Summary: Design Build Services Statement of Work – Rawlins Field Office HVAC Improvements

This is a Performance Work Statement for design-build services to replace and upgrade the HVAC system at the Bureau of Land Management (BLM) Rawlins Field Office located at 1300 North 3rd Street, Rawlins, Wyoming. The approximately 32,000 square foot, two-story building constructed in 2005 requires modernization of rooftop air conditioning units, boilers, pumps, exhaust fans, VAV reheat coils, and controls that have reached the end of their useful service lives. The project scope includes demolition of two existing rooftop air handler units, 32 VAV boxes with reheat coils, two boilers with associated pumps, three split HVAC units serving telecom rooms, and related controls. Construction deliverables require installation of two new Energy Star DX rooftop HVAC units (approximately 30 and 40 tons), two new gas-fired boilers with 85% efficiency and 700 MBH input, 32 new VAV boxes with thermostats, three new split HVAC systems with low ambient kits, two new hot water pumps (84 GPM), and complete controls reconfiguration compliant with ASHRAE Guidelines 0, 1.1, and 36 standards. The design must utilize existing AutoCAD drawings, include as-built documentation, and coordinate with the Johnson Controls MetaSys DDC system. All Architect-Engineer services must be performed by licensed professionals registered in Wyoming.

The contract includes eight defined line items covering design and equipment selection, HVAC and electrical demolition, HVAC and electrical construction, HVAC controls, testing and commissioning, and training with operations and maintenance manuals. An optional line item provides for installation of 32 JCI VMA1832s and TEC thermostats contingent on funding availability. Key contractual requirements include establishment of a Microsoft Teams project site for communication, bi-weekly equipment selection meetings, weekly on-site construction progress meetings, submission of a Quality Control Plan and Safety Plan prior to preconstruction conference, and maintenance of as-built drawings throughout construction. The contractor must obtain security clearance for two key personnel, submit a phasing plan to minimize impact on the occupied facility, provide TAB services through an independently certified AABC, NEBB, or TABB contractor, and deliver comprehensive operations and maintenance manuals and 16 hours of system training to BLM personnel prior to final acceptance. Specifications address thermal design conditions, air distribution systems, control system graphics updates, commissioning requirements, and electrical upgrades to support new mechanical equipment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design Build Services

Statement of Work

Rawlins Field Office HVAC Improvements BLM Rawlins Field Office 1300 North 3rd Street Rawlins, WY 82301-2407

01 April 2025

US Department of the Interior Bureau of Land Management

Rawlins Field Office HVAC Improvements Project Rawlins Field Office

Design-Build Statement of Work 01 April 2025

Table of Contents

Contents 1 Project Introduction

1.1 Scope

1.2 Location

1.3 Background

1.3.1 Demolition / Removal of the following Existing Items:

1.3.2 Construction / Installation of the following New Items:

1.4 Data and Materials to be Provided by the Government

1.5 Submission Requirements

2 Project Requirements

2.1 General Requirements

2.1.1 Scope of Work and Project Summary

2.1.2 Definition of Contract Line Items

2.1.3 Project Meetings

2.1.4 Submittals

2.1.5 Project Schedule

2.2 Quality Control

2.2.1 Design Quality Control:

2.2.2 Quality Control Plan:

2.2.3 Reporting:

2.2.4 Quality Control Phases:

2.3 Design Requirements

2.3.1 Design Deliverables

2.3.2 Specifications and Drawings

2.4 Construction Requirements

2.4.1 Security

2.4.2 Environmental Protection

2.4.3 Schedule of Values

2.4.4 Construction Support

2.4.5 Construction Coordination

2.4.6 Digital Images

2.4.7 Temporary Services

2.4.8 Access

2.4.9 Existing Utilities

2.4.10 Accident Prevention and Safety Plan

Design-Build Statement of Work 01 April 2025

2.4.11 Project Close-out

2.4.12 Substantial Completion, Final Inspection, and Project Acceptance

2.5 Forms

3 Design Criteria and Performance Specifications 4 Attachments to this Statement of Work

4.1 Attachment A: Schematic Design Drawings

4.2 Attachment B: Controls Sequence of Operation

4.3 Attachment C: Existing Conditions Documents

4.4 Attachment D: Pictures of the Rawlins FO Interior and Exterior

4.5 Attachment E: BLM Building Codes and Standards (March 2025)

4.6 Attachment F: BLM Forms

Design-Build Statement of Work 01 April 2025

1 Project Introduction Project Title: Rawlins Field Office HVAC Improvements

1.1 Scope

Perform the work in accordance with the terms and conditions of the Contract for the Bureau of Land Management (Government) as described below.

Perform all Architect-Engineer (A/E) Services by licensed Architects and Engineers registered in the State of Wyoming.

Use the Schematic Design Drawings and the Scope of Work as the basis of the design (see attachments).

Select equipment, perform construction, TAB and Commission the system, and develop as-constructed drawings (from existing AutoCAD drawings) of the new equipment.

1.2 Location

This project is located at 1300 North 3rd Street, Rawlins, WY 82301-2407.

1.3 Background

The Rawlins Field Office is an approximately 32,000 square foot, two-story building, constructed in 2005. The existing rooftop air conditioning units, boilers, pumps, exhaust fans, VAV reheat coils, and VMAs contain components that have either failed or have reached the end of their useful service lives. Current energy use at this facility is also higher than desired.

