Attachment 0004a - EOC Acceptance Test Procedures_FINAL.docx
DOCX document 6 MB Posted
- Attached to
- RFP for Integrated Battle Command System (IBCS) LRIP/FRP Federal contract opportunity
- Solicitation number
- W31P4Q-20-R-0015
About this file
This request for proposal is for the Integrated Battle Command System Low Rate Initial Production/Full Rate Production hardware segment. The Army is seeking to procure IBCS hardware end items that are produced in accordance with supplied technical data packages and critical item development specifications. Engineering changes may be required to address obsolescence, enable new capabilities, and facilitate export. Questions regarding this RFP were due by December 10, 2020. The RFP is open only to contractors that met entrance criteria established by the Integrated Fires Mission Command Project Office on the SAM portal and were approved for this opportunity.
View the file
Other files for this federal contract opportunity
Show all 50
RFP for Integrated Battle Command System (IBCS) LRIP/FRP has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Official Use Only
Integrated Fires Mission Command (IFMC) Integrated Battle Command System (IBCS) Acceptance Test Procedures – EOC 15 July 2020
Table of Contents
| 1. | Scope | 6 |
| 1.1 | IBCS EOC | 6 |
| 1.2 | EOC Lite | 27 |
| 1.3 | Additional Test Equipment | 28 |
| 2. | Test Configurations | 29 |
| 2.1 Test Diagrams | 29 | |
| 3. Pretest Setup | 31 | |
| 3.1 | Grounding | 31 |
| 4. | Test Procedures | 33 |
| 4.1 | System Power On | 33 |
| 4.2 | S-280 Lights | 47 |
| 4.3 | EOC Emergency Power Off | 48 |
| 4.4 | ADSI Initialization | 49 |
| 4.5 | UPS Continuity and Power Down | 55 |
| 4.6 ICE Tests | 69 | |
| 4.6.1 Power On and Lights | 69 | |
| 4.6.2 Projectors | 70 | |
| 4.6.3 Sound Commander | 73 | |
| 4.6.4 Internal EOC Voice | 74 | |
| 4.6.5 Printer / Workstation MS Office | 93 | |
| 4.6.6 File Transfer | 96 | |
| 4.7 OIV/FCN Connectivity Tests | 97 | |
| 4.7.1 Operator Workstations | 97 | |
| 4.7.2 Maintenance Laptop | 99 | |
| 4.7.3 Black (Unclassified) Network Configuration | 100 | |
| 4.7 Communications and Radio Tests | 106 | |
| 4.7.1 CASS | 106 | |
| 4.7.2 MIDS BIT Test | 107 | |
| 4.7.3 JTT | 109 | |
| 4.8 FMTV Tests | 110 | |
| 4.8.1 Blue Force Tracker | 110 | |
| 4.9 | Air Defense Functionality | 111 |
| 4.10 End of Test Data Harvest | 112 | |
| 5. | Supporting Documentation for EOC ATP Execution | 116 |
| 5.1 | Operator Instructions for Test Tools | 116 |
List of Figures
| Figure 1-1. ICE HBT® AirBeam Tent | 7 |
| Figure 1-2. Front Isometric View of EOC Prime Mover & S-280 Shelter | 8 |
| Figure 1-3. ICE Interior View | 9 |
| Figure 1-4. ICE PDU | 10 |
| Figure 1-5. ICE PDU Power Connections | 10 |
| Figure 1-6. Primary LAN Transit Case | 11 |
| Figure 1-7. Red Road Side SEP | 12 |
| Figure 1-8. Primary LAN Patch Panel | 13 |
| Figure 1-9. Workstation Transit Case | 13 |
| Figure 1-10. Workstation Transit Case Rear View Close Up | 14 |
| Figure 1-11. Secondary LAN Transit Case | 15 |
| Figure 1-12. Secondary LAN Patch Panel | 15 |
| Figure 1-13. Black Curb Side SEP | 16 |
| Figure 1-14. S-280 Curbside Interior View | 17 |
| Figure 1-15. S-280 Layout - Top View | 17 |
| Figure 1-16. S-280 Equipment Rack Overview | 18 |
| Figure 1-17. S-280 Rack 1 | 19 |
| Figure 1-18. S-280 Rack 2 | 20 |
| Figure 1-19. S-280 Rack 3 | 21 |
| Figure 1-20. S-280 Rack 4 | 22 |
| Figure 1-21. S-280 PDP | 23 |
| Figure 1-22. S-280 PEV Side View | 24 |
| Figure 1-23. S-280 PEV Front View | 25 |
| Figure 1-24. Front View SEP | 25 |
| Figure 1-25. EOC Lite | 27 |
| Figure 2-1. S-280-to-ICE | 29 |
| Figure 2-2. SEP (Black) Ping (w/o Software) | 30 |
List of Tables
| Table 1‑1. EOC Configurations by Echelon | 26 |
| Table 1-2. Additional Test Equipment | 28 |
| Table 4-4. Power On | 33 |
| Table 4-5. S-280 Lights | 47 |
| Table 4-6. EOC Emergency Power Off | 48 |
| Table 4-7. ADSI Initialization | 49 |
| Table 4-8. UPS Continuity & Power Down | 55 |
| Table 4-9. End-of-Test / System Shutdown | 58 |
| Table 4-10. ICE Lights | 69 |
| Table 4-11. Projectors | 70 |
| Table 4-12. Sound Commander | 73 |
| Table 4-13. Internal EOC Voice | 74 |
| Table 4-14. Printer / Workstation MS Office | 93 |
| Table 4-15. File Transfer | 96 |
| Table 4-16. Operator Workstations | 97 |
| Table 4-17. Maintenance Laptop | 99 |
| Table 4-18. Black (Unclassified) Network Configuration | 100 |
| Table 4-19. CASS | 106 |
| Table 4-20. MIDS BIT Test | 107 |
| Table 4-21. JTT | 109 |
| Table 4-22. Blue Force Tracker | 110 |
| Table 4-23. Air Defense Functionality | 111 |
| Table 4-24. End of Test Data Harvest | 112 |
| For Official Use Only | W31P4Q-20-R-0015 | |
| ATTACHMENT 0004a |
1. Scope
The objective of this Acceptance Test Description / Procedure (ATD/P) is to provide the detailed test steps necessary to demonstrate key functionality of the Integrated Battle Command System (IBCS) Engagement Operations Centers (EOCs) and to confirm conformity of integrated hardware and software end items with the qualified baseline. The qualified baseline is the successful integration of the Major End Item (MEI) hardware and software.
Satisfaction of the following criteria shall constitute successful completion of the AT process:
1. Hardware components shall exhibit no defects during In-process and Functional Check-Out (FCO).
2. After hardware and software integration, Information Assurance (IA) scans and analysis will be conducted to ensure the system complies with applicable Information Assurance Vulnerability Alerts (IAVA) and Security Technical Implementation Guides (STIGs) requirements to ensure IA hardening and reduce cyber vulnerabilities.
3. Following IA scans, MEI hardware initialization, system operations, data harvesting, and shutdown shall be completed without functional failure and/or error In Accordance With (IAW) the procedures detailed in this document.
