This is an Amendment One to a federal solicitation for the Tepee Work Center Well Pump Replacement project located at the Black Hills National Forest in Custer County, South Dakota. The solicitation number is 1240LT26Q0079, issued by the U.S. Department of Agriculture Forest Service.

Amendment One accelerates the project timeline with the following key changes: the deadline for submitting questions has been moved from June 16, 2026, to June 11, 2026, at 9:00 a.m. Central Daylight Time; the quote submission deadline has been advanced from July 15, 2026, to June 17, 2026, at 9:00 a.m. Central Daylight Time; and the Period of Performance has been adjusted from July 30 through August 31, 2026, to June 30 through August 15, 2026. A mandatory site visit has been incorporated on June 9, 2026, at 11:00 a.m. Central Daylight Time at the Tepee Work Center, 10623 Tepee Work Center Loop, Edgemont, SD 57735. Contractors must contact Richard Zacher at Richard.zacher@usda.gov or (605) 673-9222 by June 8, 2026, at noon Central Daylight Time to schedule the site visit. Questions and quote submissions should be directed to Janice King, Contract Specialist, at janice.king@usda.gov and Lucas Dahlman, Contracting Officer, at lucas.dahlman@usda.gov, with the email subject line "Tepee Work Center Well Pump Project Quote – 1240LT26Q0079." All other terms and conditions from the original solicitation remain unchanged.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF CHANGES

PROJECT: Tepee Work Center Well Pump Replacement Black Hills National Forest in Custer County, South Dakota

Solicitation Number: 1240LT26Q0079

AMENDMENTE ONE (Amend 0001):

The purpose of Amendment One (Amend 0001) is as follows:

1) to move the due date up for questions from June 16, 2026, at 9:00 a.m. Central Daylight Time to June 11, 2026, at 9:00 a.m. Central Daylight Time;

2) to move the due date up for quotes from the July 15, 2026, at 9:00 a.m. Central Daylight Time to June 17, 2026, at 9:00 a.m. Central Daylight Time;

3) to update the Period of Performance from July 30, 2026, through August 31, 2026, to June 30, 2026, through August 15, 2026;

4) to incorporate a Site Visit on June 9, 2026, at 11:00 a.m. Central Daylight Time. Contact Richard Zacher at Richard.zacher@usda.gov or by phone at (605)673-9222 by June 8, 2026, at noon Central Daylight Time to schedule a site visit,.

Site visit location: Tepee Work Center - 10623 Tepee Work Center Loop, Edgemont, SD 57735

5) All other terms and conditions remain the same.

Email addresses for submission of questions and quotes are as follows:

Janice King, Contract Specialist, at janice.king@usda.gov and Lucas Dahlman, Contracting Officer, at lucas.dahlman@usda.gov.

In the submission of your questions and quotes, include in the email’s subject line:

Tepee Work Center Well Pump Project Quote – 1240LT26Q0079.