The existing HVAC system consists of two indirect-direct (two-stage) evaporatively cooled rooftop air conditioners, with variable air volume airside (single-inlet VAV terminals), hot water reheat coils, and perimeter hot water cabinet heaters. There are also unit heaters and cabinet unit heaters for space heating. The rooftop air conditioners also contain hot water heating coils for tempering supply air. Exhaust fans have been provided for the toilet rooms, break room, telecom rooms, janitor rooms, the lab, and the electrical room. Two existing boilers provide hot water to the VAVs, unit heaters, and cabinet heaters.

The existing HVAC system controls consist of a Johnson Controls “Metasys” direct digital control (DDC) system.

The existing roof is a single-ply Thermoplastic Polyolefin (TPO) material.

Systems furniture is installed throughout the first and second floors.

The HVAC equipment replacement, controls updates, and additional associated improvements, include:

1.3.1 Demolition / Removal of the following Existing Items:

1. Two (2) existing rooftop air handler units.

2. Roof substrate, as necessary, to accommodate new rooftop air handler units.

3. Two (2) existing VFDs, serving the rooftop air handler units.

4. Thirty-two (32) existing VAV boxes with reheat coils and VMAs.

5. Thirty-two (32) existing thermostats.

6. Two (2) existing boilers; Two (2) existing boiler pumps; AND Two (2) existing hot water pumps.

7. Three (3) split HVAC units (indoor and outdoor units) serving the three telecom and computer rooms.

8. One (1) in-line exhaust fan serving the main electrical room.

Design-Build Statement of Work

1.3.2 Construction / Installation of the following New Items:

1. Two (2) new packaged DX rooftop HVAC units (approximately 30 and 40 tons, respectively).

2. Two (2) new roof curb adapters, serving the new packaged rooftop HVAC units.

3. All associated roof flashing and other work to install the roof curb adapters and the new rooftop HVAC units.

4. Maintain roof structural and building envelope integrity. New rooftop HVAC units may require structural rework.

5. Two (2) VFDs, serving the new packaged rooftop units.

6. Reconfiguration and reprogramming of the existing HVAC control system (to accomplish the

HVAC control sequence of operation). All control sequences shall be in accordance with ASHRAE Guideline 36 (most recent edition). The VAV logic shall be dual maximum, in accordance with ASHRAE Standard 90.1 (most recent edition) and ASHRAE Guideline 36 (most recent edition).

7. Thirty-two (32) new VAV boxes.

8. Thirty-two (32) new thermostats, associated with each of the new VAVs.

9. TAB and Commissioning of the entire new HVAC system (equipment and controls), with full integration into existing MetaSys network and monitoring. Commissioning shall be in accordance with ASHRAE Guideline 0 (most recent edition) and ASHRAE Guideline 1.1 (most recent edition).

10. Furnish and install new valves, appurtenances, insulation, etc. associated with the equipment replacement.

11. As-build 480V Panel MDP and 208V 3-phase Panel LDP.

12. Electrical panel labeling of panels (MDP, LDP, H1, and H2) in the main electrical room.

13. Electrical upgrades, associated with new mechanical equipment (to include any breaker replacements, etc.).

14. Two (2) new gas-fired boilers; Two (2) new boiler pumps; AND Two (2) new hot water pumps.

15. Three (3) new split HVAC units (indoor fan coils and outdoor condenser units) to serve the three telecom and computer rooms. The units shall include low ambient kits.

16. One (1) in-line exhaust fan serving the main electrical room.

17. Associated HVAC controls.

18. Option #1: Include JCI VMA1832s in each of the 32 new VAV boxes and replace thermostats with JCI TEC thermostats. If Option #1 is not approved, reinstall existing VMAs in new VAVs.

Slight adjustments to the proposed project may be necessary after evaluating existing conditions. Changes to the proposed project must be approved by the Government.

1.4 Data and Materials to be Provided by the Government

The following data and materials are included as Attachments to the Contract:

• Attachment A: Schematic Design Drawings

• Attachment B: Controls Sequence of Operation

• Attachment C: Existing Conditions Documents

• Attachment D: Pictures of the Rawlins FO Interior and Exterior

• Attachment E: BLM Building Codes and Standards (March 2025)

• Attachment F: BLM Forms

1.5 Submission Requirements

Deliver all submittals electronically. Provide electronic copies in both the original software format (Revit, AutoCAD, Word, Excel, etc.) and PDF format.

Design-Build Statement of Work 01 April 2025

Specifications in PDF format shall be in a single file and organized with separate bookmarks for each of the MasterFormat divisions and each specification section. Additional required formatting is as follows:

Drawings:

Sheet Size: ANSI D (22” x 34”). At half-size, 11” x 17” shall be “to scale” and legible for use in the electronic bidding process.

Digital File Format: AutoCAD 2022 or Revit 2022 and Adobe PDF. Existing AutoCAD drawings will be provided to minimize design requirements.

Organization: National CAD Standard.

Specifications:

Sheet Size: 8 ½” x 11”.

Digital File Format: MS Word and Adobe PDF.

Organization: MasterFormat with Government header and footer.

Design Calculations:

Sheet Size: 8 ½” x 11”.

Digital File Format: Adobe PDF.

Distribution:

Distribute submittals to the Government personnel identified upon project award.

Communication:

Establish a file sharing site, such as a MS Teams site, for communication of large documents and files.

Design-Build Statement of Work 01 April 2025

2 Project Requirements

2.1 General Requirements

2.1.1 Scope of Work and Project Summary

The project will consist of the equipment selection, field verification, and replacement of primarily HVAC system components and TAB and commissioning of the HVAC system at the Rawlins Field Office.

The work will include, but may not be limited to, the following:

• Evaluate the Schematic Design drawings and Performance Specifications.

• Review site data.

• Optimize system selection and upgrades (to include VAV network) for energy performance.

• Make equipment selections for the HVAC system improvements and other associated work.

• Confirm structural floor and roof capacity. Address if inadequate.

• Verify electrical load, breakers, conduit, wiring, etc.

• Develop Construction Documents.

• Secure work area and provide for continued access to the facility as technically feasible. Coordinate with the Government regarding which portions of the facility will be accessible to the public throughout the construction phase. Note that the facility will remain occupied during construction, so phasing will be required. Replacing one rooftop HVAC unit at a time is an option, if approved by the Government, to decrease occupant impact. Temporary HVAC methods may need to be provided to accomplish the work.

• Construct project.

• TAB and Commission systems. Submit TAB and Commissioning Reports. Air and Water side balancing shall be in accordance with existing mechanical plans.

• Develop and submit Operations and Maintenance (O&M) manuals.

• Maintain and submit As-Constructed documents.

2.1.2 Definition of Contract Line Items

Contract Line Item 1: Design and Equipment Selection

Contract Line Item 2: HVAC Demolition

Contract Line Item 3: Electrical Demolition

Contract Line Item 4: HVAC Construction

Contract Line Item 5: Electrical Construction

Contract Line Item 6: HVAC Controls

Contract Line Item 7: TAB and Commissioning

Contract Line Item 8: Training and O&M Manuals

Option #1: Install 32 new JCI VMA1832s and 32 new JCI TEC thermostats.

The Option will be awarded based on availability of funding and is not guaranteed to be awarded. If awarded, the option will be completed within the contract performance period. The option will be considered in accordance with FAR 52.217-5 Evaluation of Options (JULY 1990).

Design-Build Statement of Work

If Option #1 is not awarded, re-install 32 existing VMAs in the new VAV boxes.

2.1.3 Project Meetings

Establish a Microsoft Teams site to provide for communication of the project team, sharing of information, and submittals.

Schedule and conduct bi-weekly meetings and conferences to coordinate equipment selection and construction activities for the project. Conduct equipment selection and field verification meetings via Teams. Conduct construction meetings at the project site, unless otherwise approved, with a Teams connection for those who need to attend a meeting remotely.

Inform participants and individuals whose presence is required of date and time of each meeting.

Prepare and distribute the meeting agenda in advance of the meeting to all invited attendees.

Conduct project meetings as follows:

Preconstruction Conference (within 10 days of Notice to Proceed):

Submit the following a minimum of one week prior to the Preconstruction Conference:

• Letter designating the DBC Project Superintendent.

• Project Schedule with construction portion fully developed.

• Schedule of Values.

• Quality Control Plan.

• Security Plan.

Equipment Selection Phase Meetings:

Hold meetings every two weeks, via Microsoft Teams, with the DBC team and Government. Discuss the following agenda items:

• Status of project equipment selection.

• Status of field verification.

• Submittal status.

• Discussion of any required details

• Schedule update.

• Other business related to the project.

Construction Phase Progress Meetings:

Hold weekly on-site (include Teams option for virtual attendees) with the Government and DBC team during the Construction Phase. Discuss the following agenda items:

• Submittal status.

• Review of off-site fabrication and delivery.

• Requests for Information (RFIs) and issues.

• Modifications.

• Work in progress and work projected over the next six (6) weeks.

• Three-Week Look Ahead Schedule.

• Status of As-Constructed Drawings.

• Other business related to the project.

Meeting Participation:

Lead the coordination and facilitation of all meetings and ensure the attendance of the necessary design disciplines and consultants. Provide meeting minutes within one week of the meeting.

Design-Build Statement of Work 01 April 2025

2.1.4 Submittals

Supplement FAR Clause 52.236-21, Specifications and Drawings for Construction as follows:

A draft “Submittal List” is provided in the Appendix. The list may not include all required submittals and is provided to support identification of required submittals.

Verify the “Submittal List” and determine what submittals will be required and the type of submittal. Action submittals require Government approval prior to construction and Informational submittals are either accepted or rejected.

Action Submittals include product data, equipment selection, details, shop drawings, and samples.

Informational submittals include copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.

Maintain a submittal log.

Review each submittal and check for coordination with other contract work and for compliance with the contract.

Note corrections and field dimensions.

The Government has fourteen (14) calendar days to review and indicate the appropriate action on the CM-16 Transmittal Form. Review time will initiate upon submission of a complete submittal.

List of main required submittals for Government approval:

• DX rooftop HVAC units

• Rooftop HVAC units Roof Curb Adapters

• VAVs

• Thermostats

• Boilers

• Boiler Pumps

• Hot Water Pumps

• Split HVAC units (indoor and outdoor)

• Exhaust Fan

• Control Sequences; Control Devices; Control Wiring Diagrams

• Wire and Cable

• Electrical One-Line Diagrams

• Option #1: VMAs and TEC Thermostats

• Phasing Plan

• TAB Report

• Commissioning Report

• O&M Data (for VAV boxes, DX units, Pumps, VFDs, etc.)

Submittal / Transmittal:

• Name of DBC, subcontractor, and supplier.

• Specification section, page number, and paragraph, and/or drawing number.

• Description of Item.

• Area of Government action, with method for tracking status (approved, approved with changes, rejected, submittal version).

2.1.5 Project Schedule

FAR Clause 52.236-15, Schedules for Construction Contracts, is supplemented as follows:

Design-Build Statement of Work 01 April 2025

Use a bar chart method (BCM) to list the principal project design and construction tasks in rough chronological order and show the duration (number of days), as well as anticipated start and end time dates for each task.

Update the schedule to indicate planned verses actual accomplishments as the project progresses. Provide sufficient detail to enable the Government to judge as to the adequacy of the operations and to anticipate such conditions as may tend to impair or delay the progress and completion of the work.

Provide a three-week look-ahead working schedule at each project construction status meeting.

2.2 Quality Control

The Government will perform Quality Assurance in accordance with FAR Subpart 46.4.

FAR Clause 52.246-12, Inspection of Construction, is supplemented as follows:

2.2.1 Design Quality Control:

Provide QC to ensure that design work and documents are prepared in accordance with good, prudent, and generally accepted design and engineering quality control practices.

Prepare and check plans, calculations, drawings and other items, to ensure they are independently checked and back-checked. Clearly identify the originator, checker, and back-checker on the face of submittals.

Coordinate work performed by different persons to ensure that conflicts, omissions, or misalignments do not occur between drawings, or between the drawings and the specifications. Coordinate the review, approval, release, distribution, and revision of documents involving work performed by different persons.

2.2.2 Quality Control Plan:

Prior to the Preconstruction Meeting, submit for approval a written Quality Control Plan (QCP). If the plan requires revisions, resubmit the plan within 10 calendar days. Do not change the approved plan without written approval.

Include the following:

1. A list of personnel responsible for quality control and assigned duties. Include each person’s qualifications.

2. A copy of a letter of direction to the DBC’s Quality Control Supervisor outlining assigned duties.

3. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

4. Methods of performing, documenting, and enforcing quality control of all work.

5. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

2.2.3 Reporting:

For materials or work accepted by certification review all certifications to ensure compliance with the requirements of the contract prior to incorporating materials into the work and provide a signed copy of the reviewed certification(s). In accordance with FAR Subpart 46.407, materials or work without proper certification will be rejected in writing, and payment for such material or work will be withheld until proper certification has been provided to the CO.

Maintain Quality Control Daily Reports and Daily Test Report Information Sheets of quality control activities and tests.

Quality Control Daily Reports may not be substituted for other written reports required under clauses of the Contract, such as Disputes, Differing Site Conditions, or Changes.

Design-Build Statement of Work 01 April 2025

Stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Government.

Failure to comply with the approved QCP or submit quality control daily reports or test results the Government may retain payments until such time a plan is accepted and implemented.

2.2.4.1 Daily Reports:

Submit daily reports showing all inspections and tests on the first workday following the date covered by the report. Utilize the forms attached at the end of this section.

2.2.4.3 Off-Site Inspection Reports: Submit prior to shipment.

2.2.4 Quality Control Phases:

Implement the following Quality Control Phases:

2.2.5.1 Preparatory Phase: Before starting each section of work, hold a preparatory phase meeting.

Include the project superintendent, work foreperson, QCS, testers, appropriate subcontractors, and Government.

1. Review submittal requirements with personnel directly responsible for the quality control work.

2. Review all applicable specifications sections and drawings related to the feature of work.

3. Ensure that copies of all referenced standards related to sampling, testing, and execution for the feature of work are available on site.

4. Ensure that provisions have been made for field control testing.

5. Examine the work area to ensure that all preliminary work has been completed.

6. Verify all field dimensions and advise the Government of discrepancies with contract documents.

7. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.

8. Document all preparatory phase activities and discussions on the Quality Control Daily Report.

2.2.5.2 Production Phase:

1. As soon as work begins, inspect, test, and report according to the QCP and evaluate acceptability of the work produced. Discuss the status and effectiveness of the QC process with the Government weekly.

2. Identify and correct deficiencies. Make changes to work processes to prevent repeat deficiencies.

3. Document all production phase activities and discussions on the DBC’s Quality Control Daily

Report. Indicate exact location of inspections and testing for future reference and comparison with follow-up phases.

2.3 Design Requirements

2.3.1 Design Deliverables

Provide the following with each design deliverable:

1. Plans with sufficient technical information and drawings to construct the project and assess conformance with the contract requirements,

2. Construction specifications (Divisions 2 through 49),

3. Product file(s),

4. Statement of structural tests and special inspections,

5. Required permits and status,

6. Design calculations with notes and assumptions necessary to document the design,

7. Supplemental design reports being prepared or completed as part of the design.

8. Written responses for prior deliverable review comments,

9. Design exception requests (if any).

Design-Build Statement of Work 01 April 2025

10. Certification that established QA/QC procedures have been implemented and that the work conforms to said procedures.

Submit draft reports prepared to support the design for review and concurrence as they are completed.

Design Development (65%) Package The purpose of this submittal is to ascertain that the design is progressing in accordance with the project requirements, specifically that:

1. Existing conditions are properly identified and addressed,

2. Coordination is occurring between the disciplines on the elements of the project,

3. Liaison and coordination has occurred between the DBC, Government, and other entities (state, local, utility, etc.) as necessary, and

4. Design is being completed in accordance with the required standards.

Draft Construction Documents (100%) Package Provide detailed, complete, and checked design documents necessary for the construction of the project.