1.1 IBCS EOC
The IBCS EOC consists of an S-280 Shelter, which is unmanned during normal operations and the IBCS Collaborative Environment (ICE) HDT® AirBeam tent (see Figure 1-1), which the operators and staff work in. The S-280 Shelter provides two Warfighter Workstations (WFWS) so that operations can be conducted while the ICE) is being setup. IBCS EOCs are configurable mobile deployable facilities used by IFMC Army System of Systems (ASoS) commanders and staffs to control Air and Missile Defense (AMD) forces at Battery (BTRY) through Battalion (BN) echelons. The IBCS EOC incorporates Non-Developmental-Item (NDI), Commercial-Off-The-Shelf (COTS), Government-Furnished Equipment (GFE), and IBCS-developed Common Software Configuration Items (CSCI) within EOC software builds. The EOC shelters host IBCS, battle command and combat service support software suites, communications equipment, and interfaces with numerous non-battle command stations to serve as an information aggregation point.
Figure 1-1. ICE HBT® AirBeam Tent
EOCs utilize a common hardware configuration and can be tailored in software to match the mission requirements of each respective echelon in both size and capability. The BTRY EOC is the standard EOC configuration and includes a single S-280 Shelter, which is transported on a M1148 9-ton truck (see Figure 1-2) and is used to tow the Engagement Center Trailer (ECT). A BN EOC consists of two EOCs connected with a Tactical Fiber Optic Cable Assembly (TFOCA)-II fiber network. One of the BTRY S-280 / ICE pairs is intended for use in planning and support with the second S-280 / ICE pair performing engagement operations. For purposes of this test procedure all EOCs will be tested in the BTRY configuration and any references to an EOC will be understood as BTRY EOCs, unless otherwise delineated.
Figure 1-2. Front Isometric View of EOC Prime Mover & S-280 Shelter
Once setup, the ICE provides the user nine WFWS and one AMDWS workstation. It also provides the user the ability to project every WFWS onto a projector screen (see Figure 1-3 for ICE setup).
Figure 1-3. ICE Interior View
The ICE is powered using shore power or generator power plugged into a power distribution box called an ICE Power Distribution Unit (PDU) (see Figure 1-4).
Figure 1-4. ICE PDU
The ICE PDU provides power for tent lighting along with the projectors and the transit cases that host the WFWS and Local Area Network (LAN) transit cases. The wiring diagram is shown in Figure 1-5.
Figure 1-5. ICE PDU Power Connections
Each ICE has a primary and secondary LAN transit case. The purpose of the primary transit case (see Figure 1-6) is to provide connectivity between the WFWS and the S-280 EOC as well as providing video to the projectors in the ICE.
Figure 1-6. Primary LAN Transit Case
The primary transit case connects via a TFOCA-II fiber to the Red Signal Entry Panel (SEP) (see Figure 1-7) from the primary transit case path panel (see Figure 1-8).
Figure 1-7. Red Road Side SEP
The Red SEP is also where the the A-Sides (Launchers and Sensors) connections are made.
Figure 1-8. Primary LAN Patch Panel
The patch panel also connects the to the WFWS transit cases by TFOCA-II fiber. Each WFWS transit case (see Figures 1-9 and 1-10) allows for two Common Warfighter Machine Interface (CWMI) instances allowing the user to fight or plan a battle.
Figure 1-9. Workstation Transit Case
Figure 1-10. Workstation Transit Case Rear View Close Up
The secondary LAN transit case (see Figure 1-11 and 1-12) connects to the S-280 via a TFOCA-II fiber cable and allows the EOC to be monitored for CO2 and temperature.
Figure 1-11. Secondary LAN Transit Case
Figure 1-12. Secondary LAN Patch Panel
The secondary LAN transit case connects to the S-280’s Black SEP Panel’s (see Figure 1-13) LAN/NIPR port.
Figure 1-13. Black Curb Side SEP
The Black SEP is also where EOCs cab connect together through the Alt. Media ports.
The inside of the S-280 shelter (see Figure 1-14 through 1-16) contains two WFWS to enable fighting while the ICE is being set up. The EOC servers also reside in the S-280 along with tactical radios to be able to communicate with the joint world.
Figure 1-14. S-280 Curbside Interior View
Figure 1-15. S-280 Layout - Top View
Figure 1-16. S-280 Equipment Rack Overview
Rack 1 of the S-280 (see Figure 1-17) contains most of the tactical radios including MIDS and JBC-P. This rack also contains the IFCN radio, the HARRIS BPU, the voice communications box, the eMCSU, along with the EOC’s GPS server.
Figure 1-17. S-280 Rack 1
Rack 2 of the S-280 (see Figure 1-18) contains the rest of the tactical radios including the AN PRC 117Gs, the JTT, and it also houses the maintenance laptop.
Figure 1-18. S-280 Rack 2
Rack 3 of the S-280 (see Figure 1-19) contains the classified printer, the last tactical radio, the CASS receiver, the ADSI (L-16) computer, and the black network components.
Figure 1-19. S-280 Rack 3
Rack 4 of the S-280 (see Figure 1-20) contains the EOC servers, the red side network, and the Cross Domain Solution (CDS). This rack is the heart and brains of the EOC. IBCS software is housed on the servers and allows the user to execute the mission.
Figure 1-20. S-280 Rack 4
The final rack inside the S-280 is the Power Distribution Panel (PDP) (see Figure 1-21) Figure 1-21. S-280 PDP
The PDP is located on the roadside on the inside of the shelter and contains a Carbon Monoxide Detector, which provides an audible alarm if CO reaches dangerous levels and DC Main Circuit Breakers, which provide power on and off for all DC components.
The S-280 gets power from a generator, shore power, or power from another EOC through the Power Entry Vault (PEV) (see Figure 1-22 and 1-23).
Figure 1-22. S-280 PEV Side View
The PEV has several functions. The primary functions include providing prime power point of entry, exporting power to other PEVs and providing power to other subassemblies, and maintaining vehicle battery charge.
Figure 1-23. S-280 PEV Front View
The front SEP (see Figure 1-24) contains the connections that allow connections to other EOCs (through the HRFU connections), through SATCOM (VHF/UHF connections), to the joint community through MIDS (L16), and is the entry for the GPS signal into the timing units.
Figure 1-24. Front View SEP
Table 1‑1. EOC Configurations by Echelon
| Echelon |
| Vehicle |
| S-280 Shelter |
| ICE |
| Trailer |
| BN |
| 2 |
| 2 |
| 2 |
| 2 |
| BTRY |
| 1 |
| 1 |
| 1 |
| 1 |
The S-280 Shelter and IFCN / Highband Radio Frequency Unit (HRFU) antenna mast are mounted on the Container Roll-in/Out Platform (CROP) pallet and are offloaded for operations. The shelter is the basic building block for IBCS EOCs and provides space for two operators. The S-280 shelter includes equipment rack and cabling for IBCS servers and radios. The cable infrastructure provides common interfaces for data, power, radio-frequency (RF) and audio connections in every EOC.
1.2 EOC Lite
An EOC Lite (see Figure 1-25) will be used as a second C2 to test A-Side to A-Side communications during the Acceptance Test. An EOC Lite is operationally equivalent to an IBCS EOC but does not include tactical radios. Therefore, it cannot be used to test radio to radio communications nor does it check functionality of all the hardware components. It may be worthwhile to list which hardware components that are not tested – if Kyle can provide.
Figure 1-25. EOC Lite
1.3 Additional Test Equipment
In addition to the EOC Lite, the following items are needed in order to meet the AT requirements as identified in this document.
