Attachment 01 - Drawings General Stamped Part I of V - 11 pages.pdf

PDF 9 MB Posted

Attached to
Z2DA--Replace Boiler #2 and Correct Deficiencies at Boiler Plant
Solicitation number
36C24824R0178
Issued by

About this file

This document is a set of construction drawings for a project at the VA Caribbean Healthcare System in San Juan, Puerto Rico to replace boiler #2 and correct boiler plant deficiencies. The drawings outline a phased approach for the mechanical, electrical, plumbing, and structural work, including demolition of the existing boiler #2, installation of a new boiler #2, upgrades to boilers #1 and #3, installation of new steam piping and fuel oil systems, and expansion of the electrical room and restrooms. The drawings are part of Solicitation 36C24824R0178, a construction services procurement for this project issued by the Department of Veterans Affairs Veterans Integrated Service Network 8. The phasing is designed to maintain at least two operational boilers at all times during the construction process.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:0

P M

COVER SHEET

GI-000

01-03-2024 RSM PJG

SAN JUAN, PUERTO RICO

CONTRACT NO. 36C24822C0045

DESIGN SERVICES PROJECT: 672-20-602

PROJECT LOCATION: VA CARIBBEAN HEALTHCARE SYSTEM

10 CALLE CASIA - ADM. BLDG. SUITE 4M456

SAN JUAN, PR 00921-3201

ISSUING OFFICE:

DEPARTMENT OF VETERANS AFFAIRS

NETWORK CONTRACTING OFFICE 8 (NC08)

CONSTRUCTION TEAM 2

ANA ALVARADO, NC08 CONTRACTING OFFICER

REPLACE BOILER #2 AND CORRECT BOILER PLANT DEFICIENCIES

NO. DESCRIPTION DATE

bob.davenport Date 01/03/2024

GI-101 PHASE 1 SCOPE OF WORK

GI-102 PHASE 2 SCOPE OF WORK

GI-103 PHASE 3 SCOPE OF WORK

GI-104 PHASE 4 SCOPE OF WORK

GI-105 PHASE 5 SCOPE OF WORK

GI-106 PHASE 6 SCOPE OF WORK

STRUCTURAL

S-001 GENERAL NOTES

S-100 PARTIAL FOUNDATION PLANS

S-101 PARTIAL NEW FOUNDATION PLAN

S-102 PARTIAL ROOF PLANS

S-200 DETAILS/SECTIONS

S-201 DETAILS/SECTIONS

S-202 DETAILS/SECTIONS

S-203 DETAILS/SECTIONS

S-300 BATHROOM & LAB ROOM DETAILS

S-301 WINDOW DETAILS/SECTIONS

INDEX OF DRAWINGS

Drawing No. Title

GENERAL

GI-000 PROJECT COVER SHEET

GI-001 SHEET INDEX

GI-002 SCOPE OF WORK & DETAILS

GI-003 SCOPE OF WORK DETAILS

GI-004 SCOPE OF WORK DETAILS

M-001 MECHANICAL COVER SHEET

MD-101 MECHANICAL DEMOLITION – OVERALL PLAN

MD-102 MECHANICAL DEMOLITION – BOILER ROOM – HVAC

MD-103 MECHANICAL DEMOLITION – BOILER ROOM – STEAM

MD-104 MECHANICAL DEMOLITION – BOILER ROOM – FUEL OIL

MD-201 MECHANICAL DEMOLITION – ROOF PLAN

MH-101 MECHANICAL NEW WORK – OVERALL PLAN

MH-102 MECHANICAL FLOOR PLAN – BOILER ROOM – HVAC

MH-201 MECHANICAL ROOF PLAN

PLUMBING

P-001 PLUMBING COVER SHEET

PD-101 PLUMBING DEMOLITION PLANS

PL-101 PLUMBING FLOOR PLANS

PL-102 PLUMBING ISOMETRICS

PL-103 PLUMBING DETAILS & SCHEDULES

HVAC

MP-101 MECHANICAL PIPING PLAN – BOILER ROOM – STEAM

MP-102 MECHANICAL PIPING PLAN – BOILER ROOM – FUEL OIL

MS-101 MECHANICAL SITE PLAN

MT-101 MECHANICAL TEMPORARY FUEL OIL PLAN

MH-301 BOILER FLOW DIAGRAM

MH-302 MECHANICAL STEAM – SECTION & ISOMETRIC VIEW

MH-501 MECHANICAL DETAILS

MH-502 MECHANICAL DETAILS

MH-503 MECHANICAL DETAILS

EL-101 ELECTRICAL LIGHTING PLAN

EK-101 ELECTRICAL PANEL SCHEDULES

EK-201 ELECTRICAL RISER & DETAILS

MH-504 MECHANICAL DETAILS

MH-505 MECHANICAL DETAILS

MH-601 MECHANICAL SCHEDULES

MI-101 MECHANICAL CONTROL DIAGRAM

ELECTRICAL

EJ-001 ELECTRICAL COVER SHEET

ED-101 ELECTRICAL DEMOLITION PLAN

EP-101 ELECTRICAL POWER PLAN

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:0

P M

SHEET INDEX

GI-001

01-03-2024 Checker Author

NO. DESCRIPTION DATE

bob.davenport

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:2

P M

SCOPE OF WORK & DETAILS

GI-002

01-03-2024 RSM PJG

NO. DESCRIPTION DATE

bob.davenport

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:3

P M

SCOPE OF WORK DETAILS

GI-003

01-03-2024 RSM PJG

NO. DESCRIPTION DATE

bob.davenport

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:4

P M

SCOPE OF WORK DETAILS

GI-004

01-03-2024 RSM PJG

NO. DESCRIPTION DATE

bob.davenport

PHASE 1 (M,E,P)

PHASE 1(E)

PHASE 1(S)

PHASE 1 (E,P,S)

PHASE 1(M)

PHASE 1 SCOPE OF WORK

THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.

THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER

TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.

BOILER #1, BOILER #2 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.

MECHANICAL (M)

• MECHANICAL WORK ASSOCIATED WITH NEW ELECTRICAL ROOM AND RESTROOM EXPANSION.

• MECHANICAL WORK ASSOCIATED WITH PRIMARY DIESEL PUMP RELOCATION. SECONDARY PUMP, FUEL OIL

SUPPLY LINE AND DAY TANK TO REMAIN OPERATIONAL.

ELECTRICAL (E)

• IDENTIFICATION, VERIFICATION AND REMOVAL OF ALL ABANDONED/NOT-IN-USE BRANCH CIRCUITS FROM EXISTING PANELS "LPP1", "LPP2", "MPZ" AND "RPP". EXISTING ELECTRICAL PANELS SHALL REMAIN OPERATIONAL

TILL THE END OF PHASE 5.

• INSTALLATION OF NEW PANELBOARDS "LPP1", "RPP" AND ASSOCIATED TRANSFORMER IN NEW ELECTRICAL

ROOM.

• ELECTRICAL WORK ASSOCIATED WITH NEW ELECTRICAL ROOM POWER, LIGHTING AND FIRE ALARM.

• INSTALLATION OF NEW SHOWER LIGHTING.

• ELECTRICAL WORK ASSOCIATED WITH ELECTRIC WATER HEATERS EWH-2 AND EWH-3.

• ALL GENERAL BRANCH CIRCUITS SHALL BE TRANSITIONED ONE-BY-ONE TO THE NEW ELECTRICAL ROOM

PANELS AT THE END OF PHASE - 1.

PLUMBING (P)

• PLUMBING WORK ASSOCIATED WITH NEW RESTROOM & SHOWER.

• PLUMBING WORK ASSOCIATED WITH ELECTRIC WATER HEATERS EWH-2 AND EWH-3.

• PLUMBING WORK ASSOCIATED WITH THE RELOCATED SLOP SINK & EWH-4.

STRUCTURAL (S)

• DEMOLITION OF EXISTING CONTAINMENT DIKE, SLAB, AND EXPANDED METAL MESH.

• SHEET PILE WORK TO PROTECT EXISTING SLAB/HOUSEKEEPING PAD.