Stamped and Signed Construction Documents (100%) Package Provide all signed and sealed original design documents necessary for the construction of the project. Place professional stamp(s) and signatures on final construction drawings, specifications, and shop drawings in compliance with Wyoming law.

For each of the three design deliverables, the Government will be provided 30 calendar days for review.

Comments shall be integrated into the documents.

2.3.2 Specifications and Drawings

2.3.2.1 Specifications

Organize the specification package in accordance with MasterFormat.

2.3.2.2 Plan Drawings

Cover Sheet. Standard cover to include state map and vicinity map (templates as provided by BLM) identified by:

• Project Title.

• Date.

• Milestone (located in top block of project title area).

• Approval block.

• Index. Each sheet identified by both sub sheet number and overall sheet set number/total sheets in set. Locate on cover sheet if space allows. Otherwise place index on following sheet.

Code Sheet. All regulations, codes, and standards utilized for the project.

Plan Sheets.

• Number of sheets as required to construct the project

• Include sufficient technical information.

• Document outside air ventilation calculations in a schedule included with the equipment schedules in the construction drawings.

• Distinguish new work from other information shown on drawings.

• Include a date stamp on each plan sheet that includes the latest date the file was worked on.

Revisions. Add Information to the revision block when changes are made to construction drawings after they have been approved. Include:

Design-Build Statement of Work 01 April 2025

• Identifying mark (a triangle with a number or letter, used to key information in the revision block to the part of the drawing it pertains to)

• Sheet number(s) of the sheets with changes or additions

• Brief description of the revision

• Date of the revision

• Initials of person approving the revision

2.3.2.3 Project Record Drawings: Maintain one complete set of contract drawings and one set of vendor-supplied drawings. Clearly mark changes, deletions, and additions to show actual constructed conditions. Keep record drawings current.

Prior to final inspection, submit complete record drawings.

2.3.2.4 As-Built Drawings: Maintain as-built drawings by updating the approved Construction Document AutoCAD, or Revit, files with information provided on the record drawings, contract modifications; and other applicable shop drawings, sketches, and data. AutoCAD files should be in compliance with the US National CAD Standard. Provide as-constructed drawings in the following formats:

• Full-size paper copies (at the project site).

• Drawing files in both PDF and AutoCAD (or Revit) formats (uploaded to Government-approved digital repository).

Keep as-built drawings current and maintain a revision log of changes made.

Review as-built drawings for accuracy, completeness, and legibility at each project meeting and in advance of submitting the monthly invoice.

The Government may retain a portion of the progress payment if as-built drawings are not current.

Submit as-built drawings and the revision log before the final inspection. Correct errors and omissions found during the final inspection and resubmit as-built drawings for approval within 7 days after the final inspection.

After substantial completion of the project but before final completion, submit one full-size original pdf set of as-built plans and specifications. Mark the title sheet with “AS BUILT PLANS and cover sheet” with

“AS BUILT SPECIFICATIONS”.

The Government will provide existing CAD drawings as well as the Revit Schematic Design drawings.

2.4 Construction Requirements

2.4.1 Security

Submit a Security Plan at the Pre-Construction Conference outlining proposed procedures to maintain a secure project. Identify two key personnel who will receive a security clearance from the Government and these personnel will be responsible for implementing the security plan. At least one of the key personnel must be on-site during work activities. Until the employees receive clearance a Government representative will supervise access.

The building, and some interior rooms requires key card entry. The two key personnel may be issued key card passes, after security clearance.

Secure access to the building at the end of each working day.

Maintain security for all construction personnel. Issue credentialed (picture) identification for all construction personnel on the job site. Always display credentials.

2.4.2 Environmental Protection

Submit a hazardous spill plan as required by Federal, state, or local regulations at least 2 days before starting work. Where a hazardous spill plan is not required submit a "Spill Prevention, Control, and Countermeasure (SPCC) Plan".

Describe preventative measures including the location of refueling and storage facilities and the handling of hazardous material. Describe actions to be taken in case of a spill. Identify personnel, equipment, and resources available to address spill prevention and response.

Do not use equipment with leaking fluids. Repair equipment fluid leaks immediately. Keep absorbent material manufactured for containment and cleanup of hazardous material on the job site.

Notify the Government promptly of hazardous spills.

2.4.3 Schedule of Values

After contract award and before the Preconstruction Conference, submit for approval a schedule of dollar values based on the Contract Price Schedule. Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested. The total costs for the component parts of work must equal the contract line item amount for that lump-sum item. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below.

The approved Schedule of Values will form the basis for progress payments.

Receive approval of the Schedule of Values before submitting the first progress payment. A cost loaded project schedule may be an acceptable substitute for a schedule of values in some cases.

2.4.4 Construction Support

Staging Areas

FAR Clause 52.236-10, Operations and Staging Areas, is supplemented as follows:

Limit the construction site to the smallest feasible area. Controls ground disturbance and site management to prevent undue damage to vegetation, soils, and to minimize air, water, soil, and noise pollution.

Staging is limited to in or near the construction area for a construction office or trailer.

Locate construction equipment and material storage in previously disturbed areas near construction site.

FAR Clause 52.236-12, Cleaning Up, is supplemented as follows:

Return staging areas to pre-construction conditions after construction is complete.

Construction Zones To protect the public and Government staff, fence construction zones with approved construction barrier fencing, plastic, or portable fencing, before construction activity begins. Confine activity to the minimum area required for construction.