Table 1-2. Additional Test Equipment
| Item Description |
| Purpose |
| Part Number |
| 2x RTDRIU and VEST |
| To track and act as an uplinking sensor and missile fly out model. |
| LOTN |
| To act as the ELES and tell the missile fly out model to fly the missile. |
| 2x L2 |
| A simulated LINK box that is hosted on a VM that connects the launcher to the B-Side. |
| NSITE |
| An optional test asset that shows the DIS on a map in order to verify that the targets are being displayed properly on CWMI. |
| GRTTC |
| A DIS player that outputs a scenario to the sensor models and destroys targets depending on the kill PDUs received. |
| 10x TFOCA-II Cables |
| These cables will be used to connect the launchers and sensor from the test tool rack to the UUT. |
2. Test Configurations
2.1 Test Diagrams
There are three test configurations that will be used during AT (see Figures 2-1 through 2-3). However, with an EOC Lite, not all hardware components can be tested because EOC Lites lack tactical radios.
Figure 2-1. S-280-to-ICE
Figure 2- shows how the ICE connects to the S-280 through two TFOCA-II fiber cables.
Figure 2-2. SEP (Black) Ping (w/o Software)
Figure 2-2 shows how to test the Alt Media ports of the UUT.
Figure 2-3. FT3 via ALT Media
Figure 2-3 show the FT3 diagram which will be the main test of the ATP. This test will have a single RTDRIU and 8 launchers plugged into the UUT and a single RTDRIU plugged into the EOC Lite.
3. Pretest Setup
3.1 Grounding
The following steps should be taken prior to powering up any equipment to ensure proper a common ground is established to prevent any harm to equipment damage.
Table 3-1 Grounding of Test Articles
| Step # |
| Operator Actions |
| Expected Results |
| Actual Results |
| Comments/TIR # |
Verify Test Articles Grounding
****CAUTION****
Prior to connecting commercial shore power or applying power to the EOC systems, verify by visual inspection that all equipment has been properly grounded and thresholds are IAW MIL-STD-464A, dated, 19 December 2002, to ensure proper operation and prevent an electrical hazard for the equipment or operator. The thresholds are 10 mOhms or less for inside the shelter and 20 mOhms or less for outside the shelter.
MEI HW is ground to a common facility ground
| 1. |
| Verify Main circuit breaker on UUT EOC is OFF (See |
Figure 1-22. S-280 PEV Side View) EOC main circuit breaker is OFF.
| 2. |
| Verify UUT EOC shelter ground, E1 is connected to earth ground via cable (ALH-213925-0180) (See |
Figure 1-22. S-280 PEV Side View) EOC is grounded to common ground Fig 1-22 lacks this info. But maybe we leave as is.
| 3. |
| Verify UUT EOC shelter ground, E2 is connected to CROP ground stud via cable (ALH-213712-001) (See |
Figure 1-22. S-280 PEV Side View) EOC is grounded to CROP Fig 1-22 lacks this info. But maybe we leave as is.
| 4. |
| Verify HRFU Antenna Mast is connected to CROP ground via cable (ALH-214623-0180) |
| HRFU Antenna Mast is grounded to CROP |
| 5. |
| Verify EOC Lite Rack is connected to common grounded. |
| Red Rack is grounded |
| 6. |
| Verify ICE Primary LAN Transit Case is connected to Secondary LAN Transit Case ground via cable (A501W13) (See Figure 1-6. Primary LAN Transit Case and |
Figure 1-11. Secondary LAN Transit Case) ICE Primary LAN Transit Case and Workstations are grounded to Secondary LAN Transit Case
| 7. |
| Verify ICE Secondary LAN Transit Case is connected to DRASH PDU ground via cable A501W14) (See |
Figure 1-11. Secondary LAN Transit Case and Figure 4. ICE PDU) ICE Secondary LAN Transit Case is grounded to DRASH PDU.
4. Test Procedures
4.1 System Power On
Table 4-4. Power On
| Step # |
| Operator Actions |
| Expected Results |
| Actual Results |
| Comments/TIR # |
Test Configuration:
Figure 2-26. S-280-to-ICE
Initial Shore Power Safety Checkout and Connection
****CAUTION****
In order to prevent unintentional emission of RF energy inside the test facility: 1) Make certain that the HNR BPU(s) are configured for Test mode; 2) Make certain that the RF cables connecting the HRFU antennas are firmly seated.
QA witness
NOTE: Ensure that the test articles and equipment are connected per the Test Configuration drawing.
NOTE: Do Not Install Hard Drives or turn on servers during the initial Power On Sequence. Emergency Power Off will be tested after initial power on.
| 1. |
| Record test start time and PDP hour meter start time on the test procedure. |
| Test start and meter times recorded. |
| QA witness |
| 2. |
| Prior to connecting or applying commercial power, verify that the MAIN POWER circuit breaker is in the OFF (downward) position at the Power Entry Vault (PEV). |
| MAIN POWER circuit breaker on the PEV is OFF. |
| QA witness |
| 3. |
| Prior to connecting or applying commercial power, verify that the EMERGENCY POWER OFF button to the POWER ON (Pulled Out) position at the PDP. (See Figure 1-21. S-280 PDP) |
| EMERGENCY POWER OFF button at the PDP is in POWER ON position. |
| QA witness |
| 4. |
| Prior to connecting or applying commercial power, verify that the PDP power circuit breaker on the PEV is in the OFF position. (See Figure 1-23. S-280 PEV Front View) |
| PDP circuit breaker on the PEV is OFF. |
| QA witness |
| 5. |
| Prior to connecting or applying commercial power, verify that the ECS power circuit breaker on the PEV is in the OFF position. (See Figure 1-23. S-280 PEV Front View) |
| ECS circuit breaker on the PEV is OFF. |
| QA witness |
| 6. |
| Prior to connecting or applying commercial power, verify that the Gas Particulate Filter Unit (GPFU) circuit breaker is OFF at the PEV. (See Figure 1-23. S-280 PEV Front View) |
| GPFU circuit breaker at the PEV is in OFF position. |
| QA witness |
| 7. |
| Prior to connecting or applying commercial power, verify that the MAST circuit breaker is OFF at the PEV. (See Figure 1-23. S-280 PEV Front View) |
| MAST circuit breaker at the PEV is in OFF position. |
| QA witness |
| 8. |
| Prior to connecting or applying commercial power, verify that the CB7 (60A) MAIN POWER circuit breaker on the Power Distribution Panel (PDP) is in the OFF position. (Inside the shelter on the wall between the door and Rack 1) (See Figure 1-21. S-280 PDP) |
| PDP MAIN POWER circuit breaker is in the OFF position. |
| QA witness |
| 9. |
| Prior to connecting or applying commercial power, verify that the CB1 (15A) RACK 1 circuit breaker on the Power Distribution Panel (PDP) is in the OFF position. (See Figure 1-21. S-280 PDP) |
| PDP CB1 (15A) RACK 1 circuit breaker is in the OFF position. |
| QA witness |
| 10. |
| Prior to connecting or applying commercial power, verify that the CB2 (15A) RACK 2 circuit breaker on the Power Distribution Panel (PDP) is in the OFF position. (See Figure 1-21. S-280 PDP) |
| PDP CB2 (15A) RACK 2 circuit breaker is in the OFF position. |
| QA witness |
| 11. |
| Prior to connecting or applying commercial power, verify that the CB3 (15A) RACK 3 circuit breaker on the Power Distribution Panel (PDP) is in the OFF position. (See Figure 1-21. S-280 PDP) |
| PDP CB3 (15A) RACK 3 circuit breaker is in the OFF position. |
| QA witness |
| 12. |
| Prior to connecting or applying commercial power, verify that the CB4 (15A) RACK 4 circuit breaker on the Power Distribution Panel (PDP) is in the OFF position. (See Figure 1-21. S-280 PDP) |
| PDP CB4 (15A) RACK 4 circuit breaker is in the OFF position. |
| QA witness |
| 13. |
| Prior to connecting or applying commercial power, verify that the CB5 (15A) RACK 5 circuit breaker on the Power Distribution Panel (PDP) is in the OFF position. (See Figure 1-21. S-280 PDP) |
| PDP CB5 (15A) RACK 5 circuit breaker is in the OFF position. |
| QA witness |
| 14. |
| Prior to connecting or applying commercial power, verify that the CB6 (5A) Shelter Lighting Protection circuit breaker on the Power Distribution Panel (PDP) is in the OFF position. (See Figure 1-21. S-280 PDP) |
| PDP CB6 (5A) Shelter Lighting Protection circuit breaker is in the OFF position. |
| QA witness |
| 15. |
| Prior to connecting or applying commercial power, verify that the SW1 Shelter Lighting switch on the Power Distribution Panel (PDP) is in the OFF position. (See Figure 1-21. S-280 PDP) |
| PDP SW1 Shelter Lighting switch is in the OFF position. |
| QA witness |
| 16. |
| Prior to connecting or applying commercial power, verify that the Rack 1 Powergrid UPS switch is in the OFF position. (Bottom front of Rack 1.) (See Figure 1-18. S-280 Rack 2) |
| Rack 1 UPS power switch is in the OFF position. |
| QA witness |
| 17. |
| Prior to connecting or applying commercial power, verify that the Rack 2 Powergrid UPS switch is in the OFF position. (Bottom front of Rack 2.) (See Figure 1-18. S-280 Rack 2) |
| Rack 2 UPS power switch is in the OFF position. |
| QA witness |
| 18. |
| Prior to connecting or applying commercial power, verify that the Rack 3 Powergrid UPS switch is in the OFF position. (Bottom front of Rack 3.) (See Figure 1-19. S-280 Rack 3) |
| Rack 3 UPS power switch is in the OFF position. |
| QA witness |
| 19. |
| Prior to connecting or applying commercial power, verify that both Rack 4 Powergrid UPS switches are in the OFF position. (Bottom front of Rack 4.) (See Figure 1-20. S-280 Rack 4) |
| Both Rack 4 UPS power switches are in the OFF position. |
| QA witness |
| 20. |
| Prior to connecting or applying commercial power, verify that both Rack 3 API AC Power Distribution Unit (PDU) switches are in the OFF position. (Near bottom front of Rack 3.) (See Figure 1-19. S-280 Rack 3) |
| Both Rack 3 AC PDU power switches are in the OFF position. |
| QA witness |
| 21. |
| Prior to connecting or applying commercial power, verify that both Rack 4 API AC PDU switches are in the OFF position. (Near bottom front of Rack 4.) (See Figure 1-20. S-280 Rack 4) |
| Both Rack 4 AC PDU power switches are in the OFF position. |
| QA witness |
| 22. |
| Prior to connecting or applying commercial power, verify that the Rack 1 DC Power Supply is in the OFF position. (Next to bottom of Rack 1.) (See Figure 1-17. S-280 Rack 1) |
| Rack 1 DC power supply power switch is in the OFF position. |
| QA witness |
| 23. |
| Prior to connecting or applying commercial power, verify that the Rack 2 DC Power Supply is in the OFF position. (Next to bottom of Rack 2.) (See Figure 1-18. S-280 Rack 2) |
| Rack 2 DC power supply power switch is in the OFF position. |
| QA witness |
| 24. |
| Prior to connecting or applying commercial power, verify that the Rack 3 DC Power Supply is in the OFF position. (Next to bottom of Rack 3.) (See Figure 1-19. S-280 Rack 3) |
| Rack 3 DC power supply power switch is in the OFF position. |
| QA witness |
| 25. |
| Prior to connecting or applying commercial power, verify that the Rack 1 Main DC PDU and DC switches 1 – 12 are in the OFF position. (Third from bottom of Rack 1.) (See Figure 1-17. S-280 Rack 1) |
| Rack 1 DC PDU power switches are in the OFF position. |
| QA witness |
| 26. |
| Prior to connecting or applying commercial power, verify that the Rack 2 Main DC PDU and DC switches 1 – 12 are in the OFF position. (Third from bottom of Rack 2.) (See Figure 1-18. S-280 Rack 2) |
| Rack 2 DC PDU power switches are in the OFF position. |
| QA witness |
| 27. |
| Prior to connecting or applying commercial power, verify that the Rack 3 Main DC PDU and DC switches 1 – 12 are in the OFF position. (Fourth from bottom of Rack 3.) (See Figure 1-19. S-280 Rack 3) |
| Rack 3 DC PDU power switches are in the OFF position. |
| QA witness |
| 28. |
| Prior to connecting or applying commercial power, verify that the Control Power switch on the panel of the ECS evaporator (inside the S-280 shelter) is in the OFF position. |
| ECS evaporator Control Power is OFF. |
| QA witness |
| 29. |
| Prior to connecting or applying commercial power, verify that the Control Power switch on the panel of the GPFU Control Module (inside the S-280 shelter) is in the OFF position. |
| GPFU Control Module is OFF. |
| QA witness |
| 30. |
| Prior to connecting or applying commercial power, verify that the BPU switch is in the WARM position. |
| BPU is set to WARM. |
| QA witness |
| 31. |
| Prior to connecting or applying commercial power, verify that all 4 AN/PRC-117G switches are in the OFF position. |
| AN/PRC-117Gs are OFF. |
| QA witness |
| 32. |
| Prior to connecting or applying commercial power, verify that the CASS switch is in the OFF position. |
| CASS is OFF. |
| QA witness |
| 33. |
| Prior to connecting or applying commercial power, verify that the ADSI switch is in the OFF position. |
| ADSI is OFF. |
| QA witness |
| 34. |
| Prior to connecting or applying commercial power, verify that the MIDS Power Supply and Radio switches are in the OFF position. |
| MIDS is OFF. |
| QA witness |
| 35. |
| Prior to connecting or applying commercial power, verify that the KGV-72, GRM, and Transceiver switches on shelf 2 are in the Off position. (3 switches) |
| KGV-72, GMR, and Transceiver are OFF. |
| QA witness |
| 36. |
| Prior to connecting or applying commercial power, verify that the KGV-72 switch on shelf 5 is in the Off position. |
| KGV-72 is OFF. |
| QA witness |
| 37. |
| Prior to connecting or applying commercial power, verify that the PDU switch on the ICE Primary Local Area Network (LAN) Transit Case is in the OFF position. (See Figure 6. Primary LAN Transit Case) |
| ICE Primary LAN Transit Case PDU is OFF. |
| QA witness |
| 38. |
| Prior to connecting or applying commercial power, verify that the Secondary LAN Transit Case Powergrid UPS and PDU switches iare in the OFF position. (Bottom front of Secondary LAN Transit Case.) ( |
Figure 1-11. Secondary LAN Transit Case)
| Secondary LAN Transit Case UPS power and PDU switches are OFF. |
| QA witness |
| 39. |
| Prior to connecting or applying commercial power, verify that the ICE Workstation Transit Cases (1-5) Powergrid UPS switches and PDU switches are in the OFF position. (Bottom front of Workstation Transit Case.) (See Figure 9. Workstation Transit Case) |
| ICE Workstation Transit Cases (1-5) UPS power switches and PDU switches are OFF. |
| QA witness |
| 40. |
| Prior to connecting or applying commercial power, verify that the switches (P1 – P6) on the ICE PDU is in the OFF position. |
| ICE PDU is OFF. |
| QA witness |
| 41. |
| From the S-280, connect, or verify by physical inspection that commercial / external power is connected to the platform at the J1 Power Import connector on the PEV. (See |
Figure 1-22. S-280 PEV Side View)
| External power is connected |
| QA witness |
| 42. |
| From the ICE, connect, or verify by physical inspection that commercial / external power is connected to the platform at the ICE EMI/EMC filter, which is connected to the ICE PDU. |
| External power is connected |
| QA witness |
S-280 Power Entry Vault (PEV) Initialization
NOTE: If not performing Emergency Power Off and Hard drives are not installed, install Hard drives in servers and workstations.