• STRUCTURAL WORK ASSOCIATED WITH NEW CONCRETE FOUNDATIONS, NEW SLAB ON GRADE, NEW

HOUSEKEEPING PAD FOR WATER SOFTENER PRESSURE VESSELS.

• STRUCTURAL WORK ASSOCIATED WITH NEW CONTAINMENT DIKE FOR BRINE TANKS.

• STRUCTURAL WORK ASSOCIATED WITH NEW CONCRETE WALLS, NEW CONCRETE LID & RAILINGS ON TOP OF

NEW LID.

• STRUCTURAL WORK ASSOCIATED WITH STEEL COLUMNS, NEW STEEL BEAMS, NEW STEEL LADDERS, NEW BAR

GRATING & NEW RAILING FOR CATWALK AND FUTURE PIPE SUPPORT.

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:5

P M

PHASE 1 SCOPE OF WORK

GI-101

01-03-2024 RSM PJG

1/4" = 1'-0"

Phase 1 - Floor Plan

NO. DESCRIPTION DATE

bob.davenport

PHASE 2 (M,E,S)

PHASE 2(M,S)

PHASE 2(M,E)

PHASE 2(M,S)

PHASE 2 (S)

PHASE 2 SCOPE OF WORK

THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.

THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER

TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.

BOILER #1 & BOILER #2 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.

*BOILER PLANT WILL NEED TO BE TEMPORARILY SHUT DOWN FOR WORK OF STEAM HEADER. COORDINATE SHUTDOWN

WITH THE VA PRIOR TO ANY WORK*

MECHANICAL (M)

• MECHANICAL WORK ASSOCIATED WITH INSTALLATION OF NEW FUEL OIL PUMP, FUEL OIL POLISHER, FUEL OIL

SUPPLY & RETURN PIPING INSIDE NEW TRENCH.

• MECHANICAL WORK ASSOCIATED WITH MINI-SPLIT A/C UNIT REPLACEMENT SERVING OPERATORS OFFICE.

• MECHANICAL WORK ASSOCIATED WITH NEW STEAM HEADER. MECHANICAL WORK INCLUDES A NEW EXTENDED STEAM HEADER WITH FOUR VALVE CONNECTIONS FOR FUTURE (BOILER #2, BOILER #3, TEMPORARY BOILER AND

SPARE) AND A DEMOLITION OF NON STEAM RATED VALVE.

• MECHANICAL DEMOLITION OF OLD STEAM PIPING ASSOCIATED WITH BOILER #3 & TEMPORARY BOILER.

• MECHANICAL STEAM PIPING FROM NEW TEMPORARY STEAM CONNECTION TO NEW STEAM HEADER

CONNECTION.

• MECHANICAL STEAM PIPING FROM EXISTING BOILER #3 TO EXISTING HEADER.

ELECTRICAL (E)

• ELECTRICAL WORK ASSOCIATED WITH TEMPORARY BOILER.

• ELECTRICAL WORK ASSOCIATED WITH MINI-SPLIT A/C UNIT REPLACEMENT.

PLUMBING (P)

• PLUMBING WORK ASSOCIATED WITH TEMPORARY BOILER.

• PLUMBING WORK ASSOCIATED WITH MINI-SPLIT A/C UNIT REPLACEMENT.

STRUCTURAL (S)

• TEMPORARY SHORING OF STEAM HEADER AND TEMPORARY BOILER SUPPLY PIPE.

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:0

P M

PHASE 2 SCOPE OF WORK

GI-102

01-03-2024 RSM PJG

1/4" = 1'-0"

Phase 2 - Floor Plan

NO. DESCRIPTION DATE

bob.davenport

PHASE 3(M,E,P,S)

PHASE 3 SCOPE OF WORK

THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.

THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER

TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.

BOILER #1 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.

MECHANICAL (M)

• DEMOLITION OF BOILER #2 AND ALL COMPONENTS (PIPING, CONTROLS, & CONNECTIONS).

• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #2. CONNECT NEW STEAM PIPING FROM BOILER #2 INTO NEW STEAM HEADER. CONECT NEW FUEL OIL SUPPLY AND RETURN LINE SYSTEM TO NEW BOILER #2.

• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #2 ECONOMIZER & NEW BOILERFEED WATER PIPING.

ELECTRICAL (E)

• ELECTRICAL WORK ASSOCIATED WITH BOILER #2 REPLACEMENT.

• ELECTRICAL WORK ASSOCIATED WITH NEW BOILER #2 ECONOMIZER.

• ELECTRICAL WORK ASSOCIATED WITH NEW FUEL POLISHER AND DIESEL PUMP REPLACEMENT.

PLUMBING (P)

• PLUMBING WORK ASSOCIATED WITH BOILER #2 REPLACEMENT.

• PLUMBING WORK ASSOCIATED WITH NEW BOILER #2 ECONOMIZER.

STRUCTURAL (S)

• DEMOLITION OF BOILER #2 SLABS ON GRADE, FOUNDATIONS AND CONTAINMENT DIKE IN AREA OF BOILER #2.

• STRUCTURAL WORK ASSOCAITED WITH NEW CONCRETE FOUNDATIONS, NEW SLAB ON GRADE, NEW

HOUSEKEEPING PAD FOR NEW BOILER #2, CONTAINMENT DYKE, AND BLOWDOWN TRENCH.

• STRUCTURAL WORK ASSOCIATED WITH STEAM HEADER COLUMN. REMOVE TEMPORARY SHORING.

• STRUCTURAL WORK ASSOCAITED WITH NEW STEEL COLUMNS, NEW STEEL BEAMS, NEW STEEL LADDERS, NEW BAR GRATING & NEW RAILING FOR CATWALK AND SUPPORT FOR ECONOMIZERS SERVING BOILERS #1 & #2.

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:0

P M

PHASE 3 SCOPE OF WORK

GI-103

01-03-2024 RSM PJG

1/4" = 1'-0"

Phase 3 - Floor Plan

NO. DESCRIPTION DATE

bob.davenport

PHASE 3(M,E,P,S)

PHASE 4 SCOPE OF WORK

THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.

THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER

TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.

BOILER #1 & BOILER #2 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.

MECHANICAL (M)

• MECHANICAL WORK ASSOCIATED WITH BOILER #3 CONTROLS & COMPONENTS.

• MECHANICAL WORK ASSOCIATED WITH BOILER #3 SWITCHING OVER FUEL OIL PIPING FROM OLD SYSTEM TO

NEW SYSTEM.

• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #3 ECONOMIZER & NEW BOILERFEED WATER PIPING.

• MECHANICAL WORK ASSOCIATED WITH THE TEMPORARY BOILER PIPING (FEEDWATER, CONDENSATE RETURN, FUEL OIL).

ELECTRICAL (E)

• ELECTRICAL WORK ASSOCIATED WITH BOILER #3 FEEDER REPLACEMENT. BOILER REFED FROM NEW

ELECTRICAL ROOM.

• ELECTRICAL WORK ASSOCIATED WITH NEW BOILER #3 ECONOMIZER.

PLUMBING (P)

• PLUMBING WORK ASSOCIATED WITH BOILER #3 FEEDER REPLACEMENT.

• PLUMBING WORK ASSOCIATED WITH NEW BOILER #3 ECONOMIZER.

STRUCTURAL (S)

• DEMOLITION OF SLABS ON GRADE AND FOUNDATIONS IN AREA OF BOILER #3.

• SHEET PILE WORK TO PROTECT EXISTING SLAB/HOUSEKEEPING PAD.

• STRUCTURAL WORK ASSOCIATED WITH NEW CONCRETE FOUNDATIONS, NEW SLAB ON GRADE, & BLOWDOWN

TRENCH.

• STRUCTURAL WORK ASSOCIATED WITH NEW STEEL COLUMNS, NEW STEEL BEAMS, NEW STEEL LADDERS, NEW BAR GRATING & NEW RAILING FOR CATWALK AND SUPPORT FOR ECONOMIZER ASSOCIATED WITH BOILER #3.

