Attach 1- SXHT 17-1023 Technical Specs.pdf

PDF 5 MB Posted

Attached to
Repairs to Building 423, 3rd Floor (North, Center & West Side)
Solicitation number
FA252120B0003
Issued by

About this file

This document is a solicitation for a firm-fixed-price construction contract for repairs to Building 423 at Patrick Air Force Base in Florida. The project scope involves renovating the third floor north, center, and west wings and is estimated to cost between $5 million and $8 million. This is a Women-Owned Small Business set-aside requiring that offerors meet this criteria to be deemed responsive and eligible for award. Offerors must be able to financially support both the procurement and bonding requirements. Funds are not presently available as this is a fiscal year 2020 requirement, so no award will be made until funds are allocated. All bid prices and costs must remain valid until September 30, 2020. Only electronic bids submitted through the System for Award Management database will be accepted. A pre-bid site visit is scheduled for May 19, 2020 at 10:00 AM Eastern Time. The soliciting agency is the Department of the Air Force Space Command.

View the file

Other files

File Type Posted
Amendment 006 FA252120B00030006.pdf PDF
Attach 9A Bid Schedule Revision 1.pdf PDF
Amendment 005 FA252120B00030005.pdf PDF
Attach 1A- SXHT 17-1023 Revised Technical Specs.pdf PDF
Attach 3B Ref Ceiling Demo Due to Fire Main ONLY.pdf PDF
Attach 3A SXHT 17-1023 Revised Drawings.pdf PDF
Solicitation Amendment 004 FA252120B00030004.pdf PDF
Attach 8A Pre-Site Visit Attendance.pdf PDF
Attach 14- Interior Design Package.pdf PDF
Attach 11A -Consolidated Answers to Questions.pdf PDF
Attach 13 COMM grounding-n-bonding Reference.pdf PDF
Amendment 003 FA252120B0003003.pdf PDF
Attach 12 Asbestos Report and Floor Views.pdf PDF
Amendment 002 FA252120B00030002.pdf PDF
Amendment 001 FA252120B00030001.pdf PDF
Attach 6- Installation Access List Revision 1.pdf PDF
Attach 8- Pre-Site Visit RuleofEngagement.pdf PDF
Attach 9 Bid Schedule.doc DOC document
Solicitation - FA252120B0003.pdf PDF
Attach 6- Installation Access List.pdf PDF
Attach 5- SHXT 17-1023 Furniture Package.pdf PDF
Attach 3- SXHT 17-1023 Drawings.pdf PDF
Attach 10 Submittal Register.xls XLS spreadsheet
Attach 11- Q and A Template.doc DOC document
Attach 7 WD FL20200001 27Mar2020.pdf PDF
Attach 4 - SXHT 17-1023 HAZ Waste.doc DOC document
Attach 2- SXHT 17-1023 SOW.doc DOC document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PATRICK AIR FORCE BASE

Technical Specifications for

SXHT 17-1023

Repair 3rd Floor North and West Wings, Bldg. 423

100% Submittal

DATE: June 2018

RRAAEEIISS

Range Architect-Engineer Inspection Services

Repair 3rd Floor North and West Wings, Bldg. 423 SXHT 17-1023

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00.00 30 SUMMARY OF WORK

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 82 13.00 98 ASBESTOS ABATEMENT

02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD OR MERCURY

DIVISION 03 - CONCRETE

03 01 30.71 CONCRETE REHABILITATION

DIVISION 05 - METALS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

08 14 00 WOOD DOORS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

DIVISION 09 - FINISHES

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

SECTION TOC Page 1 6/21/2018

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

DIVISION 26 - ELECTRICAL

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 51 00 INTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00.00 30 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

ATTACHMENT I

ASBESTOS SURVEY RESULTS/HAZARDOUS MATERIALS TESTING RESULTS

-- End of Project Table of Contents --

SECTION TOC Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00.00 30

SUMMARY OF WORK

10/14

PART 1 GENERAL

1.1 SUMMARY

1.2 PROJECT DESCRIPTION

1.2.1 Structural

1.2.2 Architectural

1.2.3 Mechanical/Plumbing

1.2.4 Electrical

1.2.5 Telecommunications

1.2.6 Fire Protection

1.2.7 Special Construction

1.3 REFERENCES

1.4 SUBMITTALS

1.5 CONTRACT DRAWINGS

1.5.1 Layout of Work and Elevations

1.6 WORK SCHEDULING

1.6.1 Requirements

1.7 OCCUPANCY OF PREMISES/ACCESS REQUIREMENTS

1.7.1 Facility Contents

1.7.1.1 Responsibilities

1.7.1.2 Maintain Clean Work Areas

1.7.1.3 Damage To Existing Equipment

1.7.1.4 New Material and Construction Equipment

1.7.2 Construction Area Access And Control

1.7.2.1 Access and Control Requirements

1.7.3 Vehicle Parking

1.7.3.1 Requirements

1.8 STORAGE, TRANSPORTATION AND PROTECTION

1.8.1 Storage

1.8.2 Protection

1.8.3 Transportation

1.8.4 Hazardous Materials

1.8.5 Site Protection Plan

1.9 ON-SITE PERMITS

1.9.1 Utility Outage Requests And Connection Requests

1.9.1.1 Requirements

1.9.2 Protection of Work

1.9.3 Burn Permits

1.10 SALVAGE AND DISPOSAL OF MATERIAL AND EQUIPMENT

1.10.1 Removal

1.10.2 Housekeeping

1.10.3 Salvage of Material And Equipment

1.10.3.1 Salvage Items

1.10.4 Waste Disposal

1.10.5 Cleanup

1.10.6 Salvage And Disposal Record Keeping

SECTION 01 11 00.00 30 Page 1

1.11 RADIO FREQUENCY MANAGEMENT PROCEDURES

1.12 COMMUNICATION SECURITY

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 ACCESS REQUIREMENTS

3.1.1 Construction Site Requirement

3.2 PAFB VEHICLE INSPECTION

3.3 PAFB DELIVERIES

3.3.1 Non-Hazardous Deliveries

3.3.2 Hazardous Deliveries

3.4 RESPONSIBILITIES

3.5 HOISTING AND LIFTING

3.5.1 Lifting Operation Plan

3.6 QUALITY CONTROL

3.6.1 Licenses

3.6.2 Quality Control Manager

3.6.3 Government Inspection/Approval

3.6.4 Inspection Files

3.7 SUPERINTENDENT

3.8 CONSTRUCTION SCHEDULING REQUIREMENTS

3.8.1 Contractor Coordination Meetings

3.8.2 On-Site Construction Sequence

-- End of Section Table of Contents --

SECTION 01 11 00.00 30 Page 2

SECTION 01 11 00.00 30

SUMMARY OF WORK

10/14

PART 1 GENERAL

1.1 SUMMARY

The work to be performed under this project is located at Patrick Air Force Base. Patrick Air Force Base is located approximately three miles south of Cocoa Beach on State Road A1A.

The work to be performed under this project consists of providing the labor, equipment, and materials to renovate the third floor North, Center and West wings of building 423, as indicated herein, in associated Contract Drawings and Design Analysis.

Contractor shall provide construction phasing as indicated in drawings.

Contractor shall provide temporary dust barrier walls to avoid migration of dust and debris from the area of construction to occupied spaces.

1.2 PROJECT DESCRIPTION

1.2.1 Structural

Provide structural reinforcement for hurricane resistant windows, as indicated in drawings.

1.2.2 Architectural

Provide interior wall, furniture, and floor wall and ceiling finish demolition of 3rd floor, north, center, & west wings of B423 as indicated in drawings. Demolition shall remove existing assemblies, except at the existing 4 utility cores that will maintain the existing construction assemblies unless noted otherwise in the contract drawings, and west wing computer room that will be modified as indicated in drawings. Demolition will also include the removal of 2 glass block windows, sills and trim.

Replace with 4x16, hurricane resistant windows (or other infill material) at (2) locations as appropriate.

Provide new "open office concept" area to include new room layout, new finish assemblies and new utilities, ready for new systems furniture.

Provide new interior paint, new treads, risers, new stringer covers and new landings in all stairwells as well as new handrails to match existing in north west and center west stair tower.

Extend Computer Room wall assembly to bottom of existing roof structure,as indicated in wall legend details. Provide new paint finish at both sides of the Computer Room walls.

Contractor shall coordinate proposed installation of furniture with electrical and comm installation. Contractor shall coordinate the storage and delivery of free standing and systems furniture, with the Contracting Officer and Furniture manufacturer. Furniture delivery and installation shall accommodate each phase of construction.

Replace roll up door on ground level mechanical room in the north courtyard

SECTION 01 11 00.00 30 Page 36/21/2018

Contractor shall coordinate installation of interior finish assemblies with interior design notebooks and with Contracting Officer.

The contractor shall mitigate differences in floor levels as well as wall surfaces to provide a continuous subsurface for new construction.

1.2.3 Mechanical/Plumbing

Install 5 Constant Volume Air Handling Units and Make-up Air Units with Variable Air Volume Air Handlers, motorized operating valves, thermowell, chilled water return piping connections, flow control valves, isolation valves, and all associated appurtenances.

Contractor to install two (2) mini split ductless air handling units. One

(1) located in the North Wing Comm. Room and One (1) in the Central Wing Comm. Room. Contractor to install condensate drains (terminate 6" above grade-see dwg. M 401). Contractor shall mount the condensing units on the stairwell tower see drawing M 401.