NOTE: ESD procedures require the operator to wear a wrist strap with the clip end connected to a ground point when handling the HDDs. HDDs are to be stored in anti-static bags when not installed. Drives should never have direct contact with a metal safe drawer, even if in an anti-static bag.
| 43. |
| Set the MAIN POWER circuit breaker to the ON (upward) position at the PEV. (See Figure 1-23. S-280 PEV Front View) |
| MAIN POWER circuit breaker at the PEV is ON |
| QA witness |
| 44. |
| Press the PUSH TO VIEW test button on the PEV to verify that the following three (3) LEDs illuminate: |
· AC POWER, A – AC Power Phase A
· AC POWER, B – AC Power Phase B
· AC POWER, C – AC Power Phase C Three (3) PEV indicator LEDs illuminate
QA witness
| 45. |
| Press the PUSH TO VIEW test button on the PEV to verify that the three (3) LEDs extinguish |
| Three (3) PEV indicator LEDs extinguishes. |
| QA witness |
| 46. |
| Set the PDP circuit breaker to ON at the PEV. (See Figure 1-23. S-280 PEV Front View |
| PDP circuit breaker at the PEV is ON |
| QA witness |
| 47. |
| Set the ECS circuit breaker to ON at the PEV. (See Figure 1-23. S-280 PEV Front View |
| ECS circuit breaker at the PEV is ON |
| QA witness |
| 48. |
| Set the GPFU circuit breaker to ON at the PEV. (See Figure 1-23. S-280 PEV Front View |
| GPFU circuit breaker at the PEV is ON |
| QA witness |
| 49. |
| Set the MAST circuit breaker to ON at the PEV (See Figure 1-23. S-280 PEV Front View) |
| MAST circuit breaker at the PEV is ON |
| QA witness |
S-280 Power Distribution Panel (PDP) Initialization
| 50. |
| Set the MAIN BREAKER (CB7) on the Power Distribution Panel (PDP) to the ON position. (See Figure 1-21. S-280 PDP) |
| MAIN BREAKER at the PDP is ON |
| QA witness |
| 51. |
| At the PDP, set circuit breakers CB1, CB2, CB3, CB4, and CB6 in numerical order, to the ON (upward) position. CB5 is for future expansion and is not used. CB5 should remain in the OFF position. (See Figure 1-21. S-280 PDP) |
| Circuit breakers CB1, CB2, CB3, CB4, and CB6 are set to ON. CB5 remains set to OFF. |
| QA witness |
| 52. |
| Set the SW 1 SHELTER LIGHTING on PDP to ON. (See Figure 1-21. S-280 PDP) |
| Shelter lighting is on. |
| QA witness |
S-280 Environmental Control System (ECS) Initialization
****CAUTION****
Prior to starting the ECS, verify that the transport cover has been removed from the exterior of the ECS condenser (outside unit). Running the ECS with the cover in place will cause damage to the unit.
QA witness
| 53. |
| Switch the Control Power switch on the panel of the ECS evaporator (inside the shelter) from the OFF position to the ON position. |
Switch the Operating Mode selector from the OFF position to the FAN, HEAT or COOL position, as desired. Adjust temperature selector, as desired.
NOTE: Normal operating conditions indicate COOL mode and a temperature setting in the middle of the hot and cold range. Ensure that the outside air vents are closed for normal (unattended) operation.
NOTE: Do not set AC temperature below 68oF
| EOC Shelter ECS is powered on to the proper setting for local climatic conditions. |
| QA witness |
| 54. |
| Switch the Control Power switch on the panel of the GPFU Control Module (inside the shelter) from the OFF position to the ON position. |
Note: Ensure all vents are closed and door is shut.
· Open shelter door to prove that alarm sounds.
GPFU alarm sounds and when shelter is pressurized, the light extinguishes and the alarm stops.
Alarm sounds QA witness
| 55. |
| Switch the Control Power switch on the panel of the GPFU Control Module (inside the shelter) from the ON position to the OFF position. |
Note: Open fresh vents to return to normal operational state
| GPFU is OFF and vents returned to normal state |
| QA witness |
S-280 Rack AC & DC Power Supply Initialization
| 56. |
| Turn Rack 1 Powergrid UPS ON. |
| Rack 1 UPS power switch is ON. |
| QA witness |
| 57. |
| Turn Rack 2 Powergrid UPS ON. |
| Rack 2 UPS power switch is in the ON position. |
| QA witness |
| 58. |
| Turn Rack 3 Powergrid UPS ON. |
| Rack 3 UPS power switch is in the ON position. |
| QA witness |
| 59. |
| Turn both Rack 4 Powergrid UPS ON. |
| Both Rack 4 UPS power switches are in the ON position. |
| QA witness |
| 60. |
| Turn both Rack 3 API AC PDUs ON. (Near bottom front of Rack 3.) |
| Both Rack 3 AC PDU power switches are in the ON position. |
| QA witness |
| 61. |
| Turn both Rack 4 API AC PDUs ON. (Near bottom front of Rack 4.) |
| Both Rack 4 AC PDU power switches are in the ON position. |
| QA witness |
| 62. |
| Turn CDS rocker switch to ON. (Near middle front of Rack 4.) |
| CDS is ON, blue light is illuminated. |
| QA witness |
| 63. |
| Turn Rack 1 DC Power Supply ON. (Next to bottom of Rack 1.) |
| Rack 1 DC power supply power switch is in the ON position. |
| QA witness |
| 64. |
| Turn Rack 2 DC Power Supply ON. (Next to bottom of Rack 2.) |
| Rack 2 DC power supply power switch is in the ON position. |
| QA witness |
| 65. |
| Turn Rack 3 DC Power Supply ON. (Next to bottom of Rack 3.) |
| Rack 3 DC power supply power switch is in the ON position. |
| QA witness |
| 66. |
| Turn Rack 1 DC PDU ON. (Third from bottom of Rack 1.) |
Note: Wait until self-test completes, then turn on rest of toggle switches (1 – 12).
| Rack 1 DC PDU power switch is in the ON position. |
| QA witness |
| 67. |
| Turn Rack 2 DC PDU ON. (Third from bottom of Rack 2.) |
Note: Wait until self-test completes, then turn on rest of toggle switches (1 – 12).
| Rack 2 DC PDU power switch is in the ON position. |
| QA witness |
| 68. |
| Turn Rack 3 DC PDU ON. (Third from bottom of Rack 3.) |
Note: Wait until self-test completes, then turn on rest of toggle switches (1 – 12).
