Attachment 01 Statement of Work.docx

DOCX document 172 KB Posted

Attached to
Repair (restore) Bonita Bay Docks Federal contract opportunity
Solicitation number
FA481922R0010
Issued by
Department of the Air Force Air Combat Command

About this file

This statement of work describes a design-build project to demolish, repair, and restore interior and exterior elements of docks at Bonita Bay in Tyndall Air Force Base, Florida. The contractor will be responsible for design, permitting, construction, and closeout activities, including demolition, concrete repair, roof replacement, mechanical and electrical upgrades, and compliance with environmental and safety requirements. The contractor must submit schedules, progress reports, quality control plans, safety plans, and other documents according to the due dates specified in the deliverables table. Construction is to be completed within 360 calendar days of notice to proceed. The solicitation was issued by the Air Force on behalf of Tyndall Air Force Base.

View the file

Other files for this federal contract opportunity

Other files attached to Repair (restore) Bonita Bay Docks, newest first.
File Type Posted
Pre-Award RFI Bonita Bay Docks.pdf PDF
Completed AF Form 813 Repair (Replace) Bonita Bay Docks.pdf PDF
Archeological Discovery trifold July2020.pdf PDF
Copy of Questions_Bonita Bay docks 2022 06 13.xlsx XLSX spreadsheet
RFP APPENDIX - A Bonita Bay Repair Restore_XLWU 21-8122_2022 06 16 (003).docx DOCX document
Site Visit Sign in Sheet 2 June 2022.pdf PDF
Solicitation Amendment FA481922R00100002 SF 30.pdf PDF
Attachment 01 Statement of Work.docx DOCX document
Attachment 06 AF Form 3000.pdf PDF
Attachment 13 Division Cost Estimate Worksheet.xls XLS spreadsheet
Attachment 04 Wage Determination.pdf PDF
Attachment 08 AF3065.pdf PDF
Attachment 05 AF Form 66.xls XLS spreadsheet
Attachment 11 Base Access Request EAL.xlsx XLSX spreadsheet
Attachment 03 APPENDIX B.pdf PDF
Attachment 10 Other Contract Requirements.pdf PDF
Solicitation Amendment FA481922R00100001 SF 30.pdf PDF
Attachment 12 Proof of Financial Responsibility.pdf PDF
Solicitation - FA481922R0010.pdf PDF
Attachment 09 Sample RFI.PDF PDF
Solicitation Amendment - FA481922R00100001.pdf PDF
Attachment 07 AF3064.pdf PDF
Attachment 02 APPENDIX A.docx DOCX document
PKC Section L and M Template (as of 1 Dec 21).docx DOCX document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

XLWU 22-8122

12 APRIL 2022

REQUEST FOR PROPOSAL

Statement of Work (SOW)

For

Bonita Bay Repair and Restore

TYNDALL AFB FLORIDA

Project Number: XLWU 22-8122

Contents

1.0SCOPE4
1.1General Requirements4
2.0APPLICABLE DOCUMENTS9
3.0GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)17
4.0MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS17
4.0A Table 1 - Table of Deliverables20
4.1Work Breakdown Structure (WBS)23
4.2Schedule and Planning Requirements23
4.2.1Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)23
4.2.2Integrated Master Schedule (IMS)23
4.2.2.1Contract Progress Schedule (AF 3064)23
4.3Status Reporting24
4.3.1Reporting Requirements for Firm Fixed Price (FFP)24
4.4Meeting and Conference Requirements24
4.4.1Meeting/Teleconference Support24
4.4.2Red Zone Meeting25
4.4.3Senior Advisory Group (SAG) and Senior Executive Review Group (SERG)25
4.5Contractor Documentation25
4.6Notification Requirements27
4.7Permits28
4.8Photo Documentation28
4.10Site Access Badges29
4.11Worksite Activities and Coordination31
4.11.1Coordination of Activities31
4.11.2Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting31
4.11.3Recording and Preserving Historical and Archaeological Finds38
4.12Project Data/Project Deliverables38
4.12.1Protecting Unclassified DoD Data38
4.12.2Security Breach Notification38
4.12.3Data Collaboration Site38
4.13Health and Safety Plan (HSP) or (APP)39
4.14Quality System Plan (QSP)39
4.15Technical Plans and Reports39
4.15.1Construction Work Plan39
4.15.2Technical Reports39
4.15.3Environmental Protection Plan (EPP)40
5.0PROSECUTING THE WORK40
5.1Site Work42
5.1.1Conservation42
5.1.2Site Preparation42
5.1.3Demolition44
5.2Construction Operation Services45
5.2.1Construction45
5.2.2Inspections46
5.3Demobilization50
5.4Emergency Response50
5.5Maintenance and Repair50
5.6Ordnance Removal and Support50
5.7Security Requirements:50
5.8GENERAL SAFETY REQUIREMENTS50
5.9GENERATED REFUSE54
6.0FACILITY CONSTRUCTION PROJECT DELIVERY METHODS55
6.1Design Build (D-B)55
6.1.1Designers of Record (DOR)/Design Project Manager (PM)56
6.1.2Contractor Design Requirements after Award56
6.1.3User Requirements Design Meeting58
6.1.4Geotechnical/Hazardous Material Survey Requirements and Responsibilities.59
6.1.4.1Soil Survey Requirements and Responsibilities for Contractor.59
6.1.5General Design Requirements61
6.1.6Design Review71
6.2Design-Bid-Build (D-B-B)73
7.0ADDITIONAL REQUIREMENTS73
7.1Types of Projects/Work73
7.1.1Military Family Housing73
7.1.2Fueling System Projects73
7.1.3Range Construction73
7.1.4Pavement Systems (Airfield and Non-airfield)73
7.1.5Renovations (including historic buildings)73
7.1.6Construction of Classified or Highly Secure Facilities73
7.2As-Built Documentation73
POINTS OF CONTACT (POCs)76
Attachments:77
Appendix ADescription of Work77
Appendix BMaps, Drawings, and Other Project Specifics77

1.0 SCOPE

A. This is a Design-Build project to demo, repair, and restore interior and exterior elements. The project is comprised of demolition and reconstruction on land and water on Tyndall AFB, and the related disciplines of work as specific tasks in Scope of Work (See Appendix A for supporting documentation). The Design-Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW).

This project shall be broken into three phases. There shall be a design/permitting phase, and a construction phase for both the covered docks and the uncovered docks. Each phase shall have a separate Notice to Proceed (NTP).

B. The Contractor shall be responsible for all professional services, A/E design, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the tasks defined by the SOW, including the disposal of all resulting waste materials and project clean up. The performed tasks shall be based on the project description, other data furnished in this SOW, and information covered during kick-off meeting.

C. Ancillary items: Providing necessary support to the primary activities or operation of an organization, institution, industry, or system. An example of ancillary item: Lighting controls, but is not limited to the following: switches, motions sensors, and dimmers, ballasts, emergency backup controls, etc. An incompatible dimmer or electronic equipment replacement to support a conversion from Fluorescent to LEDS lights would fit the ancillary item description. Another example is Pump controls but is not limited to the following: Starters, on and off switches, logic controllers. This is all support equipment to ensure the task is completed. Roofs: All required items required by regulations code to complete the installation of a roof system such as detection, fire protections, etc. All of these items must result in a complete and usable product at completion of the project to ensure all the previous functionality was provided in the new design.

D. This SOW sets forth the requirements for Design/Build (DB) contract site-specific design and construction effort to remove, repair and restore interior and exterior elements and related infrastructure within an area on Tyndall AFB, Florida.

E. See Appendix A & B for Supporting Documentation.

1.1 General Requirements

A. Applicable provisions of the Contract Clauses in the contract will govern work under each section of the specifications.

B. This project has an estimated period of performance from the first Notification to Proceed (NTP) through completion and turnover of the facility back to the Government for mission operations of 360 calendar days.

C. Proposal Documents: The contractor shall complete the proposal schedule included in the solicitation and include the completed schedule with the submitted proposal documents.

D. Measurements: The GC is required to validate dimensions and quantities. The quantities are listed as approximations and GC field measurements and quaintly verification should be used for bidding package.

E. Field Changes:

a. Field Changes: The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the Contracting Officer (CO) prior to execution. Only the CO may authorize field changes or deviations from the SOW.

b. No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether or not acting within the limits of his authority, or any other representatives of the Government, shall constitute a change order under the “Changes” clause of this contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting Officer.

F. Job Start Meeting: A job start meeting shall be accomplished with the Contractor, Contracting Officer, Civil Engineering (CE), and user upon acceptance of the 65%, or 95% design submission. The meeting objective is to review project details, determine design delivery dates and anticipated construction start date, security procedures for site, dumpster locations, and any applicable requirements during construction. The Contractor shall visit the job site to verify location, conditions, and dimensions prior to starting work.

G. Pre-Construction Meeting: A preconstruction meeting shall be held when all the design has reached the Issued For Construction (IFC) stage and all preconstruction submittals have been approved. The contractor Quality Control Manager, Site Safety Officer, and Superintendent shall be required to attend. This meeting will address all items specific to the project to include access, safety, and environmental needs.

H. Facility Occupancy: The facility covered by this contract is currently unoccupied and non-functional. During performance of this contract, non-work areas will remain functional to normal base activities. The Contractor is responsible for diverting and restricting pedestrian and vehicle traffic if required for any reason for the duration of the performance period.

I. Bulletin Board: Immediately upon mobilization, the Contractor shall provide a bulletin board not less than 36 by 48 inches (915 by 1220 mm) in size for displaying various documents required within the contract. The bulletin board shall be located at the project site in a conspicuous place easily accessible to all employees. All documents posted shall be legible and replaced as needed when unreadable. The board shall be displayed until the work is completed whereby the Contractor shall remove the board and remain the property of the Contractor. The contents of the board shall include, but not limited to, the following:

a. Contractor’s company name

b. Project name

c. MPLS number

d. Superintendent’s name and a 24 hour available response phone number

e. Equal Employment Opportunity poster

f. Wage determination

g. Wage Rate Information poster.

h. Other documents as needed or required.

J. Employee Parking: Contractor employees shall park privately owned vehicles in an area designated by CES and approved by the CO at the public parking area near the work site.

K. Job Site Tools and Equipment: All hand tools and equipment shall be maintained in good working conditions and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.

L. Field Measurements: The Contractor shall be required to make his/her own field investigations to verify existing conditions, dimensions and other information shown on Government available non-verified furnished reference drawings, solicitation documents and construction documents. Deviations, errors, or omissions in the government supplied reference materials or the design team’s construction documents shall be identified and addressed by the contractor during the design phase of the contract. They shall be annotated on the respective contract documents as well as on a consolidated register that will be made available to the government for simplified identification and review.

M. Notification Requirements: The Contractor shall notify the Government a minimum of ten (10) days in advance of each mobilization. The Contractor is required to notify the CO and Government Project Manager of critical issues that may affect the contract performance and/or human health and the environment. For critical issues pertaining to human health and the environment, the Contractor shall immediately notify the CO and stop work. Work shall only resume at the direction of the CO following resolution of the issue.

N. On-Site Field Oversight: The Contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of the construction period for the contract. It is the responsibility of the Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.

O. Federal Holidays:

a. The standard Federal legal holidays are observed:

1. New Year’s Day

2. Birthday of Martin Luther King, Jr.

3. Washington’s Birthday

4. Memorial Day

5. Juneteenth

6. Independence Day

7. Labor Day

8. Columbus Day

9. Veterans Day

10. Thanksgiving Day

11. Christmas Day

b. Any of the holidays falling on Saturday will be observed on preceding Friday; holidays falling on Sunday will be observed on the following Monday. In addition, the Government may dictate the work day before or the work day after an observed holiday as a “Family Day.”

c. The Contractor should not perform work on observed holidays, Wing Down Days, Wing Safety Days or Family Days unless authorized by the Contracting Officer for the CO. In the event work is authorized on observed holidays, the Contractor shall pay all applicable overtime and/or holiday pay rates required by law.

P. Working Hours: The normal duty hours of the facility are from 7:00 AM to 5:00 PM, Monday thru Friday excluding Federal Holidays. All work shall be performed during normal duty hours. All other hours to include weekend and holidays shall be requested through the CO for approval. This request shall be submitted no less than three (3) workdays prior to the time requested.

Q. Availability and Use of Utility Services: The contractor should plan on having an offsite office location. The government does not guarantee office space will be provided. The Government does not guarantee utilities will be provided for office space. The use of a generator and porta toilets may be required of office space is provided. To install and office space and laydown yard will require an 813 permit determination and could take up to 60 days to obtain the permit.

R. Sanitation: The Contractor shall provide and maintain within the construction area minimum field-type sanitary facilities approved by the CO. Government toilet facilities will not be available to Contractor's personnel.

S. Clean Up: At the end of each working day the Contractor shall clean up the work site by the removal of all construction debris, waste materials, packaging material and the like. If the before mentioned items could become airborne they shall be placed in refuse containers immediately. Clean up of the work site shall include the construction area(s), construction office area(s), material storage area (s), parking and eating area(s), and any other area(s) affected by the construction process. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily. Materials resulting from demolition activities which are salvageable shall be stored within the work area or at a supplemental storage area. Stored material not in trailers, whether new or salvaged, shall be neatly stacked when stored in an approved location.

T. Contractor’s Management and Use of Electromagnetic Emission Devices on Base: (Electromagnetic emission devices include: Radio/Radar Transmitters; Navigational Aids/Instrumentations; Signaling, Intrusion Detecting, and Identification Devices; Mobile and Fixed Business Radio Communications Equipment; and MARS, CBs, and Amateur Radio Stations.) The Contractor shall comply with the Air Force Military Training Center (AFMTC) Regulation 700-14, Jul 89.

U. Preparation of Progress Schedules and Reports: The reports contemplated by FAR Clause, 52.236-15, Schedules for Construction Contracts, shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. Contract Schedules and Reports shall run from Monday through Sunday and be submitted to the CO per table of deliverables located in 4.0A Table 1 - Table of Deliverables.

V. Deteriorated Construction And Finish

a. Authority: The QA Inspector will be the governing authority in determining if existing construction and finishes are deteriorated and require repair and/or replacement.

W. Contractor Storage/Staging Area

a. Operations and Storage Approval: Notwithstanding Contract FAR Clause, FAR 52.236-10, Operations and Storage Areas, subject to approval by the CO and in turn, availability and need, a storage/staging area may be provided at the subject project site. If project site space is not available, then offsite storage may be required. The work site is outside of the controlled perimeter of Tyndall AFB. Security of material is the responsibility of the contractor.

b. Utility ‘tie-ins’, where available, are the Contractor’s responsibility. See 1.1 , Section Q. Availability and Use of Utility Services for additional information.

c. Storage Area Clean Up: Weekly discard trash and debris in the Contractor’s containers (dumpsters). Do not allow debris to accumulate. At work completion, clean the storage area. This area must be free of any materials, trash or debris before receipt of final payment.

d. In areas of high visibility, the job site construction fence shall have a screen fabric material applied to the fence fabric in order to block the view during the construction phase. The CO will make the determination at the pre-construction meeting if the subject project will require a screened fence or not. Remove fence upon completion. Rehabilitate disturbed turfs and grass and if reseeding is required use Bermuda grass.

X. Hazardous component abatement for materials such as asbestos, lead-based paint, PCBs, and other hazardous materials shall be the responsibility of the Contractor. Abatement of mold resulting from water damaged materials shall be the responsibility of the Contractor.

Y. The duration of days is considered calendar days unless otherwise noted.

Z. COVID-19 Requirements - During the COVID-19 pandemic it is vital to Tyndall AFB’s Mission that the Contractor adhere to all Tyndall AFB Covid-19 directives to mitigate virus transmission. The contractor shall be responsible for the following: follow CDC guide lines, setting up teleconference meetings, wearing mask and social distancing when entering a government facility, the screening of their employees, and reporting COVID-19 cases to the 325th CONS and 325th CES project manage (PM). As Covid-19 directives are living documents, it is the Contractor’s responsibility to be informed and follow the most recent published directive.

AA. Project Signage: As required per the FAR.

a. As required, a job sign shall be required at the project site. The CO or the Government Inspector will make a determination based on cost and visibility. The sign shall indicate the Contractor’s company name, project name and MPLS number, superintendent’s name and a 24 hour available response phone number. The size of the sign shall be 4’ x 8’ x ¾” thick plywood board mounted to a 2x4 wood frame and diagonal braces. The wood frame shall be supported on 4x4 wood supports and be mounted to the ground in concrete footings. Background color shall be in accordance with Federal Standard 595a color/number BROWN/10080 (Gloss). The color of the lettering shall be WHITE/17875 (gloss) with Arial font. With base approval the background color shall be white with black lettering - Helvetica font.

2.0 APPLICABLE DOCUMENTS

A. The Contractor shall identify and comply with all applicable federal, state, and local laws; statutes; Executive Orders; Department of Defense/Air Force manuals, handbooks, regulations, guidance, and policies. The contractor shall comply with the National Institute of Building Sciences’ Whole Building Design Guide Construction Criteria Base (CCB) Unified Facility Criteria (UFC) 3-600-01 and all of the related libraries. The primary criteria are the Air Force Criteria from the Documents Library, but other agency criteria may be directed for use, depending on the customer agency for a particular TO. The Unified Facilities Guide Specifications (UFGS) is the mandatory starting point for all specifications, and shall not be deleted, materially modified, or made less stringent without Government approval. It is the contractor’s responsibility to identify and comply with all applicable requirements. It shall be the contractor’s responsibility as the Designer of Record (DOR) to identify any design/construction criteria waivers that are warranted for the Project and to accomplish all necessary coordination activities necessary to obtain approval of these proposed waivers through the Contracting Officer (CO), and/or Project Manager (PM).

B. In addition, the contractor shall refer to and comply with the current versions of the Department of Defense Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and The United States Air Force Construction Management Implementation Guide as well as the latest version of The USAF Project Manager’s Guide to Design and Construction. Base-specific documents are identified in the attached appendices.

C. The Contractor and Design Team shall adhere to the following guidance during design and construction phase(s) of this project: Those sections of the Southern Standard Building Codes not incorporated in the UBC/International Building Code (IBC) for our respective area, International Concrete Repair Institute (ICRI) Guidelines, Air Force Standards, Department of Defense (DOD) Directives, Florida State Statutes, and the Tyndall AFB Facility Excellence Plan (Base Regulations), Occupational Safety and Health Administration (OSHA) Requirements, Department of Environmental Protection (DEP) Regulations, Environmental Protection Agency (EPA) Regulations, and ABA Accessibility Compliance Requirements.

D. The Contractor shall design and construct new facilities and related site work to meet the requirements of UFC 1-200-02 and to achieve Third Party certification under GBCI Guiding Principles Assessment or GBI Guiding Principles Compliance. Refer to Part 18 SUSTAINABLE DESIGN of this specification for specific requirements and criteria.

E. In addition to adhering to the previous guidance, the Contractor shall review and adhere to the most recent version of the following code criteria as applicable at start of the design phase:

a. UFC 1-200-01The DoD Building Code
b. UFC 1-200-02High Performance and Sustainable Building Requirements
c. UFC 1-300-02Unified Facilities Guide Specifications (UFGS) Standard
d. UFC 1-300-07ADesign Build Technical Requirements
e. UFC 1-300-08Criteria for Transfer and Acceptance of DoD Real Property
f. UFC 3-101-01Architecture
g. UFC 3-110-03Roofing
h. UFC 3-110-04Roofing Maintenance and Repair
i. UFC 3-120-01Design: Sign Standards
j. UFC 3-120-10Interior Design
k. UFC 3-190-06Protective Coatings and Paints
l. UFC 3-201-01Civil Engineering
m. UFC 3-201-02Landscape Architecture
n. UFC 3-210-10Low Impact Development
o. UFC 3-220-01Geotechnical Engineering
p. UFC 3-220-05Dewatering and Groundwater Control
q. UFC 3-230-01Water Storage and Distribution
r. UFC 3-230-10AWater Supply, Water Distribution
s. UFC 3-240-01Wastewater Collection and Treatment
t. UFC 3-250-01Pavement Design for Roads and Parking Areas
u. UFC 3-250-03Standard Practice Manual for Flexible Pavements
v. UFC 3-250-04Standard Practice for Concrete Pavements
w. UFC 3-250-08FASealing Joints and Cracks
x. UFC 3-250-11Soil Stabilization for Pavements
y. UFC 3-260-02Pavement Design for Roads, Streets, Walks, and OpenStorage Areas
z. UFC 3-300-07ADesign Build Technical Requirements
aa. UFC 3-301-01Structural Engineering
ab. UFC 3-310-04Seismic Design for Buildings
ac. UFC 3-400-02Design: Engineering Weather Data
ad. UFC 3-401-01Mechanical Engineering
ae. UFC 3-410-01Heating, Ventilating, and Air Conditioning
af. UFC 3-410-02Direct Digital Control for HVAC
ag. UFC 3-410-04Industrial Ventilation
ah. UFC 3-420-01Plumbing Systems
ai. UFC 3-420-02FACompressed Air
aj. UFC 3-430-09Exterior Mechanical Utility Distribution
ak. UFC 3-450-01Noise and Vibration Control
al. UFC 3-501-01Electrical Engineering
am. UFC 3-520-01Interior Electrical Systems
an. UFC 3-530-01Interior and Exterior Lighting and Controls
ao. UFC 3-550-01Exterior Electrical Power Distribution
ap. UFC 3-560-01Electrical Safety O&M
aq. UFC 3-570-01Cathodic Protection
ar. UFC 3-570-06Operation and Maintenance: Cathodic Protection Systems
as. UFC 3-575-01Lightning and Static Electricity Protection
at. UFC 3-580-01Telecommunications Interior Infrastructure
au. UFC 3-600-01Fire Protection Engineering for Facilities
av. UFC 3-701-01DoD Facilities Pricing Guide, with Change 2; 2019
aw. UFC 3-730-01Programming Cost Estimates for Military Construction
ax. UFC 3-740-05Handbook: Construction Cost Estimating
ay. UFC 4-010-01DOD Minimum Antiterrorism Standards for Buildings
az. UFC 4-010-05Sensitive Compartmented Information Facilities
ba. UFC 4-010-06Cybersecurity of Facility-Related Control Systems
bb. UFC 4-020-01DoD Security Engineering Facilities Planning Manual
bc. UFC 4-021-01Mass Notification Systems
bd. UFC 4-021-02Electronic Security Systems
be. UFC 4-211-01Aircraft Maintenance Hangars
bf. UFC 4-214-03Central Vehicle Wash Facilities
bg. USAF BIMMinimum Requirements Version 2.1
bh. AASHTOA Policy on Geometric Design of Highways and Streets
bi. ABASArchitectural Barriers Act Standards; The ABA
may be found at https://www.access-board.gov/guidelines-
and-standards/buildings-and-sites/about-the-aba-
standards/aba-standards
bj. AFDSAir Force Design Guide
bk. AFGM 2018-32-01Civil Engineer Control Systems Cybersecurity
bl. AFI 32-1020Planning And Programming Built Infrastructure Projects
bm. AFI 32-1024Standard Facility Requirements
bn. AFI 32-1063Electrical Power Systems
bo. AFI 32-1064Electrical Safe Practices
bp. AFI 32-1065Grounding System
www.wbdg.org › FFC › AFI › afi_32_1065_2017
bq. AFI 32-1067Water Systems
br. AFI 32-1068Heating Systems and Unfired Pressure Vessels
bs. AFI 32-1069Gas Supply and Distribution
bt. AFMAN 91-203Air Force Occupational Safety, Fire and Health Standards
bu. AFMAN 32-1084Facility Requirements Standards
bv. ANSI C2National Electric Safety Code
bw. ASCE 7-10Wind Loads
bx. ASHRAE 55Thermal Environmental Conditions for Human Occupancy
by. ASHRAE 62.1Ventilation for Acceptable Indoor Air Quality
bz. ASHRAE 90.1Energy Standard for Bldgs. Except Low-Rise Residential
ca. ASHRAE 100Energy Conservation in Existing Buildings
cb. ASHRAE 111Testing, Adjusting, and Balancing of Building HVAC
Systems
cc. ASHRAE 180Inspection & Maintenance Commercial Bldg. HVAC
Systems
cd. ASHRAE 189.1Standard for the Design of High-Performance Green
Buildings
ce. ASHRAE 202Commissioning Process for Buildings and Systems
cf. ASHRAE Guide 4Prep of Operating and Maintenance Documentation
cg. ECB 2018-11Control System Cybersecurity Coordination Requirement
ch. EISAEnergy Independence and Security Act of 2007
ci. EM 385-1-1USACE Safety and Health Requirements Manual
cj. EPAct 2005Energy Policy Act of 2005
ck. FC 4-218-03FAir Force Criteria for Precision Measurement EquipmentLaboratory Design and Construction
cl. FARFederal Acquisition Regulations
cm. FS 553Florida Building Code
cn. IBCInternational Building Code
co. IESIlluminating Engineering Society Lighting Handbook
cp. IFGSInternational Fuel Gas Code
cq. IMCInternational Mechanical Code
cr. IPCInternational Plumbing Code
cs. MIL-HDBK-1190MILITARY HANDBOOK: FACILITY PLANNING AND
DESIGN GUIDE

ct. NACE SP-0169

cu. NACE SP-0185

cv. NACE SP-0286

cw. NBIMS US V3National BIM Standard US Version 3
cx. NEBBStandards for Whole Building Systems Commissioning
cy. NECNational Electrical Code, current edition
cz. NEMANational Electrical Manufacturer's Association
da. NESCNational Electrical Safety Code current edition
db. NFPA 13Standard for the Installation of Sprinkler Systems
dc. NFPA 24Installation of Private Fire Service Mains and Their
Appurtenances
dd. NFPA 70National Electric Code
de. NFPA 72National Fire Alarm Code
df. NFPA 90AStandard for the Installation of Heating and Air
Conditioning Systems
dg. NFPA 101Life Safety Code
dh. NFPA 1141Standard for Fire Protection Infrastructure for Land
Development in Wildland, Rural, and Suburban Areas
di. NPDESNational Pollutant Discharge Elimination System
http://www.dep.state.fl.us/water/stormwater/npdes/construction3.htm

dj. SMACNA Guides

Sheet Metal & Air Conditioning
Contractors’ NationalAssoc.
dk. TAFB FEPTAFB Facility Excellence Plan
dl. TAFB IFSTAFB Installation Facility Standard
https://www.tyndallifs.com/
dm. TM 5-683Facilities Engineering Electrical Interior Facilities
dn. TM 5-684Facilities Engineering - Electrical Exterior
do. USAF BIMMinimum Requirements Version 2.1
dp. UFASUniform Federal Accessibility Standards
dq. UFGS 23 09 00Instrumentation and Control for HVAC
dr. UFGS 23 09 13Instrumentation and Control Devices for HVAC

ds. UFGS 23 09 23.02

BACnet Direct Digital Control for HVAC and Other
Building Control Systems
dt. UFGS 23 09 93Sequences of Operations for HVAC Controls
du. UFGS 25 05 11Cybersecurity for Facility-Related Control Systems
dv. UFGS 23 08 10Utility Monitoring and Control System Testing
dw. UFGS 25 10 10Utility Monitoring and Control System (UMCS) Front End
and Integration

F. Miscellaneous

a. AFCEC AGRAM 17-01 Change to AF New Construction and Major Renovation Certification Requirements

b. Air Force Pamphlet 91-210 (Contract Safety)

c. Air Force Systems Security Instruction 7700 - Communications and Information - Emission Security

d. Air Force Systems Security Instruction 7702 - Communications and Information - Emission Security

e. Air Force Sustainable Design and Development (SDD) Implementation Guidance

f. Tyndall Mass Notification System Messages

g. Tyndall Rebuild Facility Related Control Systems (FRCS) Technology Summary –Appendix L –22 Sept 2021

h. Memorandum For ALMAJCOM-FOA-DRU, Mandatory Use Policy for Air Force Carpet Acquisitions within the Contiguous U.S.

i. Draft Rule Amendments of the Environmental Resource Permitting (ERP) Program in the Northwest District, Applicant's Handbook Volume I & II, http://www.dep.state.fl.us/water/wetlands/erp/rules/draft nw.htm.

j. Recommended Standards for Wastewater Facilities (Ten States Standards)

k. Chapter 62-555 FAC General Permit of Construction of Water Main Extension for Public Water System

l. Chapter 62-600 of the Florida Administrative Code, Public Drinking Water Distribution System and Domestic Wastewater Facilities

m. Chapter 62-604 FAC Collection Systems and Transmission Facilities of the Florida Administrative Code, Domestic Wastewater Facilities and the Wastewater Permit checklist.

n. Manual of Practice No. FD-4 Design of Wastewater and Stormwater Pumping Stations.

o. Manual of Practice No. FD-5 Gravity Sanitary Sewer Design and Construction.

p. USACE ETL 1110-3-466 Selection and Design of Oil/Water Separators at Army Facilities, August 1994

q. USACE Designing Coalescing Oil/Water Separators for Use at Army Washracks, December 2000

r. GCEC MANUAL OF STANDARDS AND SPECIFICATIONS FOR WATER MAIN CONSTRUCTION FOR TYNDALL AFB SYSTEM

s. Guiding Principles for Sustainable Federal Buildings and Associated Installations

t. Illuminating Engineering Society of North America (Handbook)

u. Florida Fish and Wildlife Commission; Sea Turtle Lighting Guidelines - Chapter 62B-55 Model Lighting Ordinance for Marine Turtle Protection.

v. E.O. 13834 Efficient Federal Operations

G. Lightning Protection Requirement: Lightning Protection System (LPS) shall be designed and installed IAW the following references:

a. AFI 32-1065Grounding System
www.wbdg.org › FFC › AFI › afi_32_1065_2017
b. NFPA 70National Electric Code
c. NFPA 780Standard for the installation of Lightning Protection System
d. UFC 3-575-01Lightning and Static Electricity Protection System
e. UL 96Lightning Protection Components
f. UL 96AInstallation Requirements for Lightning Protection System
g. UL 467Grounding and Bonding Equipment

F. Security Requirements:

a. MIL-HDBK-1013:DOD Military Handbook Design Guidelines for Physical
Security of Facilities
b. AFI 31-101:Air Force Instruction 31-101: The Air Force Installation
Security Program
c. DOD 5200.1.RDepartment of Defense 5200.1.R: Information Security
Program Construction Standards.
d. ICD-ICS-705Tech Spec
e. UFC 4-010-01Unified Facilities Criteria Antiterrorism Standards for New
and Existing Facilities
f. UFC 4-010-05Sensitive Compartmented Information Facilities
g. UFC 4-010-06Cybersecurity of Facility-Related Control Systems

G. FAR Case No. 92-54 requires the Solicitation Package for all construction projects to reflect the government's preference for "acquisition of environmentally sound and energy efficient products and services, and an affirmative procurement program favoring items containing the maximum practicable content of recovered materials".

H. DOD Information

a. Department of Defense Manual 5200.01, Volume 1; DoD Information Security Program: Overview, Classification, and Declassification; 2012

b. Department of Defense Manual 5200.01, Volume 2; DoD Information Security Program: Marking of Classified Information; 2013

c. Department of Defense Manual 5200.01, Volume 3; DoD Information Security Program: Protection of Classified Information; 2013

d. Department of Defense Manual 5200.01, Volume 4; DoD Information Security Program: Controlled Unclassified Information (CUI); with Change 1 2018

I. DOD Information J. Facilities Department of K. Federal Green Construction Guide for specifiers. This guide can be found at: http://www.wbdg.org/design/greenspec.php

L. Non-ERP Soil Management Guidelines, May 2020

M. The Contractor shall perform all work IAW with AFI, ETL, UFC and industry standards. Compliance with AF UFCs is mandatory unless the IFS has more stringent requirements. If the Contractor determines that the work cannot be performed and/or included in the SOW IAW with ETL’s/UFCs or industry standards, the Contractor shall notify the Tyndall AFB POC listed in this document in writing immediately before award of the contract. Otherwise, the Contractor shall be responsible for the required work.

N. All work shall be in compliance with all Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DODI), Department of Defense Directives (DODD), or other higher authority documents as applicable. Many applicable compliance documents are authorized by DoD MIL-STD-3007F, and are available through the Government-sponsored Whole Building Design Guide located at https://www.wbdg.org.

O. If there is a conflict between these codes, regulations specifications, and/or guidance documents, the most stringent requirements shall apply, as determined by the CO through the Request for Information (RFI) process. These listed documents do not relieve the Contractor from complying with other required regulatory documents not listed.

P. The government may take up to 30 days to review design documents. The contractor schedule activity for less days will be overridden by this time frame and will not be considered a delay by the government. The contractor schedule shall reflect the 30 day review time.

3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)

A. Historical architectural and structural construction documents may be available for review, however field verification and documentation of existing conditions and configurations prior to construction is essential. The government takes no responsibility for errors and omissions contained in the reference material and field verification shall be performed by the contractor.

4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS

A. Design submittals 65%, 95%, and 100%, will be routed with an AF Form 3000 and will be reviewed and approved/disapproved within 30 calendar days.

B. No delay damages or time extensions will be allowed for time lost in late or lost submittals. Government review times may take up to 30 days and is not considered a delay for design reviews. The contractor’s schedule shall include time for these 30 day reviews. The official review time starts when the CO acknowledges the receipt of the submittal.

C. Submittals pertaining to environmental issues may take up to 30-45 days for review and approval. Wetland permits may take greater than 60 days to process. Environmental 813 submittals shall include drawings, locates for utilities with depth, size of lines, length of runs, underground or above ground routing, spatial coordinates, duration of the laydown yard or temporary trailer, number of personnel, location of temporary porta toilets, etc. Delays greater than the anticipated days listed herein do not constitute a governmental delay. Contractor will be allotted a no-cost PoP extension for days over and above those listed herein. Contractor must also coordinate permits with United States Army Corps of Engineers (USACE) for work in water areas.

D. All other submittals should be reviewed and approved/disapproved within 10 work days. Submittals will be reviewed for accuracy and relevance to the project and specifications. Material Submittal documents shall be submitted with AF Form 3000, Material Approval Submittal.

E. Submittal documents shall include required forms, reports, drawings, samples, media recordings, manufacturer data, certifications, test reports, equipment warranty information, and the like. Submittal documents shall be submitted by the Contractor to the by CO for approval. All submitted documentation shall become the complete property of the Government. The Contractor shall not purchase, install, or construct any equipment or facility component, for which a submittal is required, without first obtaining an approved signed submittal from the CO. Required submittals shall be listed on AF Form 66, Schedule of Material Submittals, and/or a Submittal Register approved by the CO.

F. Table of Deliverables: Project deliverables shall be as shown in the following 4.0A Table 1 - Table of Deliverables. The dates in the table are hard dates not to be exceeded without CO approval. The deliverables and scheduled activities may be provided or completed early.

G. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.

H. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but have been omitted from the register or marked "N/A."

I. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.

J. Contracting Officer Review will be completed within 30 calendar working days after the date of submission for submittals requiring Government approval.

4.0A Table 1 - Table of Deliverables

Document

Copies
Max Delivery Timeframe
325 CES
325 CONS
Electronic
Hard Copy
Electronic
Hard Copy

Standard Meetings and Reports

Meeting Minutes
1
0
1
0
3 calendar days after each meeting
Progress Schedule(AF 3064 or approved equivalent)
1
0
1
0
5 calendar days after NTP or modification to extend PoP
Progress Report (AF 3065 or approved equivalent)
1
0
1
0
Weekly
3-week Look Ahead report
1
0
1
0
Weekly
Daily Logs - Form 1477 or equiv.
1
0
1
0
NLT 0900 the day following - Daily
HAZMAT Forms 81 and 82
1
1
1
1
10 Days prior to preconstruction meeting
Work Clearance Request (AF Form 103A)
1
1
1
1
10 Days prior to preconstruction meeting
Material Approval (AF Form 3000)
1
0
1
0
At the 100% Final Design
Construction Material Testing Reports
1
0
1
0
As required
Welding/Burn Permit
1
0
1
0
Prior to commencing work
Production or Delivery Problem Report
1
1
1
1
At time of identification
Draft DD1354
1
0
1
0
When request for final inspection is submitted

Work Activities

IMS, WBS and AF 3064/3065
1
0
1
0
15 Days Prior to NTP
Kickoff meeting with all stakeholders
1
0
1
0
5 Days Prior to NTP
Health and Safety Plan (HSP) or (APP)
1
0
1
0
Prior to mobilization
NTP
1
0
1
0
NA
Contractor Site Investigation
1
0
1
0
5 Days from NTP
Design Quality Plan (DQCP) or (DQSP)
1
0
1
0
Prior to Design Starting
Quality Control Pan (QCP) or (QSP)
1
0
1
0
Prior to construction activities
Construction Work Plan (CWP)
1
0
1
0
Prior to construction activities
Site Investigation Memorandum
1
0
1
0
10 Days from NTP

Charrette Meeting

40 Days from NTP

Charrette Meeting Minutes Acceptance and Approval
1
0
1
0
20 Days from 1st Design Submittal
65% Design w/ AF Form 3000
1*
0
1*
0
40 Days from NTP
65% Design Review and Meeting
1
0
1
0
30 Days from 65% Design Submittal
65% Design Resubmittal if submittal was disapproved
1
0
1
0
10 Days from 65% Design Disapproval
65% Design Final Submittal and Approval
1
0
1
0
10 Days from 65% Design Re-Submittal
95% Design w/ AF Form 3000
0
0
0
0
40 Days from NTP or 20 Days 65% Design Approval
95% Design Review and Meeting
1
0
1
0
30 Days from 95% Design Submittal
95% Design Resubmittal if submittal was disapproved
1
0
1
0
10 Days from 95% Design Disapproval
95% Design Final Submittal and Approval
1
0
1
0
10 Days from 95% Design Re-Submittal
100% Design w/ AF Form 3000
1*
0
1*
0
20 Days from 95% Final Design
100% Design Review and Meeting
1
0
1
0
30 Days from 100% Design Submittal
100% Design Resubmittal if submittal was disapproved
1
0
1
0
10 Days from 100% Design Disapproval
100% Design Final Submittal and Approval
1
0
1
0
10 Days from 100% Design Re-Submittal
All Material Submittals
1
0
1
0
At 100% Design Approval or 30 Days from design Approval with CO approval.
Demolition Plan when demolition activities
1
0
1
0
Prior to 100% Design Approval
Environmental Plan (EPP)
1
0
1
0
Prior to 100% Design Approval
Storm Water Pollution Protection Plan (SWPPP)
1
0
1
0
Provided as part of the EPP
Red Line drawings Submitted
1
0
1
0
15 Days prior to Start Work
Draft Phasing Plan
1
0
1
0
10 Days prior to Start Work
Final Phasing Plan
1
0
1
0
5 Days prior to Start Work
Mobilization of Contractor
0
0
0
0
After 100% Design Approval or before with CO approval
Job Start Meeting
1
0
1
0
After 100% Design Approval or before with CO approval

Implementation of the Design

100 to 200 Days

Red Zone Meeting
1
0
1
0
60 Days Prior to Beneficial Occupancy Date (BOD)
Pre-Final Inspection
1
0
1
0
At end of Implementation
Pre-Final Inspection Report
1
0
1
0
5 Days prior to Final Inspection
Operations & Maintenance Manuals
1
1
1
1
5 Days prior to Final Inspection
HAZMAT Form 83
1
0
1
0
Prior to Final Inspection
Final Inspection
1
0
1
0
10 Days after Pre-Inspection
Final Inspection Report
1
0
1
0
5 Days After Final Inspection
O&M’s Review
1*
1
1*
0
5 Days After Final Inspection
As-Built Design Documents
1
0
1
0
5 Days After Final Inspection
As-Built Design Drawings
1*
0
1*
0
5 Days After Final Inspection
As Built Review Meeting
1
1
1
1
10 Days After Final Inspection
As Built Review Comments
1
0
1
0
15 Days After Final Inspection
O&M’s Acceptance
1*
1
1*
0
15 Days After Final Inspection
As Built Comments Acceptance
1
0
1
0
20 Days After Final Inspection
As Built Approval
1
0
1
0
20 Days After Final Inspection
Transfer & Acceptance of Military Real Property (DD 1354)
1
1
1
0
5 Days after Final Design Approval
O&M’s to user
1
0
1
0
10 Days after Final Design Approval
User training
1*
1
1*
0
15 Days after Final Design Approval

*Both Autodesk AutoCAD and Adobe Acrobat versions of drawings are required

K. Electronic copies of all design deliverable documents shall be provided on CD or DVD discs, formatted for use by the latest software version, and compatible with the Government’s version of Microsoft Word, Excel, PowerPoint, Access, Outlook, the Adobe family of products, the Autodesk family of applications, the ANSYS family of applications, or other software platform as appropriate and as determined and directed by the CO. Whenever possible, the electronic files given to the Government should be compatible with at least one software program application listed on the Air Force Evaluated Products List (EPL) or the Defense Information Systems Agency (DISA) Approved Products List (APL). For any submitted documents converted to one of the above formats from another software program, the Contractor shall also submit the electronic document file from the software program originally creating it, along with a statement describing what creating software program and version was used, as well as any programs used to convert files from one format to another. Submitted electronic files shall be unlocked and fully editable.

L. Builder Template

a. A builder template will be provided to the contractor to complete for real property items that were installed per the scope of work.

4.1 Work Breakdown Structure (WBS)

A 3064 or equivalent spreadsheet is used for the WBS. The task number, start and stop dates, Value for the task will be provided.

4.2 Schedule and Planning Requirements

A. See Section General Requirements

4.2.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)

A. Provided as needed.

4.2.2 Integrated Master Schedule (IMS)

4.2.2.1 Contract Progress Schedule (AF 3064)

A. The Contractor shall submit a signed AF 3064, Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance as described in the 4.0A Table 1 - Table of Deliverables. The line items, associated project percentages, and dates shall accurately depict the planned work to be performed.

B. A template spreadsheet may be provided by the government to use for progress reporting.

C. The progress schedule shall be signed by CE recommending approval and approved by the CO.

4.2.2.2 Contract Progress Report (AF 3065)

1. The Contractor shall submit AF 3065 as described in 4.0A Table 1 - Table of Deliverables. This report shall be signed by the Contractor’s on-site representative in the Remarks section of the AF 3065. The work elements and percentages of the total job identified on the AF 3065 shall be identical to the work elements and percentages on the AF 3064. The Contractor shall obtain either the QA Inspector or the Government contract inspector’s acceptance by signature of the actual reported progress prior to submission to the CO. Additionally, the Contractor shall submit the updated AF 3064 as an attachment to the AF 3065.

4.2.2.3 Submitting Schedules and Reports

1. Contract Progress Report. Contract Schedules and Reports shall run from Monday through Sunday and be submitted to the CO by Tuesday of the following week. Contractor will prepare reports covering activities for days work and give one to the Government Inspector for each week of work even if there was no work accomplished that week. The weekly report may be turned in for each week at the end of the week when construction begins.

A 3064/3064/schedule spreadsheet may be used to coordinate progress reporting. A example spreadsheet can be provided.

4.3 Status Reporting

4.3.1Reporting Requirements for Firm Fixed Price (FFP)
4.3.1.1Contractor’s Progress, Status, and Management Report (CPSMR)

A. A 3064 is used for this project.

4.4 Meeting and Conference Requirements

A. Upon award the Contractor shall attend the following meetings at a minimum: Project Start and Pre-Construction Job Start 65%, 95% Design Review, 100% Design Review, Corrected Design Review, Incremental Site Inspection (as needed), Test and Balance (as needed), Commissioning (as needed), Pre-Final Inspection, Final Inspection, and other meetings (as needed). The Contractor shall participate in other meetings as needed to facilitate the project’s work, and as required by the CO.

B. Job Start Meeting

a. The Contractor shall attend a Project Job Start at TAFB. The Contractor shall review the most updated versions of codes, standards, and policies applicable to this project prior to the meeting. These documents should include TAFB design standards, DoD Unified Facility Criteria, and the Florida Building Code, among others including those referenced in this document. The Contractor shall, at the Project Kickoff and Pre-Construction Meeting, submit a memorandum stating that applicable codes, standards, and policies were reviewed; stating which documents (title, revision number, date, source, etc.) were reviewed, and listing any RFI’s that resulted from the review.

b. The purpose of these meetings is to introduce project stakeholders, clarify the scope of work, review TAFB policies, and communicate information pertinent to the project. Within the time listed in 4.0A Table 1 - Table of Deliverables of the meeting, the Contractor shall submit minutes for approval.

4.4.1 Meeting/Teleconference Support

1. Upon award the Contractor shall attend the following meetings at a minimum: Project Job Start, Charrette, and Pre-Construction Job Start, 65%, 95% Design Review, 100% Design Review, Corrected Design Review, Incremental Site Inspection (as needed), Test and Balance (as needed), Commissioning (as needed), Red Zone meetings, Pre-Final Inspection, Final Inspection, and other meetings (as needed). The Contractor shall participate in other meetings as needed to facilitate the project’s work, and as required by the CO.

Contractor will be responsible to take and distribute meeting minutes to all those in attendance.

Minutes shall be distributed to attendees for review, comment, and correction the time listed in 4.0A Table 1 - Table of Deliverables of meeting events.

Unedited digital copies of all Contractor recordings shall be provided to the Government within 3 days of the recording date.

4.4.2 Red Zone Meeting

A. Construction Red Zone Activities

Once construction is 80% complete for each facility or 60 days prior to beneficial Occupancy Date (BOD), the Contractor shall conduct weekly Red Zone Meetings instead of the regular weekly Project Update meetings. Red Zone Meetings shall cover not only the construction progress, but also project close out activities, including commissioning activities, training activities, and the preparation of project close out documents. Meeting requirements and Attendees for the QA Inspector scheduled and conducted meeting can be found at P:\Projects\Templates\Red Zone Briefing.

B. Builder Template

A builder template will be provided to the contractor to complete for real property items that were installed per the scope of work. The template can be found at P:\Projects\Templates\Red Zone Briefing.

4.4.3 Senior Advisory Group (SAG) and Senior Executive Review Group (SERG)

A. Not required for this project.

4.5 Contractor Documentation

A. The Contractor shall also create and submit for approval a 4.0A Table 1 - Table of Deliverables, which includes the documents required by the approved Submittal Register.