This document contains an attachment outlining the preliminary milestone schedule for a renovation project and the corresponding federal contract opportunity solicitation. The renovation project involves upgrading a progressive care unit located at 4801 Linwood Blvd. in Kansas City, MO. for the Department of Veterans Affairs. Key milestones include notice to proceed, equipment shop drawings and submittals, field work commencement, floor abatement and piping installation, ductwork completion, mechanical rough-in, new mechanical risers and services installation, air handling unit installation, remaining work completion and substantial completion, and punchlist, commissioning and closeout. The related federal contract opportunity posted is solicitation number 36C25523R0115 to renovate the 4th floor progressive care unit under project number 589-22-420, with the Department of Veterans Affairs Veterans Health Administration as the issuing agency.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Project # 589-22-420
Renovate 4E for Progressive Care Unit
4801 Linwood Blvd., Kansas City, MO. 64128
ATTACHMENT 01 – PRELIMINARY MILESTONE SCHEDULE
07/17/2023
PRELIMINARY MILESTONE SCHEDULE
Activity Total Weeks from Notice to Proceed
1) Notice to Proceed 0 weeks
2) Major/Long Lead Equipment & Materials Shop Drawings + Submittals 5 weeks
3) Commence work in the field 8 weeks
4) Complete 3rd Floor abatement / floor cores and plumbing/piping work 18 weeks
5) Complete 4th Floor Ductwork 20 weeks
6) Complete all above-ceiling Mechanical Rough-in-4th Floor 30 weeks
7) Complete all in-wall Rough-in 30 weeks
8) Complete all new mechanical risers and services from floors below 40 weeks
9) Complete installation of new AHU 56 weeks
10) Complete all remaining work / Substantial Completion 64 weeks
11) Complete Punchlist, Commissioning, and Closeout / Final Completion 78 weeks