| Rack 3 DC PDU power switch is in the ON position. |
| QA witness |
| 69. |
| Turn Maintenance laptop (IETM) on Rack 2 to ON. |
| Maintenance Laptop is ON. |
| QA witness |
| 70. |
| Turn Network Management laptop on Rack 3 to ON. |
| Network Management laptop is ON. |
| QA witness |
| 71. |
| Turn KGV-72, GMR with GPS, and Transceiver in Rack 1, shelf 2 to ON. (3 switches) |
| KGV-72, GMR, and Transceiver are ON |
| QA witness |
| 72. |
| Turn KGV-72 in Rack 1, shelf 5 to ON. |
| KGV-72 is ON |
| QA witness |
| 73. |
| Turn Blue Force Tracker to ON. |
| Blue Force Tracker is ON |
| QA witness |
| 74. |
| Turn Sound Commander Amplifier on Rack 3 to On |
| Sound Commander Amplifier is ON. |
| QA witness |
| 75. |
| Turn all four AN/PRC-117G switches to the PT position. |
| AN/PRC-117Gs are PT. |
| QA witness |
| 76. |
| Turn the CASS switch to the ON position. |
| CASS is ON. |
| QA witness |
| 77. |
| Turn the ADSI switch is in the ON position. |
| ADSI is ON. |
| QA witness |
| 78. |
| Turn the MIDS Power Supply, then push in and rotate the radio switches to the ON position. |
| MIDS is ON. |
| QA witness |
| 79. |
| Turn the KVM to the ON position. |
| KVM is ON. |
| QA witness |
| 80. |
| Make a note of the local time that power is applied to the EOC Shelter internal systems. |
| Time is noted |
| QA witness |
Configure KG-250
| 81. |
| Verify serial number of its associated S-280 key and KG-250X match. |
Note: CIK must be provisioned SECRET when system has software and UNCLASS when system does not have software before use.
| KG-250X and key match |
| QA witness |
| 82. |
| If CIK key is not inserted in the UUT |
Insert the correct Crypto Ignition Key (CIK) into the KG-250X and press KG-250X POWER button Wait until the ALARM LED extinguishes and the PWR/READY LED turns green.
| KG-250X is on and PWR/READY LED illuminates green |
| QA witness |
Note: If KG-250 READY LED does not turn green in 5 minutes press RESET on KG-250
ICE Power Up
NOTE: Skip this section if performing Emergency Power On.
| 83. |
| Turn ICE PDU Power ON (Switches P1 – P6). |
| ICE PDU is ON. |
| QA witness |
| 84. |
| Turn the Secondary LAN Transit Case Powergrid UPS switch to the ON position. (Bottom front of Secondary LAN Transit Case.) (See |
Figure 1-11. Secondary LAN Transit Case)
| Secondary LAN Transit Case UPS is ON. |
| QA witness |
| 85. |
| Turn the PDU switch on the ICE Secondary LAN Transit Case to the ON position. (See Figure 1-12. Secondary LAN Patch Panel) |
| ICE Secondary LAN Transit Case PDU is ON. |
| QA witness |
| 86. |
| Turn the PDU switch on the ICE Primary LAN Transit Case to the ON position.) (See Figure 6. Primary LAN Transit Case) |
| ICE Primary LAN Transit Case PDU is ON. |
| QA witness |
| 87. |
| Turn the ICE Workstation Transit Cases (1-5) Powergrid UPS and PDU switches to the ON position. (Bottom front of Workstation Transit Case.) (See Figure 1-12. Secondary LAN Patch Panel) |
| ICE Workstation Transit Cases (1-5) UPS power and PDU switches are ON. |
| QA witness |
| 88. |
| Make a note of the time that power is applied to the ICE primary LAN equipment. |
| Time is noted |
| Time ________ |
QA _________
| 89. |
| Turn both projectors ON. |
Verify lens caps are removed.
| Both projectors are ON |
| QA witness |
| 90. |
| Turn Sound Commander ON |
| Sound Commander is ON |
| QA witness |
EOC Network Components Initialization
NOTE: The EOC primary and secondary LAN components initialize automatically when power is applied. A high fan sound and whine is normal during initialization.
| 91. |
| Ensure S-280 Rack 3 network devices are powered up. |
| Verify that the following Rack 3 components are powered on: Cisco 5508 firewall, Cisco 4351 router, and Cisco 4321 router. |
| QA witness |
| 92. |
| Ensure S-280 Rack 4 network devices are powered up. |
| Verify that the following Rack 4 components are powered on: 2 Cisco 3850 switches, Cisco 5508 firewall, Cisco 4321 router, and Cisco 4351 router. |
| QA witness |
| 93. |
| Note: Skip if performing Emergency Power OFF |
Ensure ICE Primary LAN Transit Case network devices are powered up.
| Verify that the following ICE Primary LAN Transit Case components are powered on: Cisco 3850 switch, and Cisco 4500 switch. |
| QA witness |
| 94. |
| Note: Skip if performing Emergency Power OFF |
Ensure ICE Secondary LAN Transit Case network devices are powered up.
| Verify that the following ICE Secondary LAN Transit Case components are powered on: Cisco 3850 switch. |
| QA witness |
EOC Processing Components Initialization
| 95. |
| Verify that the Primary LAN (red side) switch and router have fully initialized (switch ports show actively blinking GREEN lights) and that the Spectracom SecureSync timing unit has synced and fully initialized (Sync light is GREEN and Fault light has extinguished). Document the time displayed on the SecureSync Network Time Protocol (NTP) Server. |
| Primary LAN is initialized |
Timing unit is synced and initialized
QA witness
| 96. |
| Verify that the NTP server is displaying STRAT = 1 and SYNC = Y. |
| NTP server is sync’d |
| QA witness |
| 97. |
| On Rack 4, toggle the POWER switch on the front of VM Server 1 and allow it to begin initialization. |
| VM Server 1 begins initialization. |
| QA witness |
| 98. |
| On Rack 4, toggle the POWER switch on the front of VM Server 2 and allow it to begin initialization. |
| VM Server 2 begins initialization. |
| QA witness |
| 99. |
| On Rack 4, toggle the POWER switch on the front of VM Server 3 and allow it to begin initialization. |
| VM Server 3 begins initialization. |
| QA witness |
| 100. |
| On Rack 4, toggle the POWER switch on the front of VM Server 4 and allow it to begin initialization. |
| VM Server 4 begins initialization. |
| QA witness |
| 101. |
| On Rack 4, toggle the POWER switch on the front of Security Server and allow it to begin initialization. |
| Security Server begins initialization. |
| QA witness |
| 102. |
| On Rack 4, toggle the POWER switch on the front of Stand-In Server 1 and allow it to begin initialization. |
| Stand-In Server 1 begins initialization. |
| QA witness |
| 103. |
| On Rack 4, toggle the POWER switch on the front of Stand-In Server 3 and allow it to begin initialization. |
Note: Wait 10 minutes for initialization, unless performing EPO.
| Stand-In Server 3 begins initialization. |
| QA witness |
| 104. |
| Press POWER button on both operator Workstation servers in Rack 4. |
NOTE: Ensure operator Workstation monitors are turned on and respond to Workstation initialization. Also, verify keyboard and mouse respond to commands, unless performing EPO..
| Both S-280 Workstations power on. |
| QA witness |
| 105. |
| Press POWER button on all ten (10) ICE operator Workstation servers in Workstation Transit Cases (1-5). (See Figure 1-12. Secondary LAN Patch Panel) |
NOTE: Skip if performing Emergency Power OFF.
NOTE: Do Not Power on ICE Workstations at initial power up, this will put them in a state for Emergency Power OFF.
NOTE: Ensure operator Workstation monitors are turned on and respond to Workstation initialization. Also, verify keyboard and mouse respond to commands.
Ten (10) ICE Workstations power on.
QA witness
4.2 S-280 Lights
Table 4-5. S-280 Lights
| Step # |
| Operator Actions |
| Expected Results |
| Actual Results |
| Comments/TIR # |
Test Configuration:
S-280 Lights
| 1. |
| Set the SW 1 SHELTER LIGHTING on PDP to ON (See Figure 1-21. S-280 PDP) |
| Shelter lighting is on. |
| QA witness |
| 2. |
| Set the SHELTER LIGHTING MODE switch on the PDP to BLACKOUT ONLY. See (Figure 1-21. S-280 PDP) |
| Shelter blackout lighting is on. |
| QA witness |
| 3. |
| Open then close shelter door. |
| Shelter blackout lighting remains on and unchanged. |
| QA witness |
| 4. |
| Set the SHELTER LIGHTING MODE switch on the PDP to WHITE ONLY. (See Figure 1-21. S-280 PDP |
| Shelter white lighting is on. |
| QA witness |
| 5. |
| Open then close shelter door. |
| Shelter white lighting remains on and unchanged. |
| QA witness |
| 6. |
| Set the SHELTER LIGHTING MODE switch on the PDP to AUTOMATIC BLACKOUT/WHITE. (See Figure 1-21. S-280 PDP) |
| Shelter lighting is on. |
| QA witness |
| 7. |
| Open then close shelter door. |
| Shelter white lighting switches to blackout lighting when door opens then returns to white lighting when door shuts. |
| QA witness |
| 8. |
| Change back to WHITE ONLY |
| Lights are WHITE ONLY |
| QA witness |
4.3 EOC Emergency Power Off
Table 4-6. EOC Emergency Power Off
| Step # |
| Operator Actions |
| Expected Results |
| Actual Results |
| Comments/TIR # |
Test Configuration
Emergency Power Off
****Caution**** To avoid possible software corruption related to emergency loss of power no hard drives should be installed.
| 1. |
| Push the Emergency Power Button OFF. (See Figure 1-21. S-280 PDP) |
| All power to S-280 components, and UPS are powered OFF, with exception to Maintenance laptop, Network Management laptop, and Sound Commander Alarm Amplifier.. |
| QA witness |
| 2. |
| Power OFF Maintenance Laptop (Rack 2) |
| Maintenance Laptop is powered OFF |
| QA witness |
| 3. |
| Power OFF Network Management Laptop (Rack 3) |
| Network management Laptop is powered OFF |
| QA witness |
| 4. |
| Depress mic push-to-talk button and speak into mic, slowly turning volume knob clockwise until the desired volume is reached. |
| Amplified voice is heard over speaker array |
| QA witness |
| 5. |
| Push Horn Button for 2 seconds and release. |
| Horn sounds and silenced |
| QA witness |
| 6. |
| Alternate between Yelp and Wail by using rocker switch, then place rocker switch in neutral position. |
| Yelp and Wail sounds and silenced. |
| QA witness |
| 7. |
| Power OFF Sound Commander Alarm Amplifier (Rack 3) |
| Sound Commander Alarm Amplifier is powered OFF. |
| QA witness |
| 8. |
| Return system to operational state by using the Power On Procedures |
| System powered ON. |
| QA witness |
4.4 ADSI Initialization
Table 4-7. ADSI Initialization
| Step # |
| Operator Actions |
| Expected Results |
| Actual Results |
| Comments/TIR # |
Test Configuration:
EOC Power Up
NOTE: If EOC is already powered up, skip to the ADSI Initialization section.
NOTE: Prior to using ADSI, it is necessary to verify that the system date and time are correct. This must be done with ADSI drives removed. Do not install ADSI drives at this time.
IBCS software must be installed to complete this test.
NOTE:
Ensure that the KG-250X has been loaded with classified test keys prior to performing test. Check the latest configuration documentation to verify that the KG-250X has been loaded with the correct keys.
****CAUTION****
Unless trained and familiar with its operation and fully briefed on Communications Security (COMSEC) and cryptographic security procedures, the operator must not attempt to operate the KG-250X equipment. Incorrect operation can result in a serious security incident.
QA witness
NOTE: Ensure that the KG-250X has its associated CIK inserted. Each CIK key is labeled with the serial number of its associated EOC and KG-250X.
QA witness
| 1. |
| Verify that the PWR/READY LED is illuminated GREEN, indicating that the KG-250X is powered ON and ready. |
NOTE: If the KG-250X is not powered on, press the ON / OFF button on the front panel of the KG-250X to power ON the unit. Observe the KG-250X until the ZEROIZE, ALARM and LO BATT red LEDs extinguish in succession and the PWR/READY LED turn from red to green. If after 60 seconds the PWR/READY light stays RED, press the KG-250X RESET button. All lights on the KG-250X will turn RED then to GREEN.
| PWR/READY LED is illuminated green on KG-250X |
| QA witness |
| 2. |
| On the BPU front panel verify the following LED indicators |
Crypto – green Nav System – green Xmit enable green 1 Link – green Data Xmit – blinking green
NOTE: SYSTEM FAIL LED should be extinguished. If it is blinking red ensure Timing Unit is sync’d and IGRM is displaying GPS locked and wait for LED to extinguish. If solid red and SCIM displays GPS locked, reset the BPU and wait for LED to extinguish.
| The SCIM Panel SYSTEM FAIL LED is extinguished. |
| QA witness |
ADSI Initialization
NOTE: If ADSI software is not installed skip this section and MIDS Initialization. Go to the Radio Power UP section.
| 3. |
| Slide out KVM in Rack 2 and switch POWER on |
| KVM splash screen displays |
| QA witness |
| 4. |
| On the Rack 2 KVM select the ADSI Linux server using the following commands: |
· Double press the Shift key
· Use the [ / ] keys to select the desired server
· Press Enter
| The KVM screen should be blank since the ADSI is off. |
| QA witness |
| 5. |
| NOTE: ESD procedures require the operator to wear a wrist strap with the clip end connected to a ground point when handling the HDDs. HDDs are to be stored in anti-static bags when not installed. Drives should never have direct contact with a metal safe drawer, even if in an anti-static bag. |
Install both ADSI hard drives and ensure they are proper installed with seating screws tightened down.
| ADSI TSDW (CPU 1) | ADSI MDB/MLIU (CPU 2) | |
| ADSI hard drives are installed. | ||
| QA witness |
| 6. |
| On Rack 3, turn on the ADSI Server via POWER switch on the front of ADSI Server. |
NOTE: Both ADSI drives should BE installed at this point.
| ADSI Server begins initialization. |
| QA witness |
| 7. |
| On the Rack 2 KVM select the ADSI Windows server using the following commands: |
· Press and release CTRL
· Press and release Esc
· Use the arrow up / down keys to select the desired server
| ADSI Windows splash screen appears. |
| QA witness |
| 8. |
| Login to ADSI using Admin credentials |
| ADSI Windows screen appears. |
| QA witness |
| 9. |
| Open the ADSI System Manager window by: |
· Click on the Windows START button
· Navigate to ALL PROGRAMS > ULTRA ELECTRONICS INC > ADSI
· Select “System Manager”
NOTE: If the Application Status panel is not present, Select View from the menu bar and click the box for Application Status.
| The ADSI System Manager windows is displayed. |
| QA witness |
| 10. |
| Verify that the ADSI is connected. |
In the APPLICATION STATUS panel in the lower right side of the ADSI System Manager Application window, verify that the COMPACT PCI shows a status of CONNECTED.
