Attachment 01 SOW EHRM - Infra Upgrades - Loch Raven.pdf

PDF 704 KB Posted

Attached to
Y1DA--512-22-710 EHRM Infrastructure Upgrades - Loch Raven MD - Construction (VA-24-00060549)
Solicitation number
36C77624R0114_1
Issued by

About this file

This is a Construction Scope of Work for EHRM Infrastructure Upgrades at VA Loch Raven Health Care System in Baltimore, MD (Project #512-22-710). The contractor must furnish labor, materials, and equipment to prepare sites for installation of IT Tower Additions, new data cabling, fiber optic cabling, and TR equipment for Electronic Health Record deployment.

The project has an estimated construction cost between $10-20 million with a performance period of 540 calendar days after Notice to Proceed. Work must be completed during normal hours (0730-1600) unless otherwise approved, with Acela Architects + Engineers providing Construction Period Services. Key requirements include developing an Infection Control Risk Assessment plan, minimizing disruptions to veterans/staff, fire caulking all wall/ceiling penetrations, and verifying field conditions through pre-bid site walks. The contract will remain open until after the facility's go-live date to accommodate any additional work identified by Cerner and the Change Leadership Team. The A/E must review contractor RFIs and change order proposals, providing detailed cost breakdowns and independent estimates for both additions and deductions.

View the file

Other files

File Type Posted
36C77624R0114 0002.pdf PDF
Attachment 01 Site Visit Sign In Log - EHRM 20241211.pdf PDF
Attachment 02 Site Visit Agenda - Loch Raven.doc DOC document
Attachment 7 - EHRM Infra Upgrade Drawings 1 of 2 Dated 12.10.24.pdf PDF
Attachment 9 - Structural Appendix - PEC Report.pdf PDF
Attachment 8 - EHRM Infra Upgrade Drawings 2 of 2 Dated 12.10.24.pdf PDF
36C77624R0114 0001.docx DOCX document
Attachment 11 SOW - Att 10 - CIVIL PART 1A - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 03 - SOW - Specs - 2 of 4.pdf PDF
Attachment 18 SOW - Att 17 - CIVIL PART 3 - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 24 SOW - Att 23 - Structural Appdx PEC Report - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 23 SOW - Att 22 - TECH Docs - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 28 Loch Raven VA Medical Center Visitor Guide - Campus Map.pdf PDF
Attachment 21 SOW - Att 20 - Gen Info Docs - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 05 - SOW - Specs - 4 of 4.pdf PDF
Attachment 22 SOW - Att 21 - STRUCT Docs - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 12 SOW - Att 11 - CIVIL PART 1B - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 25 DBA Wage Rate 11.21.24.pdf PDF
Attachment 27 Site Visit Instructions Loch Raven.docx DOCX document
Attachment 17 SOW - Att 16 - CIVIL PART 2D - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 04 - SOW - Specs - 3 of 4.pdf PDF
Attachment 20 SOW - Att 19 - FP-PL-MECH Combined - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 29 Division Cost Breakdown.xlsx XLSX spreadsheet
36C77624R0114_1.pdf PDF
Attachment 13 SOW - Att 12 - CIVIL PART 1C - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 10 SOW - Att 09 - ARCH PART 4 - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 14 SOW - Att 13 - CIVIL PART 2A - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 15 SOW - Att 14 - CIVIL PART 2B - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 19 SOW - Att 18 - ELECTRIC DOC - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 06 SOW - Att 04 - Asbestos Report - EHRM - Infra Upgrades - Loch Raven.xls XLS spreadsheet
Attachment 09 SOW - Att 08 - ARCH PART 3 - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 07 SOW - Att 06 - ARCH PART 1 - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 16 SOW - Att 15 - CIVIL PART 2C - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Attachment 26 - J and A Final Redacted.pdf PDF
Attachment 02 - SOW - Specs - 1 of 4.pdf PDF
Attachment 08 SOW - Att 07 - ARCH PART 2 - EHRM - Infra Upgrades - Loch Raven.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Loch Raven Health Care System 05/29/2024 3901 The Alameda Baltimore, MD 21218

CONSTRUCTION SCOPE OF WORK

EHRM Infrastructure Upgrades – Loch Raven MD

PROJECT NO: 512-22-710

PROJECT NAME: EHRM Infrastructure Upgrades – Loch Raven MD

1. GENERAL INTENT:

The Contractor shall furnish all labor, materials and equipment to prepare the sites identified on the Loch Raven Veteran’s Affairs (VA) campus for the installation of additional IT Tower Additions (TR Towers), new data cabling, new fiber optic cabling, and TR equipment for deployment of the Electronic Health Record (EHR).

2. STATEMENT OF WORK:

Provide all work detailed in the 100% Narrative provided by the A/E in the Bid Files. Contractor to ensure all work adheres to all specifications (specs), and addendums provided in addition to all local, national, federal, and VA standards, specs, and guidelines. Before commencing construction, contractor is to provide an Infection Control Risk Assessment (ICRA) plan for approval by VA Infection Control team.

Contractor also to phase work as necessary to ensure limited disruptions to veterans and VA staff. Any new penetrations made or existing penetrations in walls and/or ceilings found during construction must be fire caulked and sealed.

Offerors are to verify field conditions with a pre-bid site walk and Requests for Information (RFI’s).

All construction work shall be completed during normal working hours, 0730 AM to 4:00 PM. If off-hours and/or weekend work is required, it will be communicated and approved by the VA Contracting Officer’s Representative (COR) in advance. Construction Period Services are to be provided by the Design A/E of record, Acela Architects + Engineers, PC.

In accordance with Veteran’s Affairs Acquisition Regulations (VAAR) 836.204 the Estimated Construction Cost (ECC) is between $10,000,000.00 and $20,000,000.00.

3. PERIOD OF PERFORMANCE:

3.1 Work timelines and completion progress shall be communicated to the COR for tracking purposes.

3.2 Work described in A/E provided SOW shall be completed within 540 calendar days following Notice to Proceed (NTP).

4. PROJECT COMPLETION:

4.1 The contract shall not be closed by the Contracting Officer until after the station’s go-live date in the event that additional work is identified by Cerner and the Change Leadership Team.

SOL # 36C77624R0114 Project # 512-22-710 EHRM Infrastructure Upgrades - Loch Raven MD - Construction

VA Loch Raven Health Care System 05/29/2024 3901 The Alameda Baltimore, MD 21218

4.2 The A/E shall review the Contractor's requests for information and cost proposals for construction change orders when requested by the COR. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.

SOL # 36C77624R0114 Project # 512-22-710 EHRM Infrastructure Upgrades - Loch Raven MD - Construction

File details come from the government source that posted it. Updated .