This document is a data table presenting Department of Defense (DoD) statistics on change order definitization timelines for construction contracts.
The table tracks 234 change order proposals that were definitized during contract performance, categorized by the time elapsed between receipt of an adequate change order definitization proposal and final definitization. The data shows that definitization timeframes vary significantly: 41 proposals were definitized within 30 days or less, 35 proposals between 31 to 60 days, 24 proposals between 61 to 90 days, 48 proposals between 91 to 180 days, 47 proposals between 181 to 365 days, and 39 proposals exceeding 365 days. Additionally, 146 change order proposals were not definitized until after completion of contract performance, when all undefinitized equitable adjustments accumulated during performance were addressed through a single contract modification. This data illustrates the range of definitization practices within DoD construction contracts, with a substantial portion of adjustments remaining undefinitized until final contract closeout.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Selected Agency: DoD
Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts
Number of Change Order Proposals definitized under Construction Contracts
30 days or less 41
31 to 60 days 35
61 to 90 days 24
91 to 180 days 48
181 to 365 days 47
Greater than 365 days 39
After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance