This Mission-Essential Contractor Services Plan details the continuity requirements for Recycle Center Management Services at FE Warren AFB, Wyoming. The document, prepared for the 90th Missile Wing, outlines how the contractor will maintain essential services during a crisis, with two primary Contract Line Item Numbers (CLINs): Recycle Center Management and Pallet Disposal, each priced per the existing contract and set for a 12-month period. The plan requires the contractor to develop procedures for personnel and resource acquisition, address challenges like pandemics, establish communication and notification protocols, and maintain operations under adverse conditions. Pricing will remain consistent with the current contract, and the services will continue until the Contracting Officer directs cessation of the plan.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3

FA461325XXXXX

Mission-Essential Contractor Services Plan for

Recycle Center Management

Services

FE WARREN AFB, WY

31 March 2025

FA461325XXXXX

1. INTRODUCTION. This Mission-Essential Contractor Services Plan has been developed in accordance with DFARS Clause 252.237-7023 – Continuation of Essential Contractor Services.

It addresses how [Insert Name of Contractor] will continue providing the mission-essential Recycle Center Management services identified in the solicitation during periods of crisis, upon notification by the Contracting Officer (CO) to activate the plan.

2. OBJECTIVE. In support of the 90th Missile Wing, the objective is to provide mission-essential Recycle Center Management services for FE Warren AFB, WY during a crisis. The essential contractor services are identified below and will be performed at the prices in the contract at the time the plan is activated.

3. CONTRACTOR PROCEDURES. Contractor MUST answer the following in this plan:

a. Identify provisions made for the acquisition of essential personnel and resources, if necessary, for continuity of operations for up to 30 days or until normal operations can be resumed;

1)

b. How you will address challenges associated with maintaining essential contractor services during an extended event, such as a pandemic that occurs in repeated waves (i.e. list efforts taken to maintain sufficient level of staff and ensure adequate supplies);

1)

c. How you will address time lapse associated with the initiation of the acquisition of essential personnel and resources and their actual availability on site (i.e. discuss actions/time needed to get personnel and resources in place, actions to expedite the process, ability to work extended hours if base access is restricted);

1)

d. How you will address components, processes, and requirements for the identification, training, and preparedness of personnel who are capable of relocating to alternate facilities or performing work from home (i.e. list actions that can be performed remotely, contract manager duty location, etc);

1)

e. How you will establish an alert and notification procedure for mobilizing identified “essential contractor service” personnel (i.e. explain if alert/notification will be made after Government direction and means of notification, etc); and

1)

FA461325XXXXX

f. The approach you will use for communicating expectations to contractor employees regarding their roles and responsibilities during a crisis (i.e. explain means of communication, use of Quality Control Plan, checklists, or other additional duties).

1)

g. Identify how you will conduct plant operations to overcome adverse conditions and situations, such as significant weather situations, employee illnesses, or unexpected vacancies (i.e. explain means of maintaining operations if weather limits travel or loss of employees).

1)

4. PRICING. The mission-essential Recycle Center Management services are identified in paragraph 5 and will be paid at the prices in the contract at the time the Plan is activated. The prices will also be used as the basis for any equitable adjustments resulting from the activation of the Plan.

5. Mission-Essential Contractor Services.

CLIN

Description of Service Qty Unit Unit Price Total Price

X001 Recycle Center Management 12 MO Per the

Contract Per the

Contract

X002 Pallet Disposal 12 MO Per the

Contract Per the

Contract

6. QUALITY CONTROL PLAN (QCP). The contractor shall utilize its own internal QCP during the performance of this plan.

7. DEACTIVATION OF PLAN. [Insert Name of Contractor] shall perform the mission-essential contractor services during a crisis until notified by the CO to cease performance of the Plan.

SIGNATURE PAGE

Contractor Point of Contact:_______________________________________

Phone Number(s):_______________________________________

Email Address:_______________________________________

FA461325XXXXX

Date:_____________________________

File details come from the government source that posted it. Updated .