Attachment_0002__Statement_of_Work.pdf
PDF 84 KB Posted
- Attached to
- Replacement HVAC System CBVC ADMIN, Chickamauga Ch Federal contract opportunity
- Solicitation number
- 140P5126Q0016
About this file
This is a Statement of Work (SOW) for the complete replacement of Mitsubishi mini-split HVAC systems at Chickamauga/Chattanooga National Military Park, issued by the National Park Service. The project (PMIS 314962A) is structured as a Firm-Fixed-Price contract requiring the contractor to procure, install, and commission 18 new Mitsubishi outdoor units and 18 new Mitsubishi high-wall indoor units (or approved equivalent models) of appropriate sizing and capacity to match or exceed the performance of existing units being replaced. The contractor must also remove and properly dispose of 18 existing outdoor units and 18 existing indoor units in compliance with EPA refrigerant handling regulations, with disposal costs included in the fixed price. All equipment must be new, currently manufactured, and registered for full manufacturer warranty upon installation.
Installation work includes retrofitting refrigerant line sets with UV-resistant covers, installing low-voltage control wiring in raceways, installing digital remote thermostats for each zone, and installing properly sloped condensate drain lines compliant with local codes. The contractor must perform comprehensive system startup and commissioning with verification of electrical parameters and full operational testing of all 18 zones in heating and cooling modes. Deliverables required before final payment include signed start-up and commissioning reports for all eight outdoor units, warranties and O&M manuals in hard copy and digital format, minimum one-hour training for NPS personnel on system operation and troubleshooting, final project record drawings showing component locations and line set routing, and proof of proper refrigerant disposal. Work shall be performed during normal park administrative hours (7:00 AM–4:00 PM, Monday–Friday) unless otherwise approved by the Contracting Officer's Representative to minimize disruption. The contractor must exercise extreme caution near historic structures and comply with the Secretary of the Interior's Standards for Historic Preservation, with any damage repaired at the contractor's expense.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5126Q0016_Amd_0002.pdf | ||
| Attachment_0009__Questions_and_Answers_0002.pdf | ||
| Attachment_0008__Revised_Amd_2_Statement_of_Work_0002.pdf | ||
| Attachment_0007__Revised_Statement_of_Work_0001.pdf | ||
| Sol_140P5126Q0016_Amd_0001.pdf | ||
| Attachment_0006__Revised_Solicitation_Clause_0001.pdf | ||
| Attachment_0001__Solicitation_Clause.pdf | ||
| Attachment_0005__Past_Performance.docx | DOCX document | |
| Sol_140P5126Q0016.pdf | ||
| Attachment_0004__Price_Schedule.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) for HVAC System Replacement-PMIS 314962A
Project Title: Mitsubishi Mini-Split HVAC System Replacement Location:
Chickamauga/Chattanooga National Military Park (CHCH) Contracting Agency: National Park Service (NPS)
1.0 Introduction and Background
and replace existing Mitsubishi mini-split HVAC systems with new, comparable, and energy- within designated facilities at the Chickamauga/Chattanooga National Military Park.
2.0 Scope of Work
The Contractor shall perform a complete, turnkey replacement of the existing
- -Price contract, and the Contractor is solely responsible for ensuring the new systems are installed, tested, and operational in compliance with all applicable federal, state, and local codes, and the Secretary of the Interior's Standards for Historic Preservation where applicable.
The Contractor shall execute the following tasks:
Procure eight (1 -split outdoor units and -wall indoor units (or approved exceed the performance of the units being replaced.
for the full manufacturer’s warranty upon installation.
Develop and submit a detailed Accident Prevention Plan (APP) and Construction Schedule Representative (COR) for approval prior to the start of work.
A site visit is highly suggested.
3.2 Removal and Disposal of Existing Units
Safely decommission and evacuate refrigerant from eighteen (18) existing outdoor units and eighteen (18) existing indoor units in compliance with EPA regulations, including proper handling of refrigerants.
Carefully disconnect and remove all associated refrigerant line sets, wiring, and condensate lines.
-site at an approved recycling or disposal facility. The disposal cost shall
3.3 New System Installation
Install eighteen (1 in the same general locations as the units being replaced, ensuring proper mounting and vibration isolation.
Install -wall indoor units in the exact same interior locations as the units being replaced.
Install new refrigerant line sets for all new systems. All line sets shall be insulated and protected using new UV-resistant line set covers/raceways to match the aesthetic of the building exterior.
Install new low-voltage control wiring between all indoor and outdoor units, routed discreetly and protected in raceways.
Install new digital remote thermostats and calibrated for optimal performance.
Install new, properly sloped condensate drain lines for all indoor units, ensuring compliance with local drainage codes and park aesthetics.
3.4 System Start-up and Testing
Charge the new systems with the appropriate refrigerant type and
Perform a comprehensive system startup and commissioning, including
Conduct a full operational test of all in both heating and cooling modes to ensure the systems meet manufacturer
The Contractor shall
A. Start-up and Commissioning Reports for all eight outdoor units, including refrigerant charge, system pressures, and test results.
B. Warranties and Manufacturer Documentation (hard copy and digital format), including Operation and Maintenance (O&M) manuals, C. Training for NPS personnel (minimum one hour) on the operation, programming, and basic troubleshooting of the new digital remote thermostats and indoor units.
D. Project Record Drawings of all major components and line set routing.
E. Proof of proper refrigerant disposal.
5.0 Government Furnished Property (GFP)
The Government (NPS) will provide access to the work areas and existing materials will be provided by the Government.
6.0 Schedule and Place of Performance
Place of Performance: Chickamauga/Chattanooga National Military will be provided in the Notice to Proceed (NTP).
Period of Performance: The work shall be completed within [Insert Number] calendar days from the issuance of the Notice to Proceed
(NTP).
Work Hours: Work shall generally be performed during normal park disruption to park operations and visitors.
Historic Site Preservation: The Contractor must exercise extreme caution when working near historic structures, artifacts, and landscape features. Any damage to historic property or cultural resources caused by the Contractor shall be repaired or restored to the original condition at the Contractor’s expense and to the satisfaction of the COR.
Safety and Security: All Contractor personnel shall adhere to all NPS times while on park property.
Cleanliness: The work area shall be cleaned and all debris removed at the end of each workday. The site must be left in a safe, neat, and orderly condition upon completion of the project.