Parking of Construction Vehicles Limit parking of vehicles to existing roads, in legally designated areas, and within approved staging area(s). Include company insignia / logo on construction vehicles.

Design-Build Statement of Work 01 April 2025

2.4.5 Construction Coordination

Submit a phasing plan, to ensure continued operations at the Rawlins Field Office. Receive approval prior to the commencement of work. Maintain operations of main lobby. Note that transitional seasons (Spring and Fall) are the best times to conduct HVAC work (the more accommodating temperatures generally fall between April and June). The building may be vacated for up to two full calendar weeks to accommodate safe crane and rigging operations.

2.4.6 Digital Images

Use StructionSite or similar software for digital image documentation of progress. Develop a photo location plan for approval. Take and submit images weekly.

2.4.7 Temporary Services

Temporary materials may be new or used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

Water: Water is available on site without metering and without payment of use charges for on-site use only. Provide connections and extensions of services as required for construction operations.

Electrical Power Service: Electrical power from existing system is available for use without metering and without charge. Provide connections and extensions of services as required for construction operations.

Heating and Cooling: Furnish temporary heating and cooling, if required due to the climate during construction. Do not use permanent heating and cooling system without approval. When the permanent heating and cooling system is approved for use as temporary heating and cooling, pay all costs until final acceptance. Install new filters before final acceptance. Equipment warranties shall start on date of Final Acceptance.

Sanitary Facilities: Provide and maintain temporary toilet facilities in accordance with State Health Department. Provide separate accessible facilities for men and women with privacy locks. Enclosures shall be weatherproof, sightly, and of sturdy construction. Completely remove sanitary facilities on completion of work.

2.4.8 Access

Coordinate construction efforts with the Government such that there is minimal impact to the work of the Government personnel and the visiting public. The facility will be occupied during construction, requiring strong coordination by the DBC. Coordinate site access with the Government.

Keep driveways, loading areas, and entrances serving the premises clear and available at all times.

2.4.9 Existing Utilities

Schedule and perform work to minimize disruptions of services. Coordinate with the local utility companies.

Receive approval for disruptions at least 48 hours of the disruption.

FAR Clause 52.236-14, Availability and use of Utility Services, is supplemented as follows:

Use cellular service and phones for job-site telephone service.

2.4.10 Accident Prevention and Safety Plan

Prior to the Preconstruction Meeting, submit for approval a Safety Plan. Receive approval before any on-site work begins. Comply with OSHA and project requirements. Include the following:

• Name of the responsible supervisor to carry out the plan.

• Monthly safety meetings.

• First aid procedures.

Design-Build Statement of Work 01 April 2025

• Outline of each phase of work.

• Hazards associated with each phase and methods proposed to ensure safety of the public, Bureau of

Land Management staff, and DBC employees, as well as property protection.

• Training.

• Planning for possible emergency situations.

• Housekeeping and fire protection.

Accident Reporting: Reportable accidents, defined as death, occupational disease, traumatic injury to DBC’s personnel, Government employees or the public, property; property damage or any accident more than $100; and fires. Report accidents within seven calendar days on Accident/Property Damage Report (attached form CM-22).

Fire Protection Equipment: Observe and enforce standards of fire prevention. No open fires shall be allowed.

Vehicles and Equipment: Provide one fire extinguisher on each vehicle or piece of equipment.

Extinguishers shall have a minimum UL rating of 2-A:10-B: C. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.

Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.

Spark Arresters: Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters approved by the U. S. Forest Service. Written determinations of areas and periods of potential fire hazard will be issued by the Government. Locate internal combustion equipment so that exhausts discharge well away from combustible materials. Locate service areas a minimum of 50 feet from buildings. Shut down equipment before refueling.

Smoking: Smoking within buildings or temporary storage sheds is prohibited. Smoking shall be limited to designated smoking areas only.

Welding: Cutting by torch or welding shall be performed only when adequate fire protection is provided.

2.4.11 Project Close-out

Posted Operating Instructions: Furnish operating instructions attached to or posted adjacent to equipment. Include wiring diagrams, control diagrams, control sequence, start-up adjustment, operation, lubrication, shutdown, safety precautions, procedures in case of equipment failure, and other items of instruction recommended by the manufacturer.

Final Inspection: Before submitting a request for final inspection, submit the following:

• Project Record Drawings and As-Constructed Drawings.

• Spare Parts and Materials: As specified in Performance Requirements and Specifications

• Operation and Maintenance Data.

• Keys and Keying Schedule: Submit all keys including duplicates. Wire all keys for each lock securely together. Tag and plainly mark with lock number, equipment identification, or panel or switch number, and indicate location, such as building and room name or number.

• Operating Tools: As specified in the individual sections.

• Special Tools: One set of special tools required to operate, adjust, dismantle, or repair equipment.

Special tools are those not normally found in possession of mechanics or maintenance personnel.

• System Demonstration and Training.

• Mechanical and Electrical Systems: Verify the following in writing:

Design-Build Statement of Work 01 April 2025 o All systems are complete.

o All systems have been properly started and are operational.

o All controls are complete and operational, and sequences have been checked and are functioning properly.

• Testing and Balancing Report.

• Commissioning Report.

Operation and Maintenance Manuals: Provide one set of three-ring binders with operation and maintenance data to the Government for review, prior to the final inspection. Include manufacturer's standard literature, equipment data sheets, and vendor-furnished as-built drawings; custom written data not included in manufacturer’s standard literature; and schedules, warranties, parts lists, test results, and subcontractor list.

After Government review of operation and maintenance data is complete, incorporate comments and submit three final sets of operation and maintenance data to the Government.

System Demonstration and Training: Train designated personnel in adjustment and operation (including seasonal and emergency operations, if applicable), maintenance, and safety requirements of equipment and systems. Instructors shall be thoroughly trained in operating theory as well as practical operation and maintenance work for each type of equipment or system. The sequence of the training shall follow the approved outline of the training guide (i.e. Operating and Maintenance Data). Individual sections specify the duration of training required. If no duration is listed, provide training of 16 hours to adequately cover the subjects.

2.4.12 Substantial Completion, Final Inspection, and Project Acceptance Submit written certification to the Government that the project, or designated portion of the project, is substantially complete, and request a final inspection. Upon receipt of written request that project is substantially complete, the Government will proceed with inspection within 30 calendar days of receipt of request or will advise the DBC of items that prevent the project from being designated as substantially complete.

When work is determined to be substantially complete, the Government will prepare a list of deficiencies ("Punch List") to be corrected before final acceptance. The Government will issue a Letter of Substantial Completion once it is obtained. If work is not determined to be substantially complete, the Government will notify the DBC in writing.

After completing work, the DBC shall resubmit certification and request a new final inspection.

Following the final inspection, if the work is determined to be substantially complete, the Government will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.

Complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the DBC fails to complete the work within this time frame, the Government may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.

Acceptance of the Work: After all deficiencies have been corrected, the Government will issue a Letter of Final Acceptance.

2.5 Forms

The Government will require the following forms:

• Submittal / Transmittal.

• Accident / Property Damage Reports.

• Quality Control Reports.

• Testing Reports.

• Inspection Reports.

• Update / Status Reports.

Design-Build Statement of Work 01 April 2025

The actual forms used will be designed by the DBC with input from the Government and approved by the Government.

Attached are forms the Government has used in the past. The Government may require additional information prior to approving the form.

Design-Build Statement of Work 01 April 2025

3 Design Criteria and Performance Specifications

B10. Superstructure. Confirm the structural capacity of the roof and floor framing is adequate to support the new systems. Address improvements if required.

B30. Exterior Horizontal Enclosures.

• Minimize disturbance to the existing roof system.

• Patch and replace portions of the roof disturbed using materials, details, and installation methods that match the existing single-ply Thermoplastic Polyolefin (TPO) material.

• Furnish a written 20-year minimum warranty from the date of substantial completion on roofing materials and a 2-year warranty against defects in workmanship for the roofing patch and replacements.

C10. Interior Construction.

• Minimize disturbance to existing interior assemblies and partitions to only those necessary for mechanical, electrical and plumbing work to be completed.

• Confirm required interior wall framing system changes. Address improvements if required.

• Where fire-resistance-rated assemblies are modified, provide materials and construction identical to those tested in assembly indicated according to ASTM E119 by an independent testing agency.

• For STC-rated assemblies, provide materials and construction identical to those tested in assembly indicated according to ASTM E90 and classified according to ASTM E413 by an independent testing agency.

C20. Interior Finishes.

• Volatile organic compound (VOC) content for interior paint shall not exceed 50 grams per liter, less water.

• VOC content for carpet, tile, and cove base adhesives shall not exceed 50 grams per liter, less water.

• Replace any damaged ceiling tiles and suspension system obtain each type of acoustical ceiling tile and its suspension system from single source from single manufacturer to match existing ceiling tiles.

• Provide 10 full-size ceiling tiles to the Government for use in future repairs and maintenance.

• Where existing finishes are to be disturbed or modified for the installation of new HVAC equipment, the patch and replace portions of the disturbed finishes using materials, details and installation methods that match the existing finishes

D30 HVAC Commissioning. Perform the following tasks and deliverables:

• Commissioning Plan: Submit a commissioning plan prior to commencing commissioning work.

• Pre-Functional Inspections: Perform pre-functional inspections to determine whether all systems and equipment being commissioned have been installed properly. The pre-functional inspections can occur at any time up to and including system and equipment start-up.

• Testing, Adjusting, and Balancing (TAB) Oversight: Provide oversight and witness at a minimum 10% of the waterside and airside balancing work of the TAB Contractor. Substantially complete testing and balancing prior to functional performance testing, especially where unbalanced conditions would affect the results of the functional performance tests.

• Functional Performance Testing (Performance Verification): Participate in functional performance testing of all systems and equipment being commissioned; Test all HVAC equipment in the building for proper function in all operational modes. Execute performance tests to simulate operation of the HVAC systems in all weather conditions (summer, intermediate, and winter weather seasons). If performance tests for all weather conditions cannot be satisfactorily simulated when the HVAC commissioning is initially performed, return to the jobsite during appropriate weather conditions to complete the performance testing as necessary. Submit performance verification documentation at the end of functional performance testing, including records of deficiency resolution.

• Deficiency Resolution: Document any deficiencies found during pre-functional inspections and functional performance testing, and document the adjustments and/or alterations required to correct the deficiencies. Re-inspect and re-test the affected systems and equipment after the deficiencies for

Design-Build Statement of Work 01 April 2025 systems related to this contract are corrected. Note deficiencies discovered during the commissioning process related to elements of the HVAC system that are performed under this contract in the deficiency log.

