Attachment 01 - Drawings General Stamped Part I of V - 11 pages.pdf
PDF 9 MB Posted
- Solicitation number
- 36C24824R0178
About this file
This document is a set of construction drawings for a project at the VA Caribbean Healthcare System in San Juan, Puerto Rico to replace boiler #2 and correct boiler plant deficiencies. The drawings outline a phased approach for the mechanical, electrical, plumbing, and structural work, including demolition of the existing boiler #2, installation of a new boiler #2, upgrades to boilers #1 and #3, installation of new steam piping and fuel oil systems, and expansion of the electrical room and restrooms. The drawings are part of Solicitation 36C24824R0178, a construction services procurement for this project issued by the Department of Veterans Affairs Veterans Integrated Service Network 8. The phasing is designed to maintain at least two operational boilers at all times during the construction process.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:0
P M
COVER SHEET
GI-000
01-03-2024 RSM PJG
SAN JUAN, PUERTO RICO
CONTRACT NO. 36C24822C0045
DESIGN SERVICES PROJECT: 672-20-602
PROJECT LOCATION: VA CARIBBEAN HEALTHCARE SYSTEM
10 CALLE CASIA - ADM. BLDG. SUITE 4M456
SAN JUAN, PR 00921-3201
ISSUING OFFICE:
DEPARTMENT OF VETERANS AFFAIRS
NETWORK CONTRACTING OFFICE 8 (NC08)
CONSTRUCTION TEAM 2
ANA ALVARADO, NC08 CONTRACTING OFFICER
REPLACE BOILER #2 AND CORRECT BOILER PLANT DEFICIENCIES
NO. DESCRIPTION DATE
bob.davenport Date 01/03/2024
GI-101 PHASE 1 SCOPE OF WORK
GI-102 PHASE 2 SCOPE OF WORK
GI-103 PHASE 3 SCOPE OF WORK
GI-104 PHASE 4 SCOPE OF WORK
GI-105 PHASE 5 SCOPE OF WORK
GI-106 PHASE 6 SCOPE OF WORK
STRUCTURAL
S-001 GENERAL NOTES
S-100 PARTIAL FOUNDATION PLANS
S-101 PARTIAL NEW FOUNDATION PLAN
S-102 PARTIAL ROOF PLANS
S-200 DETAILS/SECTIONS
S-201 DETAILS/SECTIONS
S-202 DETAILS/SECTIONS
S-203 DETAILS/SECTIONS
S-300 BATHROOM & LAB ROOM DETAILS
S-301 WINDOW DETAILS/SECTIONS
INDEX OF DRAWINGS
Drawing No. Title
GENERAL
GI-000 PROJECT COVER SHEET
GI-001 SHEET INDEX
GI-002 SCOPE OF WORK & DETAILS
GI-003 SCOPE OF WORK DETAILS
GI-004 SCOPE OF WORK DETAILS
M-001 MECHANICAL COVER SHEET
MD-101 MECHANICAL DEMOLITION – OVERALL PLAN
MD-102 MECHANICAL DEMOLITION – BOILER ROOM – HVAC
MD-103 MECHANICAL DEMOLITION – BOILER ROOM – STEAM
MD-104 MECHANICAL DEMOLITION – BOILER ROOM – FUEL OIL
MD-201 MECHANICAL DEMOLITION – ROOF PLAN
MH-101 MECHANICAL NEW WORK – OVERALL PLAN
MH-102 MECHANICAL FLOOR PLAN – BOILER ROOM – HVAC
MH-201 MECHANICAL ROOF PLAN
PLUMBING
P-001 PLUMBING COVER SHEET
PD-101 PLUMBING DEMOLITION PLANS
PL-101 PLUMBING FLOOR PLANS
PL-102 PLUMBING ISOMETRICS
PL-103 PLUMBING DETAILS & SCHEDULES
HVAC
MP-101 MECHANICAL PIPING PLAN – BOILER ROOM – STEAM
MP-102 MECHANICAL PIPING PLAN – BOILER ROOM – FUEL OIL
MS-101 MECHANICAL SITE PLAN
MT-101 MECHANICAL TEMPORARY FUEL OIL PLAN
MH-301 BOILER FLOW DIAGRAM
MH-302 MECHANICAL STEAM – SECTION & ISOMETRIC VIEW
MH-501 MECHANICAL DETAILS
MH-502 MECHANICAL DETAILS
MH-503 MECHANICAL DETAILS
EL-101 ELECTRICAL LIGHTING PLAN
EK-101 ELECTRICAL PANEL SCHEDULES
EK-201 ELECTRICAL RISER & DETAILS
MH-504 MECHANICAL DETAILS
MH-505 MECHANICAL DETAILS
MH-601 MECHANICAL SCHEDULES
MI-101 MECHANICAL CONTROL DIAGRAM
ELECTRICAL
EJ-001 ELECTRICAL COVER SHEET
ED-101 ELECTRICAL DEMOLITION PLAN
EP-101 ELECTRICAL POWER PLAN
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:0
P M
SHEET INDEX
GI-001
01-03-2024 Checker Author
NO. DESCRIPTION DATE
bob.davenport
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:2
P M
SCOPE OF WORK & DETAILS
GI-002
01-03-2024 RSM PJG
NO. DESCRIPTION DATE
bob.davenport
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:3
P M
SCOPE OF WORK DETAILS
GI-003
01-03-2024 RSM PJG
NO. DESCRIPTION DATE
bob.davenport
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:4
P M
SCOPE OF WORK DETAILS
GI-004
01-03-2024 RSM PJG
NO. DESCRIPTION DATE
bob.davenport
PHASE 1 (M,E,P)
PHASE 1(E)
PHASE 1(S)
PHASE 1 (E,P,S)
PHASE 1(M)
PHASE 1 SCOPE OF WORK
THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.
THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER
TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.
BOILER #1, BOILER #2 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.
MECHANICAL (M)
• MECHANICAL WORK ASSOCIATED WITH NEW ELECTRICAL ROOM AND RESTROOM EXPANSION.
• MECHANICAL WORK ASSOCIATED WITH PRIMARY DIESEL PUMP RELOCATION. SECONDARY PUMP, FUEL OIL
SUPPLY LINE AND DAY TANK TO REMAIN OPERATIONAL.
ELECTRICAL (E)
• IDENTIFICATION, VERIFICATION AND REMOVAL OF ALL ABANDONED/NOT-IN-USE BRANCH CIRCUITS FROM EXISTING PANELS "LPP1", "LPP2", "MPZ" AND "RPP". EXISTING ELECTRICAL PANELS SHALL REMAIN OPERATIONAL
TILL THE END OF PHASE 5.
• INSTALLATION OF NEW PANELBOARDS "LPP1", "RPP" AND ASSOCIATED TRANSFORMER IN NEW ELECTRICAL
ROOM.
• ELECTRICAL WORK ASSOCIATED WITH NEW ELECTRICAL ROOM POWER, LIGHTING AND FIRE ALARM.
• INSTALLATION OF NEW SHOWER LIGHTING.
• ELECTRICAL WORK ASSOCIATED WITH ELECTRIC WATER HEATERS EWH-2 AND EWH-3.
• ALL GENERAL BRANCH CIRCUITS SHALL BE TRANSITIONED ONE-BY-ONE TO THE NEW ELECTRICAL ROOM
PANELS AT THE END OF PHASE - 1.
PLUMBING (P)
• PLUMBING WORK ASSOCIATED WITH NEW RESTROOM & SHOWER.
• PLUMBING WORK ASSOCIATED WITH ELECTRIC WATER HEATERS EWH-2 AND EWH-3.
• PLUMBING WORK ASSOCIATED WITH THE RELOCATED SLOP SINK & EWH-4.
STRUCTURAL (S)
• DEMOLITION OF EXISTING CONTAINMENT DIKE, SLAB, AND EXPANDED METAL MESH.
• SHEET PILE WORK TO PROTECT EXISTING SLAB/HOUSEKEEPING PAD.
• STRUCTURAL WORK ASSOCIATED WITH NEW CONCRETE FOUNDATIONS, NEW SLAB ON GRADE, NEW
HOUSEKEEPING PAD FOR WATER SOFTENER PRESSURE VESSELS.
• STRUCTURAL WORK ASSOCIATED WITH NEW CONTAINMENT DIKE FOR BRINE TANKS.
• STRUCTURAL WORK ASSOCIATED WITH NEW CONCRETE WALLS, NEW CONCRETE LID & RAILINGS ON TOP OF
NEW LID.
• STRUCTURAL WORK ASSOCIATED WITH STEEL COLUMNS, NEW STEEL BEAMS, NEW STEEL LADDERS, NEW BAR
GRATING & NEW RAILING FOR CATWALK AND FUTURE PIPE SUPPORT.
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:5
P M
PHASE 1 SCOPE OF WORK
GI-101
01-03-2024 RSM PJG
1/4" = 1'-0"
Phase 1 - Floor Plan
NO. DESCRIPTION DATE
bob.davenport
PHASE 2 (M,E,S)
PHASE 2(M,S)
PHASE 2(M,E)
PHASE 2(M,S)
PHASE 2 (S)
PHASE 2 SCOPE OF WORK
THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.
THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER
TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.
BOILER #1 & BOILER #2 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.
*BOILER PLANT WILL NEED TO BE TEMPORARILY SHUT DOWN FOR WORK OF STEAM HEADER. COORDINATE SHUTDOWN
WITH THE VA PRIOR TO ANY WORK*
MECHANICAL (M)
• MECHANICAL WORK ASSOCIATED WITH INSTALLATION OF NEW FUEL OIL PUMP, FUEL OIL POLISHER, FUEL OIL
SUPPLY & RETURN PIPING INSIDE NEW TRENCH.
• MECHANICAL WORK ASSOCIATED WITH MINI-SPLIT A/C UNIT REPLACEMENT SERVING OPERATORS OFFICE.
• MECHANICAL WORK ASSOCIATED WITH NEW STEAM HEADER. MECHANICAL WORK INCLUDES A NEW EXTENDED STEAM HEADER WITH FOUR VALVE CONNECTIONS FOR FUTURE (BOILER #2, BOILER #3, TEMPORARY BOILER AND
SPARE) AND A DEMOLITION OF NON STEAM RATED VALVE.
• MECHANICAL DEMOLITION OF OLD STEAM PIPING ASSOCIATED WITH BOILER #3 & TEMPORARY BOILER.
• MECHANICAL STEAM PIPING FROM NEW TEMPORARY STEAM CONNECTION TO NEW STEAM HEADER
CONNECTION.
• MECHANICAL STEAM PIPING FROM EXISTING BOILER #3 TO EXISTING HEADER.
ELECTRICAL (E)
• ELECTRICAL WORK ASSOCIATED WITH TEMPORARY BOILER.
• ELECTRICAL WORK ASSOCIATED WITH MINI-SPLIT A/C UNIT REPLACEMENT.
PLUMBING (P)
• PLUMBING WORK ASSOCIATED WITH TEMPORARY BOILER.
• PLUMBING WORK ASSOCIATED WITH MINI-SPLIT A/C UNIT REPLACEMENT.
STRUCTURAL (S)
• TEMPORARY SHORING OF STEAM HEADER AND TEMPORARY BOILER SUPPLY PIPE.
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:0
P M
PHASE 2 SCOPE OF WORK
GI-102
01-03-2024 RSM PJG
1/4" = 1'-0"
Phase 2 - Floor Plan
NO. DESCRIPTION DATE
bob.davenport
PHASE 3(M,E,P,S)
PHASE 3 SCOPE OF WORK
THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.
THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER
TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.
BOILER #1 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.
MECHANICAL (M)
• DEMOLITION OF BOILER #2 AND ALL COMPONENTS (PIPING, CONTROLS, & CONNECTIONS).
• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #2. CONNECT NEW STEAM PIPING FROM BOILER #2 INTO NEW STEAM HEADER. CONECT NEW FUEL OIL SUPPLY AND RETURN LINE SYSTEM TO NEW BOILER #2.
• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #2 ECONOMIZER & NEW BOILERFEED WATER PIPING.
ELECTRICAL (E)
• ELECTRICAL WORK ASSOCIATED WITH BOILER #2 REPLACEMENT.
• ELECTRICAL WORK ASSOCIATED WITH NEW BOILER #2 ECONOMIZER.
• ELECTRICAL WORK ASSOCIATED WITH NEW FUEL POLISHER AND DIESEL PUMP REPLACEMENT.
PLUMBING (P)
• PLUMBING WORK ASSOCIATED WITH BOILER #2 REPLACEMENT.
• PLUMBING WORK ASSOCIATED WITH NEW BOILER #2 ECONOMIZER.
STRUCTURAL (S)
• DEMOLITION OF BOILER #2 SLABS ON GRADE, FOUNDATIONS AND CONTAINMENT DIKE IN AREA OF BOILER #2.
• STRUCTURAL WORK ASSOCAITED WITH NEW CONCRETE FOUNDATIONS, NEW SLAB ON GRADE, NEW
HOUSEKEEPING PAD FOR NEW BOILER #2, CONTAINMENT DYKE, AND BLOWDOWN TRENCH.
• STRUCTURAL WORK ASSOCIATED WITH STEAM HEADER COLUMN. REMOVE TEMPORARY SHORING.
• STRUCTURAL WORK ASSOCAITED WITH NEW STEEL COLUMNS, NEW STEEL BEAMS, NEW STEEL LADDERS, NEW BAR GRATING & NEW RAILING FOR CATWALK AND SUPPORT FOR ECONOMIZERS SERVING BOILERS #1 & #2.
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:0
P M
PHASE 3 SCOPE OF WORK
GI-103
01-03-2024 RSM PJG
1/4" = 1'-0"
Phase 3 - Floor Plan
NO. DESCRIPTION DATE
bob.davenport
PHASE 3(M,E,P,S)
PHASE 4 SCOPE OF WORK
THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.
THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER
TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.
BOILER #1 & BOILER #2 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.
MECHANICAL (M)
• MECHANICAL WORK ASSOCIATED WITH BOILER #3 CONTROLS & COMPONENTS.
• MECHANICAL WORK ASSOCIATED WITH BOILER #3 SWITCHING OVER FUEL OIL PIPING FROM OLD SYSTEM TO
NEW SYSTEM.
• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #3 ECONOMIZER & NEW BOILERFEED WATER PIPING.
• MECHANICAL WORK ASSOCIATED WITH THE TEMPORARY BOILER PIPING (FEEDWATER, CONDENSATE RETURN, FUEL OIL).
ELECTRICAL (E)
• ELECTRICAL WORK ASSOCIATED WITH BOILER #3 FEEDER REPLACEMENT. BOILER REFED FROM NEW
ELECTRICAL ROOM.
• ELECTRICAL WORK ASSOCIATED WITH NEW BOILER #3 ECONOMIZER.
PLUMBING (P)
• PLUMBING WORK ASSOCIATED WITH BOILER #3 FEEDER REPLACEMENT.
• PLUMBING WORK ASSOCIATED WITH NEW BOILER #3 ECONOMIZER.
STRUCTURAL (S)
• DEMOLITION OF SLABS ON GRADE AND FOUNDATIONS IN AREA OF BOILER #3.
• SHEET PILE WORK TO PROTECT EXISTING SLAB/HOUSEKEEPING PAD.
• STRUCTURAL WORK ASSOCIATED WITH NEW CONCRETE FOUNDATIONS, NEW SLAB ON GRADE, & BLOWDOWN
TRENCH.
• STRUCTURAL WORK ASSOCIATED WITH NEW STEEL COLUMNS, NEW STEEL BEAMS, NEW STEEL LADDERS, NEW BAR GRATING & NEW RAILING FOR CATWALK AND SUPPORT FOR ECONOMIZER ASSOCIATED WITH BOILER #3.
• STRUCTURAL WORK ASSOCIATED TEMPORARY STEEM BOILER SUPPLY PIPE.
• REMOVE TEMPORARY "TEMPORARY STEAM BOILER SUPPLY PIPE SHORING."
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:1
P M
PHASE 4 SCOPE OF WORK
GI-104
01-03-2024 RSM PJG
1/4" = 1'-0"
Phase 4 - Floor Plan
NO. DESCRIPTION DATE
bob.davenport
PHASE 5(M,E,P,S)
PHASE 5 SCOPE OF WORK
THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.
THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER
TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.
BOILER #2 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.
MECHANICAL (M)
• MECHANICAL WORK ASSOCIATED WITH BOILER #1 INCLUDING NEW STEAM PIPING, CONTROLS & COMPONENTS.
• MECHANICAL WORK ASSOCIATED WITH BOILER #1 SWITCHING OVER FUEL OIL PIPING FROM OLD SYSTEM TO
NEW SYSTEM.
• MECHANICAL WORK ASSOCIATED WITH NEW BOILER #1 ECONOMIZER & NEW BOILERFEED WATER PIPING.
• MECHANICAL WORK ASSOCIATED WITH NEW WATER TREATMENT LAB.
ELECTRICAL (E)
• ELECTRICAL WORK ASSOCIATED WITH BOILER #1 FEEDER REPLACEMENT. BOILER REFED FROM NEW
ELECTRICAL ROOM.
• ELECTRICAL WORK ASSOCIATED WITH NEW BOILER #1 ECONOMIZER.
• EXISTING DEAERATOR CIRCUIT TO BE TRANSITIONED TO NEW ELECTRICAL ROOM PANEL AT THE END OF PHASE 5.
• OLD ELECTRICAL ROOM DECOMMISSIONED AT THE END OF PHASE .
• ELECTRICAL WORK ASSOCIATED WITH NEW WATER TREATMENT LAB .
PLUMBING (P)
• PLUMBING WORK ASSOCIATED WITH BOILER #1 FEEDER REPLACEMENT.
• PLUMBING WORK ASSOCIATED WITH NEW BOILER #1 ECONOMIZER.
• PLUMBING WORK ASSOCIATED WITH NEW WATER TREATMENT LAB & EWH-1.
• PLUMBING WORK ASSOCIATED WITH REPLACEMENT OF PVC SOFT PIPING AND NEW COPPER PIPING.
STRUCTURAL (S)
• STRUCTURAL WORK ASSOCIATED WITH SUPPORT FOR ECONOMIZER ASSOCIATED WITH BOILER #1.
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:2
P M
PHASE 5 SCOPE OF WORK
GI-105
01-03-2024 RSM PJG
1/4" = 1'-0"
Phase 5 - Floor Plan
NO. DESCRIPTION DATE
bob.davenport
PHASE 6(M)
PHASE 6 SCOPE OF WORK
THE FOLLOWING PHASING PROVIDED BELOW IS TO SHOW PHASING INTENT ONLY ASSOCIATED WITH THE DEMOLITION AND NEW CONSTRUCTION. CONTRACTORS SHALL COORDINATE BETWEEN ALL TRADES AND THE VA FOR EACH PHASE.
THE BOILER PLANT SHALL CONTINUE TO OPERATE DURING ALL CONSTRUCTION PHASES. THE BOILER PLANT SHALL HAVE A MINIMUM OF TWO (2) FULLY FUNCTIONAL BOILERS (N) AND (N+1) OPERABLE AT ALL TIMES. IN THE EVENT THAT THE (N) AND (N+1) OPERATING REQUIREMENT CAN NOT BE MET BY THE BOILER PLANT, THE CONTRACTOR SHALL PROVIDE AN ADDITIONAL TEMPORARY (RENTAL) BOILER, CONTRACTOR SHALL COORDINATE WITH THE VA AND FACILITATE THE IMPLENTATION OF THE CONNECTIONS FROM THE TEMPORARY BOILER TO THE BOILER PLANT. REFER
TO INDIVIDUAL DISCIPLINE SHEETS FOR ADDITIONAL INFORMATION.
BOILER #1, BOILER #2 & BOILER #3 WILL BE OPERATIONAL AND IN USE DURING THIS PHASE.
MECHANICAL (M)
• DEMOLITION OF ANY OVERHEAD FUEL OIL PIPING, SECONDARY PUMP & DAY TANK.
REVISIONS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CD-FINAL (100% CD) SUBMITTAL 01-03-2024
CD-FINAL (100% CD)
SUBMITTAL
10 CALLE CASIA - ADM. BLDG.
SUITE 4M456
672-20-602
FULLY SPRINKLERED
REPLACE BOILER #2 AND
CORRECT BOILER PLAN
DEFICIENCIES
/3
/2
:5
:3
P M
PHASE 6 SCOPE OF WORK
GI-106
01-03-2024 RSM PJG
1/4" = 1'-0"
Phase 6 - Floor Plan
NO. DESCRIPTION DATE
bob.davenport
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:45:10-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:45:24-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:45:32-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:45:40-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:45:49-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:45:58-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:46:08-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:46:17-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:46:25-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:46:35-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
| THIS ITEM HAS BEEN ELECTRONICALLY SIGNED AND SEALED BY ROBERT G DAVENPORT, PE USING A DIGITAL SIGNATURE AND DATE. PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED ON ANY ELECTRONIC COPIES. | |
| 2024-01-03T16:46:43-0500 | |
| Robert G Davenport | |
| I have reviewed this document. |
File details come from the government source that posted it. Updated .