This is a Statement of Work (SOW) for the replacement of a deep-well pump system at the Tepee Work Center operated by the Black Hills National Forest, Hell Canyon Ranger District, under the U.S. Department of Agriculture (USDA).

The contractor shall replace the existing pump system for a 921-foot well by pulling the existing pump assembly, providing and installing a new 5 horsepower deep-well submersible pump suitable for installation at 820-880 feet depth, installing submersible pump cable (approximately 900-950 feet), torque arrestors, centralizers, and stainless-steel check valves, and providing a new pump control system including overload protection, surge protection, and pressure switch or optional VFD control. The contractor must also disinfect the well per standards, flush the system, perform bacteriological testing, conduct performance testing to verify required flow and pressure, and provide as-built documentation, test results, and warranty information. All labor, materials, equipment, testing, and documentation necessary to restore the well to proper working condition are contractor-provided. Key personnel must include a licensed pump installer, qualified electrician, and well technician experienced with deep-well installations exceeding 800 feet, with resumes demonstrating relevant experience and certifications. All travel costs to the well site are included in the contractor's quote with no separate reimbursement provided. Deliverables include a pump removal findings report (due first), submittals for pump, motor, and controls prior to installation, disinfection and bacteriological test results prior to opening water valves to dwellings, a final installation report and system performance test prior to final acceptance, and as-built drawings and warranty documentation within 10 days of final acceptance. The government will provide access to the well site, historical well logs if available, and operational data, with government personnel reviewing and approving all reports and submittals. All electronic deliverables must be Section 508 compliant, and all data, reports, and documentation generated become the property of the U.S. Government.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

BLACK HILLS NATIOANAL FOREST

HELL CANYON RANGER DISTRICT

TEPEE WORK CENTER WELL PUMP REPLACEMENT

STATEMENT OF WORK

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Project Insert Project Title Here

General Information

1.0 Scope of Work

This project includes the replacement of a deep-well pump system for a 921-foot well, including the installation of a 5 HP submersible pump and associated controls. The contractor shall provide all labor, materials, equipment, testing, and documentation necessary to restore the well to proper working condition.

2.0 Background

The existing pump system for the 921-foot well has exhibited signs of failure, diagnostic evaluation leads to the well pump has seized. Historical data for this site details how the previous well pump had been seized due to rust. The system utilizes a deep-well submersible pump, originally installed to support agricultural or facility water supply operations. This SOW outlines the requirements for assessment, repair, replacement, testing, and commissioning of a new 5 HP submersible pump system and associated surface controls.

Contractor Requirements

3.0 Technical Requirements / Tasks

The contractor shall perform the following tasks:

- Pull existing pump assembly and inspect drop pipe, cabling, and check valves.

- Provide and install a new 5 HP deep-well submersible pump suitable for installation at 820-880 feet depth based on water levels.

- Install submersible pump cable (approx. 900-950 feet), torque arrestors, centralizers, and stainless-steel check valves.

- Provide new pump control system, including overload protection, surge protection, and pressure switch or optional VFD control.

- Disinfect well per standards, flush system, and perform bacteriological testing.

- Conduct performance testing to verify required flow and pressure.

- Provide as-built documentation, test results, and warranty information.

4.0 Government Furnished

The government will provide access to the well site, historical well logs (if available), and any required operational data.

No government-furnished equipment is anticipated. Government personnel will review and approve all provided reports and submittals.

5.0 Deliverables / Schedule

Example 1 Key Deliverables

Item No. Deliverable Objective Due 1 Pump removal findings

Initial condition assessment and inspection report

Identify reasons for pump failure. First contract action item

2 Submittals for pump, motor, and controls.

FS verification of equipment, materials and installation certification credentials.

Prior to performing installation of equipment

3 Disinfection and bacteriological test results

Verification water is fit for consumption. Prior to opening water valves to dwellings.

4 Final installation report and system performance test

Verification of working system and operation instruction.

Prior to final acceptance and demobilization

5 As-built drawings and warranty documentation

Provide future reference and warranty information Within 10 days of final acceptance

6.0 Travel

Travel to the well site is required for assessment, pump removal, installation, and testing. All travel costs shall be included in the contractor’s quote. No separate reimbursement will be provided.

7.0 Contractor’s Key Personnel

Key personnel shall include a licensed pump installer, qualified electrician, and well technician experienced with deep-well installations exceeding 800 feet. Resumes shall demonstrate relevant experience and certifications.

8.0 Security Requirements

No security clearance is required. Contractor personnel shall check in with site representatives upon arrival and comply with all USDA site access requirements.

9.0 Data Rights

All data, reports, test results, and documentation generated under this contract become the property of the U.S.

Government.

10.0 Section 508 – Electronic and Information Technology Standards All electronic deliverables shall be Section 508 compliant, including readable PDFs and accessible text formats.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards