This file is a detailed rate sheet and price schedule for a District 17 Environmental Remediation Services Multiple Award Task Order Contract (MATOC) for the U.S. Coast Guard. The document outlines a comprehensive pricing structure for various professional environmental service disciplines, including Program Managers, Project Managers, Environmental Scientists, Engineers, Specialists, and technical support roles. The pricing template includes base rates, overhead, profit percentages, and a proposed escalation rate of 3.50% across multiple optional ordering periods spanning up to six years.

The contract covers multiple tasks related to environmental services, specifically for the Eldred Rock Site Characterization and District 17 Environmental Support, with contract line items (CLINs) covering project management, planning documents, field work, reporting, and environmental program support. Key tasks include site characterization work plans, long-term monitoring, environmental due diligence audits, site compliance reporting, and potential divestiture support. The solicitation is issued by the Department of Homeland Security's U.S. Coast Guard for environmental remediation services in the Arctic Region (formally District 17), structured as an Indefinite Delivery Indefinite Quantity (IDIQ) contract.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEED PROJECT PRICE SCHEDULE

SEED PROJECT: ELDRED ROCK SITE CHARACTERIZATION AND DISTRICT 17 ENVIRONMENTAL SUPPORT
CONTRACT LINE ITEM NUMBER (CLIN)DESCRIPTIONUNITQTYPRICE
0001Task 1 – Project Management and MeetingsLump Sum (LS)1$ - 0
0002Task 2 – Planning Documents
0002AATask 2.1 – Eldred Rock Site Characterization Work PlanLS1$ - 0
0002ABTask 2.2 – USCG Light Station Review and LTM Work PlanLS1$ - 0
0003Task 3 – Field Work
0003AATask 3.1 – Eldred Rock Field WorkLS1$ - 0
0003ABTask 3.2 – USCG Light Station LTM Field WorkLS1$ - 0
0004Task 4 – Reporting and Environmental Program Support
0004AATask 4.1 – Eldred Rock Site Characterization ReportLS1$ - 0
0004ABTask 4.2 – Long Term Monitoring (LTM) ReportsLS1$ - 0
0004ACTask 4.3 – Environmental Due Diligence Audit (EDDA) UpdateLS1$ - 0
0004ADTask 4.4 – Site Compliance Report (SCR) UpdateLS1$ - 0
0004AETask 4.5 – Eldred Rock Divestiture SupportLS1$ - 0
0004AETask 4.6 – Memorandum of Agreement (optional) *See BelowLS1$ - 0
TOTAL PROPOSED PRICE:$ - 0
Notes:
1. Do not edit grey cells.
2. Edit white cells.
3. Fill in RATE SHEET
* CLIN 0004AE will be evaluated IAW 52.217-5 (BASE PLUS ALL OPTIONS) and executed under 52.217-7 OPTION FOR INCREASE QUANTITY - SEPARATLY PRICED LINE ITEMS with a 60 DAY FILL IN.

RATE SHEET

DISTRICT 17 ENVIRONMENTAL IDIQ RATE FIRM FIXED PRICE SHEET FOR ALL YEARS
Instructions:

1. Fill in the White Cells include Escalation Rate, Base Rate, Firm Overhead (OH), Firm Profit, and Prime Markup on Subcontractors.