• STRUCTURAL WORK ASSOCIATED TEMPORARY STEEM BOILER SUPPLY PIPE.

• REMOVE TEMPORARY "TEMPORARY STEAM BOILER SUPPLY PIPE SHORING."

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:1

P M

PHASE 4 SCOPE OF WORK

GI-104

01-03-2024 RSM PJG

1/4" = 1'-0"

Phase 4 - Floor Plan

NO. DESCRIPTION DATE

bob.davenport

PHASE 5(M,E,P,S)

PHASE 5 SCOPE OF WORK

THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.

THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER

TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.

BOILER #2 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.

MECHANICAL (M)

• MECHANICAL WORK ASSOCIATED WITH BOILER #1 INCLUDING NEW STEAM PIPING, CONTROLS & COMPONENTS.

• MECHANICAL WORK ASSOCIATED WITH BOILER #1 SWITCHING OVER FUEL OIL PIPING FROM OLD SYSTEM TO

NEW SYSTEM.

• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #1 ECONOMIZER & NEW BOILERFEED WATER PIPING.

• MECHANICAL WORK ASSOCIATED WITH NEW WATER TREATMENT LAB.

ELECTRICAL (E)

• ELECTRICAL WORK ASSOCIATED WITH BOILER #1 FEEDER REPLACEMENT. BOILER REFED FROM NEW

ELECTRICAL ROOM.

• ELECTRICAL WORK ASSOCIATED WITH NEW BOILER #1 ECONOMIZER.

• EXISTING DEAERATOR CIRCUIT TO BE TRANSITIONED TO NEW ELECTRICAL ROOM PANEL AT THE END OF PHASE 5.

• OLD ELECTRICAL ROOM DECOMMISSIONED AT THE END OF PHASE .

• ELECTRICAL WORK ASSOCIATED WITH NEW WATER TREATMENT LAB .

PLUMBING (P)

• PLUMBING WORK ASSOCIATED WITH BOILER #1 FEEDER REPLACEMENT.

• PLUMBING WORK ASSOCIATED WITH NEW BOILER #1 ECONOMIZER.

• PLUMBING WORK ASSOCIATED WITH NEW WATER TREATMENT LAB & EWH-1.

• PLUMBING WORK ASSOCIATED WITH REPLACEMENT OF PVC SOFT PIPING AND NEW COPPER PIPING.

STRUCTURAL (S)

• STRUCTURAL WORK ASSOCIATED WITH SUPPORT FOR ECONOMIZER ASSOCIATED WITH BOILER #1.

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:2

P M

PHASE 5 SCOPE OF WORK

GI-105

01-03-2024 RSM PJG

1/4" = 1'-0"

Phase 5 - Floor Plan

NO. DESCRIPTION DATE

bob.davenport

PHASE 6(M)

PHASE 6 SCOPE OF WORK

THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.

THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER

TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.

BOILER #1, BOILER #2 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.

MECHANICAL (M)

• DEMOLITION OF ANY OVERHEAD FUEL OIL PIPING, SECONDARY PUMP & DAY TANK.

REVISIONS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

CD-FINAL (100% CD) SUBMITTAL 01-03-2024

CD-FINAL (100% CD)

SUBMITTAL

10 CALLE CASIA - ADM. BLDG.

SUITE 4M456

672-20-602

FULLY SPRINKLERED

REPLACE BOILER #2 AND

CORRECT BOILER PLAN

DEFICIENCIES

/3

/2

:5

:3

P M

PHASE 6 SCOPE OF WORK

GI-106

01-03-2024 RSM PJG

1/4" = 1'-0"

Phase 6 - Floor Plan

NO. DESCRIPTION DATE

bob.davenport

THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:45:10-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:45:24-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:45:32-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:45:40-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:45:49-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:45:58-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:46:08-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:46:17-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:46:25-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:46:35-0500
Robert G Davenport
I have reviewed this document.
THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES.
2024-01-03T16:46:43-0500
Robert G Davenport
I have reviewed this document.

File details come from the government source that posted it. Updated .