Install various Terminal Boxes (VAV) within the newly zoned area with associated thermostats and control wiring

Demolish all existing supply air ductwork, dampers, supports and air distribution devices and replace with new galvanized steel ductwork with insulation, new supports, new dampers, new flexible ducting, new Titus ceiling diffusers and return air grilles.

Install new exhaust system for restrooms

Install cooling for corridors and return air grilles

Install new Outside Air motorized and manual dampers and fire/smoke detection

Install chilled water supply and return pipe stop in order for units not being replaced but kept functioning for spaces not in contract if necessary

Install new condensate lines for new air handling units (pipe to existing floor drains)

Existing heating hot water supply and return piping within each Mechanical room to remain.

Demolish existing return air duct and outside air duct and replace with new within the Mechanical rooms.

Install Variable Frequency Drives for new VAV system.

Install mechanical digital controls, optimized sequence of operations, ventilation control, and emergency shutoff.

For the existing Air handling Unit(labeled AHU-1) which currently serves an area that is not in this contract, but shares a Make-Up Air Unit with an existing AHU to be demolished under this contract, contractor shall install a conditioned outside air duct. The duct, indicated on drawing M-412, shall be utilized to serve the existing air handler(AHU-1).

SECTION 01 11 00.00 30 Page 4

1.2.4 Electrical

Remove existing & install new electrical equipment as indicated on the drawings. Remove existing & install new lighting fixtures as indicated on the drawings. Disconnect & remove power to existing HVAC equipment. Provide power to new HVAC equipment. Remove existing fire alarm & detection system. Install new fire alarm and mass notification system & connect to existing fire alarm mass notification panel on the 1st floor. Test new fire alarm & mass notification system. Connect existing generator feed to new electrical panel supplying the secure computer server room. Conduct generator outage test.

1.2.5 Telecommunications

Remove existing and install new telecommunications equipment as indicated on the drawings. Disconnect and remove existing cabling from office areas to communications cabinets. Provide new communication outlets for LAN and phones. Provide new CAT 6 communication cables from communications room to each office as shown on the drawings. Terminate all cables in RJ45 jacks and test.

1.2.6 Fire Protection

Extend the existing fire sprinkler system into the area of work as identified in the design documents. The new fire sprinkler system will be supplied by an existing floor control valve located on the third floor.

The fire sprinkler piping will be routed above the ceiling space and sprinkler heads will be located at the ceiling.

1.2.7 Special Construction

The contractor shall remove and abate hazardous materials, including asbestos, lead and other heavy metals, where encountered and as indicated on the plans prior to any building and/or equipment removal and demolition.

Asbestos removal and abatement shall be completed as per Section 02 82 13.00 98, Asbestos Abatement. Lead removal and abatement shall be completed as per Section 02 82 33.13 20, Removal/Control and Disposal of Paint With Lead or Mercury.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 101 (2018; TIA 18-1) Life Safety Code

U.S. AIR FORCE (USAF)

AFI 33-580 (2013) Spectrum Management

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

SECTION 01 11 00.00 30 Page 5 submittals not having a "G" designation are for Contractor Quality Control information only. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES in sufficient detail to show full compliance with the specification:

SD-01 Preconstruction Submittals

Submit the following items to the Contracting Officer:

Lifting Operation Plan;G

Utility Outage Requests;G

Connection Requests;G

Air Force Form 3952 (AF 3952), Chemical/Hazardous Material Request Authorization;G (including all paint)

SOLID WASTE DISPOSAL DIVERSION TRACKING;G

Premises/Access Plan;G

Storage Area Request;G

Superintendent Contact and Qualifications;G

1.5 CONTRACT DRAWINGS

See Drawing Index for list of project drawings.

Contract drawings, maps, and specifications will be furnished to the Contractor either hard copy or electronic at the Government's discretion.

Reference publications will not be furnished.

Contractor shall immediately check furnished drawings and notify the Contracting Officer of any discrepancies.

The drawings indicate the general location and arrangement of existing conditions. Field measurements may be necessary to determine the size and quantity of materials. Conditions which are obvious/visible or which should be reasonably anticipated by the Contractor on inspection will not be considered under the Differing Site Conditions clause of this contract.

1.5.1 Layout of Work and Elevations

Dimensions and elevations indicated in the layout of work shall be verified by the Contractor. Discrepancies between the drawings, specifications and/or existing conditions shall be referred to the Contracting Officer in writing, for review, before the affected work is performed. Failure to make notification shall place the responsibility upon the Contractor to carry out the work in a satisfactory and workmanlike manner.

1.6 WORK SCHEDULING

Work Schedules for all on-site activities must be reviewed and approved by the Contracting Officer prior to start of the project; and all activities coordinated with the Contracting Officer once work has begun. Due to the critical nature of the work location, all work pertaining to this contract shall be completed with minimal disruption to the operation of the facility

SECTION 01 11 00.00 30 Page 6 functions, including the Command Suite.

Contractor shall allow for non-access days where construction activity is prohibited due to hazardous operations or launch activity. When possible, the Government will provide 24 hour notification each time the restrictions are invoked.

1.6.1 Requirements

Working hours will normally range between the hours of 7:30 AM and 4:00 PM (0730-1600) excluding Saturdays, Sundays and Federal Holidays. If work must be done during periods other than above, additional Government inspection and Range Support personnel may be required. Notification must be given to the Contracting Officer five working days in advance of intention to work during other periods to allow assignment of additional inspection forces when the Contracting Officer determines that they are reasonably available. If such support is reasonably available, the Contracting Officer may authorize work to be performed during periods other than normal duty hours/days. Work beyond normal hours/days may be required for major utility outages. Its is to the government's discretion to request copies of contractor inspection records for periods worked on holidays and weekends (FAR 52.246-12 Inspection of Construction).

No construction work shall take place over the Christmas/New Year holiday period. This period will start one full work day before the Federal Christmas holiday and end the first work day after the Federal New Year Holiday. The Contractor may request to work during this time at the discretion of the Contracting Officer, however no base support will be available.

1.7 OCCUPANCY OF PREMISES/ACCESS REQUIREMENTS

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area. Contractor shall post warning signs in accordance with OSHA requirements.

Before work is started, the Contractor shall submit a Premises/Access Plan to the Contracting Officer or Representative for approval. The plan shall include a sequence of procedures, means of access, space plan for storage of materials and equipment, and use of approaches, corridors, and stairways.

This plan must comply with NFPA 101 requirements that all exits and exit access must be maintained at all times. Base Fire Department is required to approve any deviations which affect the exiting or exit access from the building.

1.7.1 Facility Contents

1.7.1.1 Responsibilities

The schedule of work shall be closely coordinated with the Contracting Officer. User shall remove mission critical equipment, prior to start of work. Unless otherwise stated, remove all furniture, equipment, curtains, drapes, pictures, blackboards, etc., as required to perform the work. Any movable or fixed furniture, equipment, carpet, etc., remaining in the work area shall be covered and protected from damage. All relocated items shall also be protected from damage throughout the construction period. After completion of work and prior to final acceptance, replace removed items in

SECTION 01 11 00.00 30 Page 7 their original location.

The entire area will not be available to the Contractor at one time. The following phases of work and procedures are required:

a. Sequence of construction phasing shall be based upon selected Areas of Work as indicated in drawings.

Demolition of critical facility systems mechanical, electrical, etc. shall not be started until replacement equipment is on site.

1.7.1.2 Maintain Clean Work Areas

All work areas shall be kept clean at all times. Contractor shall prevent introduction of dirt or dust into areas adjacent to the work areas. All materials, tools and equipment shall be thoroughly cleaned prior to being brought into the work areas or adjacent areas.

1.7.1.3 Damage To Existing Equipment

Any damage must be reported to the Contracting Officer immediately. Damage to existing materials, equipments, systems, or properties occurring from Contractor activities or neglect, shall, at the sole discretion of the Contracting Officer, be repaired or replaced by the Contractor at no cost to the Federal Government.

1.7.1.4 New Material and Construction Equipment

Only material and construction equipment designated for performance of contract work may be stored at the construction site or located in Government-controlled warehouses or shop facilities.

1.7.2 Construction Area Access And Control

1.7.2.1 Access and Control Requirements

Exclusive use or control of any area will not be allowed as the Government must have access to all areas at all times. All work must be scheduled around operational constraints.

1.7.3 Vehicle Parking

1.7.3.1 Requirements

Job and support vehicles for workers will be parked in designated parking areas within reasonable access to the worksite. All vehicle operators must comply with all traffic laws including mandatory seat belt usage, speed limits and hauling restrictions. Contractor shall be responsible for repairing or replacing any facility/grounds damaged areas.

1.8 STORAGE, TRANSPORTATION AND PROTECTION

1.8.1 Storage

At Government discretion, Contractor may be assigned a storage area upon submitting written Storage Area Request to the Contracting Officer.

Contractor's Storage Area Request shall indicate dimensions of trailer, size of storage area, and utilities required. All trailers shall be in good and safe condition. Storage space is normally co-located with

SECTION 01 11 00.00 30 Page 8 construction site, at the Contracting Officer's discretion. Storage areas may require fence and screening as required by Government. Contractor shall secure storage areas during inclement weather situation.