2. Add Disciplines as necessary.

3. Rates are locked in on the Base Year and used to calculate out years.

CLIN 0001: BASE ORDERING PERIOD (1 YEAR) SLIN 0001AA: Base Year PricingCLIN 1001: Optional Ordering Period 1: SLIN 0001AA YEAR 1CLIN 1001: Optional Ordering Period 1: SLIN 0001AB YEAR 2CLIN 1001: Optional Ordering Period 1: SLIN 0001AC YEAR 3CLIN 1002: Option Ordering Period 2: SLIN 1002AA YEAR 1CLIN 1002: Option Ordering Period 2: SLIN 1002AB YEAR 2CLIN 1002: Option Ordering Period 2: SLIN 1002AC YEAR 3
Proposed Escalation Rate:3.50%Escalation Rate:0%3.50%Escalation Rate:3.50%Escalation Rate:3.50%Escalation Rate:3.50%Escalation Rate:3.50%Escalation Rate:
DisciplineBase Rate ($/hr)Firm OH (%)Firm Profit (%)Prime Markup (%)Fully Burdened Rate ($/hr)HoursTotal Proposed RateDisciplineBase Rate ($/hr)Firm OH (%)Firm Profit (%)Prime Markup (%)Fully Burdened Rate ($/hr)HoursTotal Proposed RateDisciplineBase Rate ($/hr)Firm OH (%)Firm Profit (%)Prime Markup (%)Fully Burdened Rate ($/hr)HoursTotal Proposed RateDisciplineBase Rate ($/hr)Firm OH (%)Firm Profit (%)Prime Markup (%)Fully Burdened Rate ($/hr)HoursTotal Proposed RateDisciplineBase Rate ($/hr)Firm OH (%)Firm Profit (%)Prime Markup (%)Fully Burdened Rate ($/hr)HoursTotal Proposed RateDisciplineBase Rate ($/hr)Firm OH (%)Firm Profit (%)Prime Markup (%)Fully Burdened Rate ($/hr)HoursTotal Proposed RateDisciplineBase Rate ($/hr)
Program Manager$ 92.5010.00%185.00%0.00%$ 272.88$ - 0Program Manager$ 95.7410.00%185.00%0.00%$ 282.43$ - 0Program Manager$ 99.0910.00%185.00%0.00%$ 292.31$ - 0Program Manager$ 102.5610.00%185.00%0.00%$ 302.54$ - 0Program Manager$ 106.1510.00%185.00%0.00%$ 313.13$ - 0Program Manager$ 109.8610.00%185.00%0.00%$ 324.09$ - 0Program Manager$ 113.71
Project/Task Manager - Prime$ 2.000.00%0.00%0.00%$ 2.00$ - 0Project/Task Manager - Prime$ 2.070.00%0.00%0.00%$ 2.07$ - 0Project/Task Manager - Prime$ 2.140.00%0.00%0.00%$ 2.14$ - 0Project/Task Manager - Prime$ 2.220.00%0.00%0.00%$ 2.22$ - 0Project/Task Manager - Prime$ 2.300.00%0.00%0.00%$ 2.30$ - 0Project/Task Manager - Prime$ 2.380.00%0.00%0.00%$ 2.38$ - 0Project/Task Manager - Prime$ 2.46
Project/Task Manager - Sub$ 3.0012.00%10.00%5.00%$ 3.81$ - 0Project/Task Manager - Sub$ 3.1012.00%10.00%5.00%$ 3.94$ - 0Project/Task Manager - Sub$ 3.2112.00%10.00%5.00%$ 4.08$ - 0Project/Task Manager - Sub$ 3.3312.00%10.00%5.00%$ 4.22$ - 0Project/Task Manager - Sub$ 3.4412.00%10.00%5.00%$ 4.37$ - 0Project/Task Manager - Sub$ 3.5612.00%10.00%5.00%$ 4.53$ - 0Project/Task Manager - Sub$ 3.69
Environmental Scientist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Scientist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Scientist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Scientist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Scientist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Scientist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Scientist$ - 00.00%0.00%0.00%$ - 0$ - 0
Environmental Engineer$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Engineer$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Engineer$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Engineer$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Engineer$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Engineer$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Engineer$ - 00.00%0.00%0.00%$ - 0$ - 0
Environmental Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Environmental Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0
Regulatory Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Regulatory Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Regulatory Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Regulatory Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Regulatory Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Regulatory Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0Regulatory Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0
Site Superintendent$ - 00.00%0.00%0.00%$ - 0$ - 0Site Superintendent$ - 00.00%0.00%0.00%$ - 0$ - 0Site Superintendent$ - 00.00%0.00%0.00%$ - 0$ - 0Site Superintendent$ - 00.00%0.00%0.00%$ - 0$ - 0Site Superintendent$ - 00.00%0.00%0.00%$ - 0$ - 0Site Superintendent$ - 00.00%0.00%0.00%$ - 0$ - 0Site Superintendent$ - 00.00%0.00%0.00%$ - 0$ - 0
Site Safety & Health Officer$ - 00.00%0.00%0.00%$ - 0$ - 0Site Safety & Health Officer$ - 00.00%0.00%0.00%$ - 0$ - 0Site Safety & Health Officer$ - 00.00%0.00%0.00%$ - 0$ - 0Site Safety & Health Officer$ - 00.00%0.00%0.00%$ - 0$ - 0Site Safety & Health Officer$ - 00.00%0.00%0.00%$ - 0$ - 0Site Safety & Health Officer$ - 00.00%0.00%0.00%$ - 0$ - 0Site Safety & Health Officer$ - 00.00%0.00%0.00%$ - 0$ - 0
Field Technician - Environmental$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Environmental$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Environmental$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Environmental$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Environmental$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Environmental$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Environmental$ - 00.00%0.00%0.00%$ - 0$ - 0
Field Technician - Mechanical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Mechanical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Mechanical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Mechanical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Mechanical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Mechanical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Mechanical$ - 00.00%0.00%0.00%$ - 0$ - 0
Field Technician - Electrical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Electrical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Electrical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Electrical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Electrical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Electrical$ - 00.00%0.00%0.00%$ - 0$ - 0Field Technician - Electrical$ - 00.00%0.00%0.00%$ - 0$ - 0
QA/QC Manager (Site or Office)$ - 00.00%0.00%0.00%$ - 0$ - 0QA/QC Manager (Site or Office)$ - 00.00%0.00%0.00%$ - 0$ - 0QA/QC Manager (Site or Office)$ - 00.00%0.00%0.00%$ - 0$ - 0QA/QC Manager (Site or Office)$ - 00.00%0.00%0.00%$ - 0$ - 0QA/QC Manager (Site or Office)$ - 00.00%0.00%0.00%$ - 0$ - 0QA/QC Manager (Site or Office)$ - 00.00%0.00%0.00%$ - 0$ - 0QA/QC Manager (Site or Office)$ - 00.00%0.00%0.00%$ - 0$ - 0
Geologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0
Geologist$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist$ - 00.00%0.00%0.00%$ - 0$ - 0Geologist$ - 00.00%0.00%0.00%$ - 0$ - 0
Chemist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0
Chemist$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist$ - 00.00%0.00%0.00%$ - 0$ - 0Chemist$ - 00.00%0.00%0.00%$ - 0$ - 0
$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0
Biologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0
Biologist$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist$ - 00.00%0.00%0.00%$ - 0$ - 0Biologist$ - 00.00%0.00%0.00%$ - 0$ - 0
$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0
GIS Specailist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specailist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specailist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specailist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specailist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specailist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specailist, Sr.$ - 00.00%0.00%0.00%$ - 0$ - 0
GIS Specalist Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specalist Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specalist Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specalist Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specalist Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specalist Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0GIS Specalist Specialist$ - 00.00%0.00%0.00%$ - 0$ - 0
Data Manager$ - 00.00%0.00%0.00%$ - 0$ - 0Data Manager$ - 00.00%0.00%0.00%$ - 0$ - 0Data Manager$ - 00.00%0.00%0.00%$ - 0$ - 0Data Manager$ - 00.00%0.00%0.00%$ - 0$ - 0Data Manager$ - 00.00%0.00%0.00%$ - 0$ - 0Data Manager$ - 00.00%0.00%0.00%$ - 0$ - 0Data Manager$ - 00.00%0.00%0.00%$ - 0$ - 0
Clerical Support$ - 00.00%0.00%0.00%$ - 0$ - 0Clerical Support$ - 00.00%0.00%0.00%$ - 0$ - 0Clerical Support$ - 00.00%0.00%0.00%$ - 0$ - 0Clerical Support$ - 00.00%0.00%0.00%$ - 0$ - 0Clerical Support$ - 00.00%0.00%0.00%$ - 0$ - 0Clerical Support$ - 00.00%0.00%0.00%$ - 0$ - 0Clerical Support$ - 00.00%0.00%0.00%$ - 0$ - 0
Technical Writer$ - 00.00%0.00%0.00%$ - 0$ - 0Technical Writer$ - 00.00%0.00%0.00%$ - 0$ - 0Technical Writer$ - 00.00%0.00%0.00%$ - 0$ - 0Technical Writer$ - 00.00%0.00%0.00%$ - 0$ - 0Technical Writer$ - 00.00%0.00%0.00%$ - 0$ - 0Technical Writer$ - 00.00%0.00%0.00%$ - 0$ - 0Technical Writer$ - 00.00%0.00%0.00%$ - 0$ - 0
Cost Estimator$ - 00.00%0.00%0.00%$ - 0$ - 0Cost Estimator$ - 00.00%0.00%0.00%$ - 0$ - 0Cost Estimator$ - 00.00%0.00%0.00%$ - 0$ - 0Cost Estimator$ - 00.00%0.00%0.00%$ - 0$ - 0Cost Estimator$ - 00.00%0.00%0.00%$ - 0$ - 0Cost Estimator$ - 00.00%0.00%0.00%$ - 0$ - 0Cost Estimator$ - 00.00%0.00%0.00%$ - 0$ - 0
Scheduler$ - 00.00%0.00%0.00%$ - 0$ - 0Scheduler$ - 00.00%0.00%0.00%$ - 0$ - 0Scheduler$ - 00.00%0.00%0.00%$ - 0$ - 0Scheduler$ - 00.00%0.00%0.00%$ - 0$ - 0Scheduler$ - 00.00%0.00%0.00%$ - 0$ - 0Scheduler$ - 00.00%0.00%0.00%$ - 0$ - 0Scheduler$ - 00.00%0.00%0.00%$ - 0$ - 0
Asbestos Work$ - 00.00%0.00%0.00%$ - 0$ - 0Asbestos Work$ - 00.00%0.00%0.00%$ - 0$ - 0Asbestos Work$ - 00.00%0.00%0.00%$ - 0$ - 0Asbestos Work$ - 00.00%0.00%0.00%$ - 0$ - 0Asbestos Work$ - 00.00%0.00%0.00%$ - 0$ - 0Asbestos Work$ - 00.00%0.00%0.00%$ - 0$ - 0Asbestos Work$ - 00.00%0.00%0.00%$ - 0$ - 0
Hazardous Material Handler$ - 00.00%0.00%0.00%$ - 0$ - 0Hazardous Material Handler$ - 00.00%0.00%0.00%$ - 0$ - 0Hazardous Material Handler$ - 00.00%0.00%0.00%$ - 0$ - 0Hazardous Material Handler$ - 00.00%0.00%0.00%$ - 0$ - 0Hazardous Material Handler$ - 00.00%0.00%0.00%$ - 0$ - 0Hazardous Material Handler$ - 00.00%0.00%0.00%$ - 0$ - 0Hazardous Material Handler$ - 00.00%0.00%0.00%$ - 0$ - 0
Administrative Assistant$ - 00.00%0.00%0.00%$ - 0$ - 0Administrative Assistant$ - 00.00%0.00%0.00%$ - 0$ - 0Administrative Assistant$ - 00.00%0.00%0.00%$ - 0$ - 0Administrative Assistant$ - 00.00%0.00%0.00%$ - 0$ - 0Administrative Assistant$ - 00.00%0.00%0.00%$ - 0$ - 0Administrative Assistant$ - 00.00%0.00%0.00%$ - 0$ - 0Administrative Assistant$ - 00.00%0.00%0.00%$ - 0$ - 0
Laborer: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0
Laborer: Group 2$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 2$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 2$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 2$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 2$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 2$ - 00.00%0.00%0.00%$ - 0$ - 0Laborer: Group 2$ - 00.00%0.00%0.00%$ - 0$ - 0
Power Equipment Operation: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Power Equipment Operation: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Power Equipment Operation: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Power Equipment Operation: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Power Equipment Operation: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Power Equipment Operation: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0Power Equipment Operation: Group 1$ - 00.00%0.00%0.00%$ - 0$ - 0
Electrician Technician$ - 00.00%0.00%0.00%$ - 0$ - 0Electrician Technician$ - 00.00%0.00%0.00%$ - 0$ - 0Electrician Technician$ - 00.00%0.00%0.00%$ - 0$ - 0Electrician Technician$ - 00.00%0.00%0.00%$ - 0$ - 0Electrician Technician$ - 00.00%0.00%0.00%$ - 0$ - 0Electrician Technician$ - 00.00%0.00%0.00%$ - 0$ - 0Electrician Technician$ - 00.00%0.00%0.00%$ - 0$ - 0
Carpenter$ - 00.00%0.00%0.00%$ - 0$ - 0Carpenter$ - 00.00%0.00%0.00%$ - 0$ - 0Carpenter$ - 00.00%0.00%0.00%$ - 0$ - 0Carpenter$ - 00.00%0.00%0.00%$ - 0$ - 0Carpenter$ - 00.00%0.00%0.00%$ - 0$ - 0Carpenter$ - 00.00%0.00%0.00%$ - 0$ - 0Carpenter$ - 00.00%0.00%0.00%$ - 0$ - 0
Plumber$ - 00.00%0.00%0.00%$ - 0$ - 0Plumber$ - 00.00%0.00%0.00%$ - 0$ - 0Plumber$ - 00.00%0.00%0.00%$ - 0$ - 0Plumber$ - 00.00%0.00%0.00%$ - 0$ - 0Plumber$ - 00.00%0.00%0.00%$ - 0$ - 0Plumber$ - 00.00%0.00%0.00%$ - 0$ - 0Plumber$ - 00.00%0.00%0.00%$ - 0$ - 0
$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0
$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0
$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0
$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0$ - 00.00%0.00%0.00%$ - 0$ - 0