This is a Statement of Work (SOW) for the replacement of Mitsubishi mini-split HVAC systems at the Chickamauga/Chattanooga National Military Park under PMIS 314962A. The National Park Service (NPS) contracting officer will oversee this Firm-Fixed-Price contract requiring the procurement, installation, and testing of eighteen (8) new Mitsubishi 230V, 25 amp outdoor condenser units and eighteen (18) new Mitsubishi WR series high-wall indoor units with approved equivalent models of appropriate sizing to match or exceed existing unit performance. The contractor must be NATE (North American Technician Excellence) certified with a minimum of two years of field experience, recertifying every two years; non-NATE certified contractors will be automatically disqualified. Specific equipment models are identified: five condensers (5-MXZ4A30, 2-MUZ-A17NA, 1-MXZ-4A36NA) and mini-splits (7-MSZ-A09NA, 6-MSZ-A17NA, 5-MSZ-A12NA).
The contractor shall execute removal of existing units with EPA-compliant refrigerant evacuation, safe disconnection of refrigerant line sets and wiring, and off-site disposal of all removed equipment at an approved facility with costs included in the fixed price. Installation requires new refrigerant line sets with UV-resistant covers, low-voltage control wiring, digital remote thermostats, and properly sloped condensate drain lines. System start-up and commissioning must verify refrigerant charge, system pressures, and full operational testing of all eighteen zones in heating and cooling modes. Required deliverables include signed start-up and commissioning reports, manufacturer warranties and O&M manuals in hard copy and digital formats, minimum one-hour training for NPS personnel on thermostat operation and troubleshooting, final project record drawings with redlines, and proof of proper refrigerant disposal. The work shall be completed within a specified number of calendar days from the Notice to Proceed during normal park administrative hours (7:00 AM–4:00 PM, Monday–Friday) unless otherwise approved by the NPS Contracting Officer's Representative. A detailed Accident Prevention Plan and Construction Schedule must be submitted for approval prior to work commencement. Best Value Analysis will be used for award, and the contractor must exercise extreme caution regarding historic site preservation with responsibility for any damage restoration at the contractor's expense.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5126Q0016_Amd_0002.pdf | ||
| Attachment_0009__Questions_and_Answers_0002.pdf | ||
| Attachment_0007__Revised_Statement_of_Work_0001.pdf | ||
| Sol_140P5126Q0016_Amd_0001.pdf | ||
| Attachment_0006__Revised_Solicitation_Clause_0001.pdf | ||
| Attachment_0001__Solicitation_Clause.pdf | ||
| Sol_140P5126Q0016.pdf | ||
| Attachment_0004__Price_Schedule.docx | DOCX document | |
| Attachment_0002__Statement_of_Work.pdf | ||
| Attachment_0005__Past_Performance.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) for HVAC System Replacement-PMIS 314962A
Project Title: Mitsubishi Mini-Split HVAC System Replacement Location:
Chickamauga/Chattanooga National Military Park (CHCH) Contracting Agency: National Park Service (NPS)
1.0 Introduction and Background
This Statement of Work (SOW) de nes the requirements for a contractor to provide all necessary labor, materials, equipment, and supervision to remove and replace existing Mitsubishi mini-split HVAC systems with new, comparable, and energy-e icient units within designated facilities at the Chickamauga/Chattanooga National Military Park.
2.0 Scope of Work
The contractor shall be NATE (North American Technician Excellence) certi ed which entails at least 2 years eld experience, that they recertify every 2 years to stay knowledgeable on new, e icient refrigerant technologies.
More information about NATE under 2.1. The Contractor shall perform a complete, turnkey replacement of the existing HVAC equipment as detailed in Section 3.0. This is a Firm-Fixed-Price contract, and the Contractor is solely responsible for ensuring the new systems are installed, tested, and operational in compliance with all applicable federal, state, and local codes, and the Secretary of the Interior's Standards for Historic Preservation where applicable.
2.1 NATE Certi ed Technicians are required because many manufacturers only validate warranties if the tech is NATE, Installation results in better energy e iciency and lower utility bills, they follow precise speci cations for less callbacks, and they are certi ed to handle speci c chemicals (refrigerants) safely and in compliance with EPA. NATE certi ed techs ensure the highest quality of work.
2.2 The contractor must be certi ed NATE by reasons above and disquali ed by same reasons above. Non-NATE certi ed will be automatic disquali cation.
