Attachment 0003- Request for Clarification.xls
XLS spreadsheet 52 KB Posted
- Solicitation number
- W519TC-23-Q-2220
About this file
This solicitation requests quotes for the procurement and installation of metal shelving units for warehouses at Khashm-Al-An Riyadh, Kingdom of Saudi Arabia. The United States Army Contracting Command- Rock Island will award a firm fixed price contract for the metal shelving assembly and installation in accordance with the statement of work and specifications. Offerors must submit any clarification questions by May 30th, 2023 using the request for clarification template provided. Quotes are due by the date listed in block 13 of the solicitation. The Army Materiel Command Contracting Command Rock Island Arsenal will evaluate quotes and award to the responsive, responsible offeror with the lowest priced technically acceptable proposal.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFC-Front
| Request for Clarification | ||
| SECTION-A (To be filled by Contractor) | ||
| Contract Number: | Date: | |
| Project Name: | RFC No.: | |
| RFI Description: | ||
| Specification Section: | ||
| Drawing Number: | ||
| SECTION-B (To be filled by Contractor) | ||
| Requested Clarification Information (for more space continue on back sheet): | ||
| Contractor's Recommended Action (for more space continue on back sheet): | ||
| Submitted by: | Impact Mark 'X' if applies): | |
| Cost | ||
| Date: | Time | |
| SECTION-C (To be filled to COR/MNG) | ||
| Response from COR & MNG: | ||
| COR: | MNG: | Recommendation to KO: |
| Concur | ||
| Date: | Date: | Non-concur |
| SECTION-D (To be filled by Contracting Officer) | ||
| Response from Contracting Officer: | ||
| KO: | Contractor's RFC is: | |
| Concurred with | ||
| Date: | Disagreed with |
&CPage &P
RFC-Back
| Request for Clarification | |||
| SECTION-A (To be filled by Contractor) | |||
| Contract Number: | ='RFC-Front'!C3:F3 | Date: | 31-Dec-99 |
| Project Name: | ='RFC-Front'!C4:F5 | RFC No.: | ='RFC-Front'!H4:I5 |
| RFI Description: | ='RFC-Front'!C6:I6 | ||
| Specification Section: | ='RFC-Front'!C7:I7 | ||
| Drawing Number: | ='RFC-Front'!C8:I8 | ||
| SECTION-B (To be filled by Contractor) | |||
| Requested Clarification Information (continuation): | |||
| Contractor's Recommended Action (continuation): |