ATTACH_4_-_Construction_Schedule.docx

DOCX document 21 KB Posted

Attached to
GCI Pollyanna #2 Acid Mine Drainage Remediation Pr
Solicitation number
140S0326R0001
Issued by

About this file

This is a construction schedule attachment for the GCI Pollyanna #2 Acid Mine Drainage Remediation Project, a Department of the Interior Office of Surface Mining Reclamation and Enforcement solicitation (140S0326R0001). The schedule outlines a 15-day construction timeline for implementing acid mine drainage remediation infrastructure at the Pollyanna #2 site.

The construction activities include mobilization, site clearing and grubbing, pond dewatering, and installation of water treatment components such as HDPE 8-inch collection pipe, concrete flow spreaders, seep steps, and high calcium limestone (AASHTO #3) dosing systems. The work also encompasses construction of a concrete vault for a 10-inch dosing siphon and a settling/oxidation pond with appurtenances including two 4-inch outlet pipes, two 2.5/3-inch orifice plates, and baffle curtains. The schedule includes 50 feet of 6-foot-tall wetland seeding and planting, permanent erosion control fencing installation, and equipment removal. The document appears to be an incomplete template allowing contractors to add additional pages as needed for detailed scheduling and phasing of construction activities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date:

Feature
Item
Day:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Pollyanna 2
Mobilization

Clearing and Grubbing

Pond Dewatering

Earth Fill / Dirt Work

HDPE 8” Collection Pipe

Concrete for Flow Spreader(s), Seep Step, and Installment

High Calcium Limestone (AASHTO #3)

Dosing Siphon Concrete Vault

10” Dosing Siphon

Settling/Oxy Pond Appurtenances: Two 4-inch Outlet Pipes, two 2.5/3-inch Orifice Plates, & Baffle Curtains 6: 50ft long x 3ft tall

Wetland Seeding and Planting

Permanent Erosion Control

Fencing (5-wire)

Removal of Equipment and Associated Tanks

Earth Fill / Dirt Work

HDPE 8” Collection Pipe

Concrete for Flow Spreader(s), Seep Step, and Installment

Add more pages as seem fit