| GOVERNMENT FORMAT PRICING MODEL - INSTRUCTIONS | |
| General | |
| 1 | The Prime Offeror shall complete this Government Format Pricing Model (GFPM). |
| 2 | Do not manipulate any cells other than those highlighted in yellow. |
| Base and Option TAB | |
| 1 | Offeror input is required in all cells highlighted in yellow. |
| 2 | Offeror shall input offeror name in cell A2 of the Year 1 worksheet. |
| 3 | Offerors shall enter a single fully burdened labor rate (FBLR) for each labor category and ordering period combination. FBLRs shall be a blend of prime and subcontractor (if applicable) loaded labor rates . Hours are pre-populated. |
| 4 | The offeror may apply indirect expenses to the Travel plug figures in cell D15 but shall explain how the indirect expenses were developed, i.e., Overhead, G&A. The total evaluated Travel price will be the sum of the Travel plug figure and any proposed indirect Travel costs. No profit/fee shall be applied to the Travel plug figure or incorporated into the indirect rate for Travel. Any proposed indirect rates applied to the Travel plug figure shall be a fixed ceiling rate for each applicable period of performance. All proposed indirect rates shall be in accordance with the offeror’s normal accounting practices and procedures. The Offeror will provide in a separate document or in an added worksheet a description of how the Travel indirect rate was developed. If the offeror's intent is to propose "zero" indirect expenses then enter "0" in cell D15 and state this intention in your cost narrative. |
| 6 | All extended values and total prices are automatically calculated. |
| 7 | The Total Evaluated Price is contained in cell E17 labelled "Total Evaluated Price " for each Performance Period worksheet. |
Labor Catagory Descriptions
| GVSC Title | SOW Equivalent | Description |
| GS-15 | Senior Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | A technical or administrative leader with advanced expertise in one or more subject matter areas, attained through advanced education and years of related technical experience |
| GS-14 | Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | A technical or administrative leader with expertise in one or more subject matter areas, attained through advanced education and years of related technical experience |
| GS-13 | Senior Project Scientist/Engineer/Analyst/Manager or Subject Matter Expert | Possesses the ability to undertake and resolve complex projects through research, analysis, and the application of judgment developed from previous experience. Addresses problems that are difficult to define, require unconventional or novel approaches, and require sophisticated analytical techniques. |
| GS-12 | Project Scientist/Engineer/Analyst/Manager | Possesses the ability to undertake and resolve projects through research, analysis, and the application of judgment. Addresses problems that are difficult to define, require unconventional or novel approaches, and require analytical techniques. |
| GS-13 Cat II | Senior Scientist/Engineer/Analyst | Possesses the ability to undertake and resolve difficult and highly complex projects through research, analysis, and the application of judgment developed from previous experience. Addresses problems that are difficult to define, require unconventional or novel approaches, and require sophisticated analytical techniques. |
| GS-11 | Scientist/Engineer/Analyst | Possesses the ability to undertake and resolve complex projects through research, analysis, and the application of judgment developed from previous experience. Addresses problems that are difficult to define, require unconventional or novel approaches, and require sophisticated analytical techniques. |
Summary
| Government Format Pricing Model | ||||||||||
| OFFEROR NAME | ||||||||||
| Summary | ||||||||||
| Labor Category | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | |||||
| FBLR | Labor Cost | FBLR | Labor Cost | FBLR | Labor Cost | FBLR | Labor Cost | FBLR | Labor Cost | |