2.3 Best Value Analysis will be used for this contract.
3.0 Speci c Tasks and Technical Requirements
The Contractor shall execute the following tasks:
3.1 Equipment Procurement and Mobilization
• Procure eighteen (8) new Mitsubishi 230V, 25 amp, condensers outdoor units and eighteen (18) new Mitsubishi WR series mini-splits high-wall indoor units (or approved equivalent models) of appropriate sizing and capacity to match or exceed the performance of the units being replaced.
• Site visit is HIGHLY RECOMMENDED since it is a historical building.
• Con rm all equipment is new, currently manufactured, and registered for the full manufacturer’s warranty upon installation.
• Develop and submit a detailed Accident Prevention Plan (APP) and Construction Schedule to the NPS Contracting O icer's Representative (COR) for approval prior to the start of work.
3.2 Removal and Disposal of Existing Units
• Safely decommission and evacuate refrigerant from eighteen (8) existing outdoor units and eighteen (18) existing indoor units in compliance with EPA regulations, including proper handling of refrigerants.
• Carefully disconnect and remove all associated refrigerant line sets, wiring, and condensate lines.
• Dispose of all removed equipment, components, and construction debris o -site at an approved recycling or disposal facility. The disposal cost shall be included in the xed price.
3.3 New System Installation
• Install eighteen (8) new Mitsubishi outdoor units in the same general locations as the units being replaced, ensuring proper mounting and vibration isolation.
• Remove condensers and mini splits and replace them with same.
• Condensers- 5-MXZ4A30, 2- MUZ-A17NA, 1- MXZ-4A36NA
• Mini Splits- 7- MSZ-A09NA, 6- MSZ-A17NA, 5- MSZ-A12NA
• Install eighteen (18) new Mitsubishi high-wall indoor units in the exact same interior locations as the units being replaced.
• Install new refrigerant line sets for all new systems. All line sets shall be insulated and protected using new UV-resistant line set covers/raceways to match the aesthetic of the building exterior.
• Install new low-voltage control wiring between all indoor and outdoor units, routed discreetly and protected in raceways.
• Install new digital remote thermostats for each zone, programmed and calibrated for optimal performance.
• Install new, properly sloped condensate drain lines for all indoor units, ensuring compliance with local drainage codes and park aesthetics.
3.4 System Start-up and Testing
• Charge the new systems with the appropriate refrigerant type and quantity.
• Perform a comprehensive system startup and commissioning, including veri cation of proper electrical power, voltage, and amperage draw.
• Conduct a full operational test of all eighteen (18) zones in both heating and cooling modes to ensure the systems meet manufacturer speci cations and are fully functional.
4.0 Deliverables
The Contractor shall provide the following to the COR before nal payment:
• A. Final signed Start-up and Commissioning Reports for all eight outdoor units, including refrigerant charge, system pressures, and test results.
• B. Warranties and Manufacturer Documentation (hard copy and digital format), including Operation and Maintenance (O&M) manuals, for all new equipment.
• C. Training for NPS personnel (minimum one hour) on the operation, programming, and basic troubleshooting of the new digital remote thermostats and indoor units.
• D. Final Project Record Drawings (Redlines) showing the nal location of all major components and line set routing.
• E. Proof of proper refrigerant disposal.
5.0 Government Furnished Property (GFP)
The Government (NPS) will provide access to the work areas and existing electrical power at the building service panels. No other equipment or materials will be provided by the Government.
6.0 Schedule and Place of Performance
• Place of Performance: Chickamauga/Chattanooga National Military Park, various designated facilities. The speci c addresses will be provided in the Notice to Proceed (NTP).
• Period of Performance: The work shall be completed within [Insert Number] calendar days from the issuance of the Notice to Proceed
(NTP).
• Work Hours: Work shall generally be performed during normal park administrative hours (e.g., 7:00 AM – 4:00 PM, Monday through Friday) unless other times are approved in advance by the COR to minimize disruption to park operations and visitors.
7.0 Special Conditions and Requirements
• Historic Site Preservation: The Contractor must exercise extreme caution when working near historic structures, artifacts, and landscape features. Any damage to historic property or cultural resources caused by the Contractor shall be repaired or restored to the original condition at the Contractor’s expense and to the satisfaction of the COR.
• Safety and Security: All Contractor personnel shall adhere to all NPS safety and security guidelines and wear appropriate identi cation at all times while on park property.
• Cleanliness: The work area shall be cleaned and all debris removed at the end of each workday. The site must be left in a safe, neat, and orderly condition upon completion of the project.