| ADSI is in connected status |
| QA witness |
| 11. |
| Click on START and wait for the ADSI COMPACT PCI to indicate RUNNING. |
| ADSI COMPACT PCI is running. |
| QA witness |
| 12. |
| In the DATA LINKS panel on the right side of the ADSI System Manager application window, verify that the MIDS LVT-11 link is checked and is ON (YELLOW) or OPER (GREEN). |
NOTE: The external data link will remain yellow until it is activated.
| MIDS LVT-11 link is on or operational. |
| QA witness |
| 13. |
| In the SECONDARY/INTEL INTERFACES panel on the right side of the ADSI System Manager application window, verify that the IBCS link is checked and is ON (YELLOW) or OPER (GREEN). |
| IBCS link is on or operational. |
| QA witness |
| 14. |
| Verify ADSI time synchronization by: |
· Select the SYSTEM STATUS tab from the System Manager menu bar
· In the SYSTEM TIME / NETWORK TIME PROTOCOL panel, verify that the Compact PCI has a GREEN CHECK for its time sync NOTE: if the time synchronization is not within 3 seconds, click: RE-SYNC.
| ADSI time is sync’d to SCIM. |
| QA witness |
| 15. |
| Select the SYSTEM CONFIGURATION tab from the System Manager menu bar |
| ADSI SYSTEM CONFIGURATION is displayed. |
| QA witness |
| 16. |
| Verify the ADSI time settings for the External Data Link |
· Select TACTICAL DATA LINKS menu on the left panel
· Select the MIDS LVT-11data link
· Select; EDIT LINK
· In the CONFIGURE LINK pop-up window, select; ADVANCED SETTINGS
· Verify that the COMMON TIME REFERENCE OPTIONS are set to UTC
· Select; OK
| ADSI data links use UTC. |
| QA witness |
| 17. |
| Verify that the ADSI is including JU (JTDS Unit Number) data |
· Select MIL-STD RULES SETTINGS
· In the panel for C2 INDICATOR BYPASS, ensure that the radio button for ENABLED is selected
| ADSI is including JU data. |
| QA witness |
| 18. |
| Verify / set ADSI forwarding settings |
· Select the FORWARDING tab from the System Manager menu bar
· Select DATA LINK FORWARDING from the left hand menu
· Near the bottom of the tab click on ENABLE ALL
· Select APPLY
| ADSI is forwarding data both ways between the Host and MIDS LVT-11 (link table doesn’t contain any red X’s) |
| QA witness |
| 19. |
| Verify / set ADSI C2 host forwarding settings |
· Select C2 HOST FORWARDING from the left hand menu
· Near the bottom of the tab click on ENABLE ALL
· Select APPLY
| ADSI is forwarding data both ways between Local Data, Tactical Links, and CSI (link table doesn’t contain any red X’s). |
| QA witness |
| 20. |
| Verify ADSI positional data |
· Select the SITE DATA tab from the System Manager menu bar
· On the left hand menu select POSITIONAL DATA
| ADSI positional data fields are populated with system values. |
| QA witness |
| 21. |
| Set ADSI JTDS data |
· Select JTDS SPECIFIC DATA on the left hand menu
· Set the value for the TIME, POSITION, & ALTITUDE/DEPTH parameters to ‘15’
· Set the value for the RELATIVE POSITION QUALITY parameter to ‘15’
· Set the value for the RELATIVE AZIMUTH QUALITY parameter to ‘7’
· Click APPLY
| JTDS data is set. |
| QA witness |
| 22. |
| Verify ADSI secondary data settings |
· Select the SECONDARY DATA tab from the System Manager menu bar
· Ensure that the C2 check box is checked in the INDICATORS panel (on the right)
| The ADSI C2 box is checked. |
| QA witness |
| 23. |
| Verify / set ADSI DX settings |
· Select the DX CONTROL tab from the System Manager menu bar
· Select LAUNCH DX VIEW
· If required, change the classification from unclassified to SECRET
· From the System Manager window, in the DX CONTROL tab on the left hand menu, select DATA LINKS
· Set the DX DISPLAY and DX RECORDING drop boxes for C2 Host and TDLG to MSG
· For the MIDS LVT-11 link, in the SET ALL LINKS section, set DX DISPLAY and DX RECORDING to MSG+IO
· Click on APPLY
| ADSI DX settings are correct. |
| QA witness |
| 24. |
| Verify / set ADSI intel and secondary links |
· Select the INTEL/SECONDARY LINKS tab on the left hand menu
· For the IBCS link, in the SET ALL LINKS sections, set DX DISPLAY to; MSG+IO
· For the IBCS link, in the SET ALL LINKS section, set DX RECORDING to; MSG
· Click on APPLY
| ADSI intel and secondary links are configured. |
| QA witness |
4.5 UPS Continuity and Power Down
Table 4-8. UPS Continuity & Power Down
| Step # |
| Operator Actions |
| Expected Results |
| Actual Results |
| Comments/TIR # |
Test Configuration:
EOC Power On
| 1. |
| If system is not powered up, execute Power On steps |
Note: EOC and ICE must have OIV and FCN running to execute steps below.
| EOC and ICE are powered up. |
| QA witness |
EOC Failover to UPS
| 2. |
| Log on to all ICE workstations. |
| Linux main user screen displayed on Operator workstation. |
| QA witness |
| 3. |
| Slide out KVM in Rack 2 and switch POWER ON. (See Figure 1-18. S-280 Rack 2) |
| KVM splash screen displays |
| QA witness |
| 4. |
| Ensure network systems have been powered on for at least 10 minutes |
| Network is powered on and configured for IBCS operations |
| QA witness |
| 5. |
| Record time prior to power off. Turn all power off to the S-280 by switching the PEV Main circuit breaker OFF. (See |
Figure 1-22. S-280 PEV Side View)
| S-280 UPS alarm sounds. All S-280 components continue to operate on UPS power. |
| Time: |
| 6. |
| Turn all power off to the ICE by switching the main ICE PDU OFF. |
| ICE UPS alarm sounds. ICE components continue to operate on UPS power. |
| QA witness |
ADSI Shutdown
NOTE: If ADSI software is not installed skip this section and go to Server & Workstation Shutdown.
| 7. |
| On the Rack 2 KVM (See Error! Reference source not found.. Rack 2) select the ADSI Windows server using the following commands: |
· Double press the Shift key
· Use the [ / ] keys to select the desired server
· Press Enter
| The ADSI Windows login screen is displayed. |
| QA witness |
| 8. |
| Log on to Windows ADSI as admin: |
· Launch the System Manager application by double-clicking on the Ultra Electronics V15 icon from the desktop
| The ADSI Windows screen is displayed. |
| QA witness |
| 9. |
| Shutdown the Command and Control (C2) Host using the following steps: |
· On the top menu bar select TOOLS
· Mouse down to System Shutdown
· Mouse over to CompactPCI
· Click on Halt (Yes)
| C2 Host shuts down |
| QA witness |
| 10. |
| Shutdown the Windows side of ADSI using the following commands: |
· Click on the bottom left Windows START button
· Click on Windows Security
· Click on the shutdown icon on the lower right corner of blue screen
· Click to confirm shutdown
| The KVM display is blank because the Windows side of ADSI is powered off. |
| QA witness |
Server & Workstation Shutdown
| 11. |
| Shutdown EOC application servers via ICE workstation doing the following: |
· Select Applications
· Select EOC Management
· Select EOC Shutdown
· Enter Password
· Select Option 4
· Type Yes All ICE operator workstations, individual VMs and the Security server are OFF.
NOTE: Virtual servers are shutdown, but physical…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .