 ENLARGED TELECOMMUNICATIONS ROOM - TR RB-04A

05-TN402 ENLARGED TELECOMMUNICATIONS ROOM - TR R-202A

05-TN403 ENLARGED TELECOMMUNICATIONS ROOM - TR R-302A

05-TN404 ENLARGED TELECOMMUNICATIONS ROOM - TR R-402A

05-TN700

BUILDING 05 - BASEMENT AND SUB-BASEMENT FLOOR PLAN - TELECOM -

CABLE DISTANCE

05-TN701

BUILDING 05 - 1ST FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

05-TN702

BUILDING 05 - 2ND FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

05-TN703

BUILDING 05 - 3RD FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

05-TN704

BUILDING 05 - 4TH FLOOR PLAN - TELECOMMUNICATIONS - CABLE

06-TD100

FIRST LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

06-TN101 FIRST LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

00 01 15 - 13

06-TN401 ENLARGED TELECOMMUNICATIONS ROOM - TR 1A

06-TN701

BUILDING 06 - 1ST FLOOR PLAN - TELECOMMUNICATIONS - CABLE

07-TD100

GROUND LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

07-TD100A

GROUND LEVEL FLOOR PLAN - AREA A - DEMOLITION -

TELECOMMUNICATIONS

07-TD100B

GROUND LEVEL FLOOR PLAN - AREA B - DEMOLITION -

TELECOMMUNICATIONS

07-TD101

FIRST LEVEL FLOOR PLAN - OVERALL - DEMOLITION -

TELECOMMUNICATIONS

07-TD101A

FIRST LEVEL FLOOR PLAN - AREA A - DEMOLITION -

TELECOMMUNICATIONS

07-TD101B

FIRST LEVEL FLOOR PLAN - AREA B - DEMOLITION -

TELECOMMUNICATIONS

07-TD400 ENLARGED TELECOMMUNICATIONS ROOM - DEMO

07-TD401 ENLARGED TELECOMMUNICATIONS EXISTING ROOM - DEMO

07-TN100 GROUND LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

07-TN100A GROUND LEVEL FLOOR PLAN - AREA A - TELECOMMUNICATIONS

07-TN100B GROUND LEVEL FLOOR PLAN - AREA B - TELECOMMUNICATIONS

07-TN101 FIRST LEVEL FLOOR PLAN - OVERALL - TELECOMMUNICATIONS

07-TN101A FIRST LEVEL FLOOR PLAN - AREA A - TELECOMMUNICATIONS

07-TN101B FIRST LEVEL FLOOR PLAN - AREA B - TELECOMMUNICATIONS

07-TN400 ENLARGED TELECOMMUNICATIONS ROOM - TR HB-15

07-TN401 ENLARGED TELECOMMUNICATIONS ROOM - TR HB-125

07-TN700

BUILDING 07 - GROUND FLOOR PLAN - TELECOMMUNICATIONS - CABLE

DISTANCE

07-TN701

BUILDING 07 - 1ST FLOOR PLAN - TELECOMMUNICATIONS - CABLE

TN500 DATA COUNTS BY TR SPACE SCHEDULE

TN501 TELECOMMUNICATIONS DETAILS

TN502 TELECOMMUNICATIONS DETAILS

TN503 TELECOMMUNICATIONS DETAILS

TN504 TELECOMMUNICATIONS DETAILS

TN505 TELECOMMUNICATIONS DETAILS

TN506 TELECOMMUNICATIONS DETAILS

TN507 TELECOMMUNICATIONS DETAILS

TN508 TELECOMMUNICATIONS DETAILS

TN509 TELECOMMUNICATIONS DETAILS

TN510 TELECOMMUNICATIONS DETAILS

ENVIRONMENTAL

H-100 HAZARDOUS MATERIALS COVER PAGE

H-101 BUILDING 01- BASEMENT FLOOR HAZARDOUS MATERIALS

H-102 BUILDING 01- 1ST FLOOR EXISTING HAZARDOUS MATERIALS

H-103 BUILDING 01- 2ND FLOOR EXISTING HAZARDOUS MATERIALS

00 01 15 - 14

H-104 BUILDING 01- 3RD FLOOR EXISTING HAZARDOUS MATERIALS

H-105 BUILDING 01- 4TH FLOOR EXISTING HAZARDOUS MATERIALS

H-106 BUILDING 05- 1ST AND 2ND FLOOR HAZARDOUS MATERIALS

H-107 BUILDING 07- GROUND FLOOR HAZARDOUS MATERIALS

H-108 BUILDING 07- 1ST FLOOR HAZARDOUS MATERIALS

SECURITY

TY000 SECURITY COVER SHEET

TY001 SITE PLAN - SECURITY

01-TY100 BUILDING 01 - BASEMENT PLAN - SECURITY

01-TY100A BUILDING 01 - BASEMENT PLAN - AREA A - SECURITY

01-TY100B BUILDING 01 - BASEMENT PLAN - AREA B - SECURITY

01-TY100C BUILDING 01 - BASEMENT PLAN - AREA C - SECURITY

01-TY100D BUILDING 01 - BASEMENT PLAN - AREA D - SECURITY

01-TY100E BUILDING 01 - BASEMENT PLAN - AREA E - SECURITY

01-TY100F BUILDING 01 - BASEMENT PLAN - AREA F - SECURITY

01-TY100G BUILDING 01 - BASEMENT PLAN - AREA G - SECURITY

01-TY100H BUILDING 01 - BASEMENT PLAN - AREA H - SECURITY

01-TY100I BUILDING 01 - BASEMENT PLAN - AREA I - SECURITY

01-TY100J BUILDING 01 - BASEMENT PLAN - AREA J - SECURITY

01-TY101 BUILDING 01 - 1ST FLOOR PLAN - SECURITY

01-TY101A BUILDING 01 - 1ST FLOOR PLAN - AREA A - SECURITY

01-TY101B BUILDING 01 - 1ST FLOOR PLAN - AREA B - SECURITY

01-TY101C BUILDING 01 - 1ST FLOOR PLAN - AREA C - SECURITY

01-TY101D BUILDING 01 - 1ST FLOOR PLAN - AREA D - SECURITY

01-TY101E BUILDING 01 - 1ST FLOOR PLAN - AREA E - SECURITY

01-TY101F BUILDING 01 - 1ST FLOOR PLAN - AREA F - SECURITY

01-TY101G BUILDING 01 - 1ST FLOOR PLAN - AREA G - SECURITY

01-TY101H BUILDING 01 - 1ST FLOOR PLAN - AREA H - SECURITY

01-TY101I BUILDING 01 - 1ST FLOOR PLAN - AREA I - SECURITY

01-TY101J BUILDING 01 - 1ST FLOOR PLAN - AREA J - SECURITY

01-TY101K BUILDING 01 - 1ST FLOOR PLAN - AREA K - SECURITY

01-TY102 BUILDING 01 - 2ND FLOOR PLAN - SECURITY

01-TY102A BUILDING 01 - 2ND FLOOR PLAN - AREA A - SECURITY

01-TY102B BUILDING 01 - 2ND FLOOR PLAN - AREA B - SECURITY

01-TY102C BUILDING 01 - 2ND FLOOR PLAN - AREA C - SECURITY

01-TY102D BUILDING 01 - 2ND FLOOR PLAN - AREA D - SECURITY

01-TY102E BUILDING 01 - 2ND FLOOR PLAN - AREA E - SECURITY

01-TY102F BUILDING 01 - 2ND FLOOR PLAN - AREA F - SECURITY

01-TY102J BUILDING 01 - 2ND FLOOR PLAN - AREA J - SECURITY

01-TY103 BUILDING 01 - 3RD FLOOR PLAN - SECURITY

01-TY103A BUILDING 01 - 3RD FLOOR PLAN - AREA A - SECURITY

01-TY103B BUILDING 01 - 3RD FLOOR PLAN - AREA B - SECURITY

01-TY103C BUILDING 01 - 3RD FLOOR PLAN - AREA C - SECURITY

01-TY103D BUILDING 01 - 3RD FLOOR PLAN - AREA D - SECURITY

01-TY103E BUILDING 01 - 3RD FLOOR PLAN - AREA E - SECURITY

00 01 15 - 15

01-TY103F BUILDING 01 - 3RD FLOOR PLAN - AREA F - SECURITY

01-TY104 BUILDING 01 - 4TH FLOOR PLAN - SECURITY

01-TY104A BUILDING 01 - 4TH FLOOR PLAN - AREA A - SECURITY

01-TY104B BUILDING 01 - 4TH FLOOR PLAN - AREA B - SECURITY

01-TY104C BUILDING 01 - 4TH FLOOR PLAN - AREA C - SECURITY

01-TY104D BUILDING 01 - 4TH FLOOR PLAN - AREA D - SECURITY

01-TY104E BUILDING 01 - 4TH FLOOR PLAN - AREA E - SECURITY

01-TY104F BUILDING 01 - 4TH FLOOR PLAN - AREA F - SECURITY

01-TY200 BUILDING 01 - TECHNOLOGY ENGLARGEMENTS

03-TY101 BUILDING 03 - 1ST FLOOR PLAN - SECURITY

05-TY009 BUILDING 05 - SUB-BASEMENT PLAN - SECURITY

05-TY100 BUILDING 05 - BASEMENT PLAN - SECURITY

05-TY101 BUILDING 05 - 1ST FLOOR PLAN - SECURITY

05-TY102 BUILDING 05 - 2ND FLOOR PLAN - SECURITY

05-TY103 BUILDING 05 - 3RD FLOOR PLAN - SECURITY

05-TY104 BUILDING 05 - 4TH FLOOR PLAN - SECURITY

07-TY100 BUILDING 07 - GROUND FLOOR PLAN - SECURITY

07-TY100A BUILDING 07 - GROUND FLOOR PLAN - AREA A - SECURITY

07-TY100B BUILDING 07 - GROUND FLOOR PLAN - AREA B - SECURITY

07-TY101 BUILDING 07 - 1ST FLOOR PLAN - SECURITY

07-TY101A BUILDING 07 - 1ST FLOOR PLAN - AREA A - SECURITY

07-TY101B BUILDING 07 - 1ST FLOOR PLAN - AREA B - SECURITY

TY300 TECHNOLOGY DETAILS AND DIAGRAMS

TY400 TECHNOLOGY SCHEDULES

- - - END - - -

01 00 00 -1

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the EHRM Infrastructure

Upgrades located on multiple building across the Montgomery VA Medical

Center Jackson MS, site (VA Project #586-21-700), as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting

Officer.

Mr. Trevor Langston/COR

601-364-7948 Trevor.Langston@va.gov G.V. (Sonny) Montgomery VA Medical Center 1500 East Woodrow Wilson Ave.

Jackson, MS 39216

C. Offices of Planate Management Group, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

01 00 00 -2

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. Schedule: See section 1.42 within this specification 01 00 00.

G. Prior to commencing work, general contractor shall provide proof that a

OSHA certified “competent person” (CP) (29 CFR 1926.20(b) (2) will maintain a presence at the work site whenever the general or subcontractors are present.

H. Training:

1. All employees of general contractor or subcontractors shall have the

10-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by the VA Contracting

Officer with input from the Infection Control Risk Assessment (ICRA) team.

2. Submit training record of all such employees for approval before the start of work.

I. Terms used in this contract such as Veterans Affairs (VA) and

Government, Contracting Officer (CO); Architect-Engineer (AE);

Contracting Officer’s Representative (COR) or COR (RE), Engineering

Officer (EO) may be used interchangeably, and refer to the same entity.

1.3 STATEMENT OF BID ITEM(S)

ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items.

ITEM II, Plumbing Work: Work includes all labor, material, equipment and supervision to perform the required plumbing construction work on this project.

ITEM III, Mechanical Work: Work includes all labor, material, equipment and supervision to perform the required mechanical construction work on this project.

ITEM IV, Electrical Work: Work includes all labor, material, equipment and

01 00 00 -3

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

supervision to perform the required Electrical construction work on this project.

ITEM IV, Technology Work: Work includes all labor, material, equipment and supervision to perform the required Technology construction work on this project.

ITEM VI, Civil/Landscape Work: Work includes all labor, material, equipment and supervision to perform the required civil/Landscape construction work on this project.

ITEM VII, Structural Work: Work includes all labor, material, equipment and supervision to perform the required Structural construction work on this project.

ITEM IIX, Commissioning Work: Work includes all labor, material, equipment and supervision to perform the required civil construction work on this project.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from

01 00 00 -4

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. (NOT USED)

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

E. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

01 00 00 -5

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

G. Fire Safety

1. Applicable Publications: Publications listed below forma part of this Article to extent referenced. Publications are referenced in text by basic designations only.

a. American Society for Testing and Materials (ASTM):

E84-15b...........Surface Burning Characteristics of Building

Materials

b. National Fire Protection Association (NFPA):

10-2018...........Standard for Portable Fire Extinguishers

01 00 00 -6

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

30-2018...........Flammable and Combustible Liquids Code

51B-2019..........Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

70-2020...........National Electrical Code

241-2019..........Standard for Safeguarding Construction, Alteration, and Demolition Operations

c. Occupational Safety and Health Administration (OSHA):

29 CFR 1926-2015..Safety and Health Regulations for Construction

2. Prior to any worker for the Contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the General

Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc. Documentation shall be provided to the COR that individuals have undergone Contractor’s safety briefing. Contractor is to perform weekly fire hazard and

OSHA safety inspections on the entire construction area from the rime construction starts until the building is turned over to the

Government. A copy of these reports, listing all hazards identified and corrective actions taken, is to be provided weekly to the COR.

For additional requirements see Article 1.14 under Section 013526, Safety Requirements.

3. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.

4. Separate temporary facilities, such as trailers, storage sheds and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 20 feet exposing overall length, separate by 10 feet.

5. Separate temporary facilities, such as trailers, storage sheds and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 20 feet exposing overall length, separate by 10 feet.

a. Install and maintain temporary construction partitions to provide

01 00 00 -7

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

smoke-tight separations between construction areas and adjoining areas. Construct partitions of gypsum board or treated plywood

(flame spread rating of 25 or less in accordance with ASTM E84) on both sides of fire-retardant treated wood or metal steel studs. Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations. As a minimum at door openings, install Class C, ¾-hour fire/smoke rated doors with self-closing devices. In all cases, the temporary partition shall meet the minimum fire/smoke barrier requirements for the area affected.

b. Close all openings in smoke barriers and fire-rated construction

(walls, floors and ceilings) to maintain fire ratings. This includes any existing holes as well as Contractor caused holes.

Holes are to be sealed as soon as possible and as a minimum by the end of each workday with temporary or permanent fire sealant.

Seal penetrations with listed through-penetration fire stop materials in accordance with Section 078400, FIRESTOPPING.

6. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.

Open flame heating devices are prohibited on the Medical Center

Grounds.

7. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with COTR.

8. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily report findings and corrective actions weekly COTR.

9. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29

CFR 1926, NFPA 241 and NFPA 10.

10. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241, and NFPA 30.

11. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions

01 00 00 -8

G. V. (SONNY) MONTGOMERY VA MEDICAL CENTER, JACKSON MS

immediately under construction, and temporarily for connections.

Provide fire watch for impairments more than 1 hour in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS

AND STORAGE AREAS, and coordinate with COTR. All existing temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with them medical center. Parameters for the testing and results of any tests shall be recorded by the Medical Center and copies provided to the COTR.

12. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with COTR.

13. Hot Work: Perform and safeguard jot work operations in accordance with NFPA 241 and NFPA 51B. The Contractor shall be responsible for assigning an authorized supervisory representative to issue hot work permits.