Contractor is to submit a Work Order Management System (WOMS) through CE to request a telephone number and line for their office trailer. Commercial Internet service is available through local Internet service provider at contractor cost.

1.8.2 Protection

Store and protect products in accordance with manufacturer's instructions.

Store products with seals, labels intact and legible. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to the product. Products acceptable for exterior storage shall be on sloped supports above ground. Contractor shall not use swales, drainage ditches, or any other storm water permitted area to store materials or equipment. If swales, drainage ditches or any other storm water permitted areas must be used for storage, Contractor must get special permission from Contracting Officer.

1.8.3 Transportation

Transport and handle products in accordance with manufacturer's instructions. Promptly inspect shipments to ensure the products comply with requirements, quantities are correct, and products are undamaged.

Protect products subject to deterioration with impervious sheet covering.

Provide ventilation to prevent condensation and degradation of products.

Store loose granular materials on solid flat surfaces in a well drained area. Prevent mixing with foreign materials.

1.8.4 Hazardous Materials

Submit an Air Force Form 3952 (AF 3952), Chemical/Hazardous Material Request Authorization if hazardous materials & petroleum product will used on site. Hazardous Materials & petroleum product containers shall be stored on an impervious surface with containment. Incompatible materials shall be segregated and have separate containment systems. Additional HAZMAT requirements are provided in Section 01 57 19 TEMPORARY ENVIRONMENTAL

CONTROLS.

1.8.5 Site Protection Plan

Structures, utilities, sidewalks, pavements, and other facilities immediately adjacent to excavations shall be protected against damage.

Contractor shall comply with "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements" and is required to protect areas adjacent to the construction site.

1.9 ON-SITE PERMITS

1.9.1 Utility Outage Requests And Connection Requests

Work shall be scheduled to hold outages to a minimum.

Utility outages and Connection Requests required during the execution of work that affect existing systems shall be arranged at the convenience of the Government, which may require scheduling outside of the regular working hours or on weekends, at no additional cost to the Government.

SECTION 01 11 00.00 30 Page 9

Each Utility Outage and Connection Requests shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.9.1.1 Requirements

A written request for a utilities outage (electricity, communication, water, compressed air, gas, steam, air conditioning, fire detection and suppression systems, etc.) must be submitted to the Contracting Officer at least 14 calendar days in advance of the desired outage. Approval is required prior to scheduling any outage. All limitations noted on the approved outage authorization shall be carefully observed. A utilities outage without prior approval and coordination is prohibited.

Utility outages affecting fire alarm, fire detection, fire suppression, fire pumps and water supplies to fire protection systems greater than 4 hours will require a fire watch.

A fire watch must provide a constant 24/7 human presence. The person performing the fire watch uses human senses (sight, hearing, smell, touch, and voice communication) to detect and report the presence of smoke, fire.

The person conducting the fire watch shall physically inspect the entire area covered every hour and document the condition, i.e. fire safe, or not fire safe. In the event the smoke or fire are discovered, the person performing the fire watch shall immediately evacuate the building and report to the dispatch center by dialing 911 or 321-494-0911 if calling from a cell phone.

Since many systems are critical to facility operations, the number and duration of utility outages shall be kept to an absolute minimum. All work effort shall be coordinated and sufficient manpower, materials, and equipment shall be provided to complete the work within the authorized outage window.

Existing utility services may be interrupted only when approved by the Contracting Officer. The interruption shall be scheduled at a time of minimum demand on the utility, convenient to the Government. Outages on weekends, holidays, or evenings shall be performed at no additional cost to the Government.

Contractor shall make all necessary arrangements to schedule and provide connections to existing utilities and to cause minimum interruption to system operation. All temporary utility hook-ups and disconnects shall be made by the Contractor.

If the Contractor fails to comply with a scheduled outage, the cost to reschedule the outage will be deducted from the final contract payment.

1.9.2 Protection of Work

All construction work requires a Work Clearance Request, AF Form 103. This permit is processed by the Government and provided to the Contractor. It is required prior to the start of any construction at the project site and must be posted in a conspicuous location on site during all construction activities.

Contractor shall obtain (from technical representative), prepare, and properly complete "Base Civil Engineering Work Clearance Request" AF Form

SECTION 01 11 00.00 30 Page 10

103. Prior to submitting 103 for review and approval, contractor shall mark in white paint all locations requiring utility locates and a commercial utility locate ticket number must be obtained by calling SUNSHINE at 1-800-432-4770. Contractor shall provide coordination for location of buried structures and utility lines before beginning any work involving digging/excavation. Contact the Government Technical Representative to schedule locates prior to any excavation. The Technical representative shall be the first and the last to coordinate on the AF Form 103.

After excavation permit has been obtained and prior to any excavating, verify with Cape Support (853-5211) that there are no "Critical Days" that would prevent excavation.

Contractor shall temporarily halt any machine excavation work or other surface penetration when approaching within 5 feet of the existing utility line until the Contractor has exposed the utility line by hand excavation to fix its location.

1.9.3 Burn Permits

Burn permits are required for any spark,flame, or welding activity. Burn Permits shall be obtained thru PAFB Fire Department (494-7642).

Permits shall be posted at a conspicuous location in the construction area.

Burning of trash or rubbish is not permitted on any USAF facility.

1.10 SALVAGE AND DISPOSAL OF MATERIAL AND EQUIPMENT

1.10.1 Removal

Remove and/or relocate only those materials or items of equipment specifically indicated in the drawings and specifications. Removal operations shall be performed in such a manner that adjacent areas, installed equipment, or existing utilities are not damaged. Repair all openings that occur due to removal or demolition operations to match adjacent, existing surfaces. Any damage incurred during removal operations shall be repaired at no additional cost to the Government.

1.10.2 Housekeeping

Sufficient personnel and equipment shall be provided to ensure compliance with all housekeeping requirements. Work will not be allowed in those areas that do not comply with the requirements of Section 14.C of EM 385-1-1.

Job sites are to be kept clean on an ongoing, daily basis. All areas are to be thoroughly cleaned prior to leaving the jobsite at completion of project work.

1.10.3 Salvage of Material And Equipment

All salvageable materials or items to be removed shall remain the property of the Federal Government. Salvageable items are listed below in the paragraph entitled, "Salvage Items". Salvageable items shall be transported to and deposited at the Defense Logistics Agency Office - Disposition Services (DLA) at Jacksonville, Florida at the contractor's expense.

Salvageable material must be segregated and separated into categories

SECTION 01 11 00.00 30 Page 11 before transport. Material shall be palletized or moveable by forklift (maximum 10,000 lbs). For material that is not palletized, it will be the responsibility of the Contractor to provide labor support for material removal.

Deliveries to DLA shall be scheduled through the Contracting Officer a minimum of 72 hours in advance. All salvageable items delivered to DLA shall be accompanied by a properly prepared DD Form 1348. This form will be furnished by the Contracting Officer. A signed copy by DLA reflecting the turn in materials shall be furnished to the Contracting Officer.

Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.

Material to be salvaged and reinstalled by the Contractor shall be protected during removal and stored to prevent damage.

For reference purposes salvageable is defined as: items, material, equipment which can be refitted, reworked, and restored and put to use or sold. The Contracting Officer shall have sole discretion as to determining whether any particular item is salvageable.

1.10.3.1 Salvage Items

As negotiated with the Contracting Officer.

1.10.4 Waste Disposal

Non-salvageable material and debris shall be removed from work areas and disposed of daily. Contractor shall dispose of C&D at a State approved disposal site.

Refer to Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS for further waste disposal and record keeping requirements.

1.10.5 Cleanup

All waste materials, except indicated salvaged items, generated by the construction shall be hauled off U.S. Government property at the end of each work day and deposited at a disposal site selected by the Contractor.

Disposal shall be in accordance with federal, state, county and city ordinances and at the expense of the Contractor.

Upon completion of the construction each day, the Contractor shall leave the work premises in a clean, neat and workmanlike condition, satisfactory to the Contracting Officer.

1.10.6 Salvage And Disposal Record Keeping

Contractor shall maintain and submit quarterly and at the completion of the project the SOLID WASTE DISPOSAL DIVERSION TRACKING form to the Contracting Officer of all materials removed from the job site. This inventory shall include waste materials disposed in landfills and materials reused on the job, sold for salvage and recycled.

SECTION 01 11 00.00 30 Page 12

1.11 RADIO FREQUENCY MANAGEMENT PROCEDURES

The following procedures shall be followed in obtaining radio frequency authorization:

The policy and procedures contained in AFI 33-580 shall be followed to obtain frequency allocation approval of electronic devices and USAF Radio Frequency Assignment.

1.12 COMMUNICATION SECURITY

Government telecommunications networks are continually subject to interception by hostile/unfriendly intelligent organizations. Therefore, the DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls from, or terminating at, DOD organizations. Contractor shall assume the responsibility for ensuring frequent dissemination of this information to all employees dealing with official DOD information.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 ACCESS REQUIREMENTS

3.1.1 Construction Site Requirement

All on-site project work is confined to non-restricted areas. That is, no restricted area badge shall be necessary to accomplish the on-site work.

However, normal access requirements into PAFB must still be accomplished.

3.2 PAFB VEHICLE INSPECTION

The Oversized Vehicle Search Area is located on State Road A1A approximately 1 mile north of Pineda Causeway. Manned Operating hours are scheduled from 0600-1700. For after hours access, call PAFB Security Forces at (321) 494-2000 to co-ordinate entry. Mandatory inspection is required for all: Commercial Vehicles, Tractor Trailers, Trailers, RVs and Boats. All other passenger vehicles will be turned away from this gate and are required to enter at either the Main Gate or South Gate. Allow ample time for inspections, especially for the critical delivery period of mixed concrete. The government will not be responsible for rejected batches, caused by Contractor delays. Advance coordination is highly recommended.

3.3 PAFB DELIVERIES

3.3.1 Non-Hazardous Deliveries

All deliveries of construction material and equipment to job sites (including cement trucks) shall use the PAFB Oversized Vehicle Search Area (located on State Road A1A approximately 1 mile north of Pineda Causeway) for access. The operating hours for the Oversized Vehicle Search Area are 0600-1700. After hours access shall be through the South Gate. The driver of each delivery vehicle and their passengers must have the following:

a. A valid photo ID; and

SECTION 01 11 00.00 30 Page 13

b. A valid bill of lading; and

c. A known delivery point on PAFB; and

d. An on-base or local phone number and POC to vouch for delivery

Only deliveries that can be verified will be allowed to proceed. Special deliveries, deliveries after normal business hours, or deliveries that cannot negotiate through the barricades must be coordinated in advance.

All delivery vehicles shall be inspected by Security Forces personnel prior to being allowed to proceed onto the installation.

3.3.2 Hazardous Deliveries

Deliveries of fuel, large volume of chemicals, or other hazardous materials shall comply with this section. All hazardous deliveries shall enter through the same gates as non-hazardous delivers and have the information required for non-hazardous deliveries (see subpart entitled "Non-Hazardous Deliveries" of this section). Only deliveries that can be verified will be allowed to proceed. In addition, hazardous deliveries must be scheduled a minimum of 48 hours in advance for escort by Security Forces to and from job site. Contractors shall contact the PAFB Security Forces at 321-494-2000 to arrange for hazardous delivery escorts. Deliveries that have not arranged in advance for Security Forces escorts will be turned away and must be re-scheduled.

3.4 RESPONSIBILITIES

The Government reserves the right to revoke badging authority, escort authority and/or base access privileges for any person, at any time and for any reason. Contractor understands that the Government has made every attempt to identify potential delays associated with background checks and badging requirements and those delays have been considered in the construction schedule. Delays resulting from the Contractor's failure to follow the badging guidelines above shall not be considered grounds for contract extension or compensation.

3.5 HOISTING AND LIFTING

3.5.1 Lifting Operation Plan

Contractor shall have a Lifting Operation Plan and procedure that is fully in accordance with the requirements of OSHA regulations, and shall include drawings/sketches of lifting slings, lifting equipment, and tag lines. The plan shall show weights, center of gravity, and clearances of load over entire lift. Plans shall have details showing any structural mounting of hoisting equipment on sheaves or structural steel, and shall show loading calculations on any such structural mounting showing forces, weights, turning moments, etc. A procedure shall accompany the drawings describing all lifting operations. Use spreader bars wherever necessary to prevent hoisting cables from contacting equipment/material.

3.6 QUALITY CONTROL

It is the Contractor's responsibility to provide, inspect and document the level of quality that has been established by all applicable standards, codes and guidelines. The Contractor shall use skilled workers, an adequate number of which are thoroughly trained and have a minimum of 3 years

SECTION 01 11 00.00 30 Page 14 experience in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for the proper performance of the work in each section of these specifications. Contractor shall submit Superintendent Contact and Qualifications to the Contracting Officer.

3.6.1 Licenses

Contractor or their subcontractors shall be licensed by the State of Florida or have an equivalent out-of-state license in all areas applicable to this contract or as otherwise stated elsewhere in this contract. Copies of licenses and certificates shall be provided to the Contracting Officer.

Asbestos Abatement Contractor shall be licensed by the State of Florida.

3.6.2 Quality Control Manager

The Quality Control Manager shall direct the execution of the Contractor's approved Quality Control Plan with exclusive responsibility for administration of the plan and inspections of work. The Quality Control Manager shall be available during normal duty within thirty (30) minutes after notification to meet with the Contracting Officer, or designated representative. The Quality Control Manager shall be a different individual than the project superintendent.

3.6.3 Government Inspection/Approval

When the Contractor considers that the work is acceptable to the Government and is complete, he/she shall inform the Contracting Officer, or designated representative, and the Government Project Manager that the work is complete and ready for inspections. In the event that the work is not acceptable, the Contractor shall record a list of items noted by the Government Project Manager, A subsequent inspection may take place in order to review the corrected items. The Government is not required to inspect all work.

3.6.4 Inspection Files

The Contractor shall be responsible for keeping inspection files for all projects. Files shall include on site records of all inspections conducted by the Contractor and the necessary corrective actions taken. Daily Reports shall be kept and made available to the Government throughout the contract performance period and for the period after completion until final settlement of any claims made under this contract.

3.7 SUPERINTENDENT

Provide name and qualifications and past experience for review. Designate a competent superintendent who shall have full authority to act for the Contractor and who shall be the primary contact with the Government until acceptance. Contractor's superintendent shall be at the job site at all times when work is taking place and shall have full authority to act for the Contractor.

3.8 CONSTRUCTION SCHEDULING REQUIREMENTS

3.8.1 Contractor Coordination Meetings

Contractor shall attend weekly project meetings, not to exceed 3 hours, scheduled by the Government. Contractor's Superintendent shall attend the scheduled coordination meetings. Subcontractor representatives shall

SECTION 01 11 00.00 30 Page 15 attend as required.

Discussion shall address the progress schedule, potential factors of delay, deficiencies, material delivery schedules, submittals, and safety issues.

3.8.2 On-Site Construction Sequence

The required work shall be performed in a sequence to minimize the time when potable water, air conditioning, panelboards, transformers, power supply, etc. are inoperative or out-of-service.

-- End of Section --

SECTION 01 11 00.00 30 Page 16

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal Descriptions (SD)

1.1.2 Approving Authority

1.1.3 Work

1.2 SUBMITTALS

1.3 SUBMITTAL CLASSIFICATION

1.3.1 Government Approved (G)

1.3.2 Sustainability Reporting Submittals (S)

1.4 PREPARATION

1.4.1 Transmittal Form

1.4.2 Source Drawings for Shop Drawings

1.4.2.1 Terms and Conditions

1.4.3 Electronic File Format

1.5 QUANTITY OF SUBMITTALS

1.5.1 Number of Copies of SD-02 Shop Drawings

1.5.2 Number of Copies of SD-03 Product Data and SD-08

Manufacturer's Instructions

1.5.3 Number of Samples SD-04 Samples

1.5.4 Number of Copies SD-05 Design Data and SD-07 Certificates

1.5.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's

Field Reports

1.5.6 Number of Copies of SD-10 Operation and Maintenance Data

1.5.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11

Closeout Submittals

1.6 INFORMATION ONLY SUBMITTALS

1.7 SUBMITTAL REGISTER

1.7.1 Use of Submittal Register

1.7.2 Contractor Use of Submittal Register

1.7.3 Approving Authority Use of Submittal Register

1.7.4 Copies Delivered to the Government

1.8 VARIATIONS

1.8.1 Considering Variations

1.8.2 Proposing Variations

1.8.3 Warranting that Variations are Compatible

1.8.4 Review Schedule Extension

1.9 SCHEDULING

1.10 GOVERNMENT APPROVING AUTHORITY

1.10.1 Review Notations

1.11 DISAPPROVED OR REJECTED SUBMITTALS

1.12 APPROVED/ACCEPTED SUBMITTALS

1.13 APPROVED SAMPLES

PART 2 PRODUCTS

SECTION 01 33 00 Page 1

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to

Certificates of insurance

Surety bonds

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Network Analysis Schedule (NAS)

Submittal register

Schedule of prices or Earned Value Report

Health and safety plan

Work plan

Quality Control(QC) plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

SECTION 01 33 00 Page 3

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

SECTION 01 33 00 Page 4

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (SDS) concerning impedances, hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.

Factory test reports.

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.1.2 Approving Authority

Office or designated person authorized to approve submittal.

SECTION 01 33 00 Page 5

1.1.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor QC approval.

Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

1.3 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.3.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."

1.3.2 Sustainability Reporting Submittals (S)

Submittals for Guiding Principle Validation (GPV) or Third Party Certification (TPC) are indicated with an "S" designation. Submit the information required by the technical sections that demonstrates compliance with the sustainable requirement, and for inclusion in the Sustainability eNotebook. A full submittal for an item may be provided under another SD;

however, for the "S" submittal, only provide that portion of the submittal that demonstrates compliance with the sustainable requirement. If the sustainable submittal does require Government Approval, it may be tagged under another SD with a "G."

Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout.

1.4 PREPARATION

1.4.1 Transmittal Form

1.4.2 Source Drawings for Shop Drawings

The entire set of Source Drawing files (DWG) will not be provided to the Contractor. Only those requested by the Contractor to prepare shop drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award.

1.4.2.1 Terms and Conditions

Data contained on these electronic files must not be used for any purpose

SECTION 01 33 00 Page 6 other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.

The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic Source Drawing files are not construction documents.

Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).

1.4.3 Electronic File Format

Provide submittals in electronic format, with the exception of material samples…