| Senior Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Senior Project Scientist/Engineer/Analyst/Manager or Subject Matter Expert | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Project Scientist/Engineer/Analyst/Manager | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Senior Scientist/Engineer/Analyst | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Scientist/Engineer/Analyst | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Total | $ - 0 | Labor Total | $ - 0 | Labor Total | $ - 0 | Labor Total | $ - 0 | Labor Total | $ - 0 | |
| Travel - Not to Exceed (NTE) | ||||||||||
| Travel NTE | 71,000.00 | 73,130.00 | 75,323.90 | 77,583.62 | 79,911.13 | |||||
| Proposed Indirect Rate % / Cost | 0.00% | - 0 | 0.00% | - 0 | 0.00% | - 0 | 0.00% | - 0 | 0.00% | - 0 |
| Travel Total | 71,000.00 | Travel Total | 73,130.00 | Travel Total | 75,323.90 | Travel Total | 77,583.62 | Travel Total | 79,911.13 |
| Total Price | $ 71,000.00 | Total Price | $ 73,130.00 | Total Price | $ 75,323.90 | Total Price | $ 77,583.62 | Total Price | $ 79,911.13 | |
| Total Evaluated Price | $ 376,948.64 |
Year 1
| Government Format Pricing Model | ||||
| OFFEROR NAME | ||||
| Year 1 | ||||
| Labor | ||||
| Labor Category | Annual Hours | FTE | Proposed FBLR | Labor Cost |
| Senior Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Senior Project Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 956 | 0.5 | $ - 0 | |
| Project Scientist/Engineer/Analyst/Manager | 956 | 0.5 | $ - 0 | |
| Senior Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Labor Total | $ - 0 | |||
| Travel - Not to Exceed (NTE) | ||||
| Travel NTE | $ 71,000 | |||
| Proposed Indirect Rate % | $ - 0 | |||
| Travel Total | $71,000 | |||
| Total Evaluated Price | $71,000 |
Year 2
| Government Format Pricing Model | ||||
| OFFEROR NAME | ||||
| Year 2 | ||||
| Labor | ||||
| Labor Category | Annual Hours | FTE | Proposed FBLR | Labor Cost |
| Senior Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Senior Project Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 956 | 0.5 | $ - 0 | |
| Project Scientist/Engineer/Analyst/Manager | 956 | 0.5 | $ - 0 | |
| Senior Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Labor Total | $ - 0 | |||
| Travel - Not to Exceed (NTE) | ||||
| Travel NTE | $ 73,130 | |||
| Proposed Indirect Rate % | $ - 0 | |||
| Travel Total | $73,130 | |||
| Total Evaluated Price | $73,130 |
Year 3
| Government Format Pricing Model | ||||
| OFFEROR NAME | ||||
| Year 3 | ||||
| Labor | ||||
| Labor Category | Annual Hours | FTE | Proposed FBLR | Labor Cost |
| Senior Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Senior Project Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 956 | 0.5 | $ - 0 | |
| Project Scientist/Engineer/Analyst/Manager | 956 | 0.5 | $ - 0 | |
| Senior Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Labor Total | $ - 0 | |||
| Travel - Not to Exceed (NTE) | ||||
| Travel NTE | $ 75,324 | |||
| Proposed Indirect Rate % | $ - 0 | |||
| Travel Total | $75,324 | |||
| Total Evaluated Price | $75,324 |
Year 4
| Government Format Pricing Model | ||||
| OFFEROR NAME | ||||
| Year 4 | ||||
| Labor | ||||
| Labor Category | Annual Hours | FTE | Proposed FBLR | Labor Cost |
| Senior Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Senior Project Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 956 | 0.5 | $ - 0 | |
| Project Scientist/Engineer/Analyst/Manager | 956 | 0.5 | $ - 0 | |
| Senior Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Labor Total | $ - 0 | |||
| Travel - Not to Exceed (NTE) | ||||
| Travel NTE | $ 77,584 | |||
| Proposed Indirect Rate % | $ - 0 | |||
| Travel Total | $77,584 | |||
| Total Evaluated Price | $77,584 |
Year 5
| Government Format Pricing Model | ||||
| OFFEROR NAME | ||||
| Year 5 | ||||
| Labor | ||||
| Labor Category | Annual Hours | FTE | Proposed FBLR | Labor Cost |
| Senior Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Program Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 1912 | 1 | $ - 0 | |
| Senior Project Scientist/Engineer/Analyst/Manager or Subject Matter Expert | 956 | 0.5 | $ - 0 | |
| Project Scientist/Engineer/Analyst/Manager | 956 | 0.5 | $ - 0 | |
| Senior Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Scientist/Engineer/Analyst | 956 | 0.5 | $ - 0 | |
| Labor Total | $ - 0 | |||
| Travel - Not to Exceed (NTE) | ||||
| Travel NTE | $ 79,911 | |||
| Proposed Indirect Rate % | $ - 0 | |||
| Travel Total | $79,911 | |||
| Total Evaluated Price | $79,911 |