• Commissioning Report: Develop a commissioning report that, includes a summary of the commissioning process, deficiency resolution history, performance verification documentation, and any outstanding issues to be addressed or any testing that may still be required. Submit a finalized commissioning report at the end of the construction warranty period if performance tests for all weather conditions cannot be satisfactorily simulated when the HVAC commissioning is initially performed.

• Demonstration and Training: Provide 16 hours training to BLM site personnel on HVAC system functions, control functions, and routine maintenance procedures.

D3020 Heat Generating Systems (Boilers)

• Furnish and install new traditional boilers, 85% efficiency, suitable for firing with natural gas with 700 MBH input with a 7:1 turndown ratio.

• Furnish and install two new boiler pumps, one for each boiler with 25 GPM pumps at 10 ft TDH.

• Furnish and install new valves and appurtenances:

o Shutoff, Drain, and Blowdown Valves: Bronze ball valves, full port, two piece, with chrome plated ball. Drain and blowdown valves shall be furnished with 3/4” hose pipe thread fittings.

o Check Valves: Bronze, swing type, regrinding type, Y pattern, with renewable bronze disk.

o Boiler Drain Valves: Brass, angle pattern, with 3/4” hose pipe thread outlet.

o Strainers: Bronze, wye type, with removable 20 mesh stainless steel screen. Furnish strainers with blowdown valve and 3/4” hose pipe thread fitting.

o Low Water Cutoff Switch: Manual reset electrode type, with 120 VAC power supply. Furnish with suitable thermowell and heat conductive compound. Provide low water cutoff with a 90-second time delay.

o Manual Reset High Limit Thermostat: Manual reset type, with snap-acting switch, and adjustable temperature range of 110 to 290 degrees F.

• Insulate New Boiler Piping: Furnish and install pipe insulation on all new boiler piping and on all other boiler piping where insulation has been removed for construction. Provide fiberglass pipe insulation with all-service jacket. Provide fiberglass insulation with molded PVC covers at all fitting locations. Furnish and install rigid insulation inserts and insulation shields at all hanger locations. Provide fiberglass pipe insulation thickness as follows:

o 1-1/2” Pipe and Smaller: 1” thick.

o 2. 2” to 6” Pipe: 1-1/2” thick.

• Furnish and Install New Pressure Relief Valve Discharge Piping: Furnish and install new pressure relief valve discharge piping from the boiler pressure relief valves to the existing floor drains; pressure relief piping shall terminate pointing down into floor drains. Use Type L copper piping with wrought copper solder fittings.

• Furnish and Install New Condensate Drain Piping: Furnish and install new condensate drain piping from the boiler condensate drain connections to the existing floor drains. Utilize Schedule 40 PVC for condensate drain piping with solvent-weld socket fittings.

• Furnish and Install New Boiler Vents: Furnish and install new boiler vents at existing connection points.

• Electrical Work: Modify the existing boiler power circuit and existing boiler pump power circuit as necessary to furnish power to the new boilers B-1 and B-2, and through the boilers to their respective boiler pumps BP-1 and BP-2 such that each boiler/boiler pump combination is fed by its own dedicated circuit. Furnish and install new disconnect switches for each boiler/boiler pump combination.

• Boiler Controls: Connect the new boiler controls in each boiler together and program in accordance with the boiler manufacturer’s instructions to execute the control sequence in the Control Sequence of Operations. Stage the boilers together for efficiency.

• Labeling: Furnish and install engraved plastic labels on the new boilers, switches, and other controls.

Furnish and install pipe markers and directional flow arrows on the new boiler piping and gas piping.

Furnish and install pre-formed, pre-printed, snap-on, color-coded pipe markers with directional flow arrows integral with the marker. Furnish and install pipe markers at a minimum of 25 feet on center in each section of pipe. Install markers on piping such that lettering is in the most legible position. Labels shall match existing.

D30303 Cooling Generating Systems.

• Furnish and install two new Energy Star direct expansion (DX) cooling rooftop air conditioning units with hot water heating coil, along with custom roof curb adapters to adapt the new rooftop units to the existing roof curb. The new rooftop HVAC units shall have an energy recover wheel or enthalpy core, in accordance with ASHRAE Standard 90.1 (most recent edition). The custom roof curb adapters and new rooftop units shall be gasketed, sealed, anchored, and secured in accordance with their respective manufacturer’s installation instructions; the existing supply and return air ducts shall be flashed airtight to the roof curb adapters. Strive to design the roof curb adapters to be the same size or smaller than the existing roof curb adapters. The new DX rooftop units shall be 30- and 40-ton rooftop units with SA airflow tracking, variable speed drive compressor, modulating hydronic heating coil, and dry bulb economizer. Provide units factory assembled, designed, tested, and rated in accordance with AHRI 210/240 or AHRI 340/360.

• Furnish and install three new, Energy Star, split HVAC systems (indoor and outdoor components, approximately 3 tons each) to serve the three telecom and computer rooms. Size and type shall be determined by the DBC, to accommodate the spaces and use. The units shall have low ambient kits.

• Thermal Design Criteria: Thermal design conditions for heating and cooling engineering calculations are:

o Closest weather data location: Rawlins, WY o Winter Design:

1) Outdoor Temperature (99% Heating DB): -0.6 deg F

2) Indoor Temperature: 70 deg F o Summer Design:

1) Outdoor Temperature, Dry Bulb (1% Cooling DB): 87.2 deg F

2) Mean Coincident Wet Bulb: 55.2 deg F

3) Design Wet Bulb: 58.1 deg F

4) Indoor…